TIDMSO4

RNS Number : 5473B

Salt Lake Potash Limited

31 January 2020

 
 31 January 2020   AIM/ASX Code: SO4 
 
 
 SALT LAKE POTASH LIMITED 
------------------------- 
 

DECEMBER 2019 QUARTERLY REPORT

Salt Lake Potash Limited (SO4 or the Company) is pleased to present its Quarterly Report for the period ending 31 December 2019. The Company is focussed on rapidly progressing development of its Lake Way SOP Project in Wiluna, Western Australia.

HIGHLIGHTS

Stage 2 On-Lake Construction progressing on schedule

-- Construction of evaporation ponds and trench infrastructure commenced in November 2019 with over 400ha of brine evaporation pond area nearing completion and 35km of brine abstraction trenches planned to complete

-- 225ha of brine evaporation ponds commissioned and in operation at 31 December 2019, and producing harvest salts for plant commissioning in Q4 2020

-- +12,000m of brine transfer piping installed with transfer pumping capacity of 600L/s to operate the brine evaporation ponds

Process Plant and Non-Process Infrastructure (NPI)

-- Progressed detailed engineering design for process plant and NPI enabling key contracts to be awarded

-- Process plant and NPI site clearance activities commence in January 2020

-- Procured key long lead process plant equipment and NPI packages, including:

o Accommodation Village Awarded

o Power Plant Awarded

o Reverse Osmosis Water Treatment Plant Awarded

o Wastewater Treatment Plant Awarded

o SOP and Schoenite Chrystallisers Awarded

o Communication System Awarded

o Concrete Package Awarded

Binding Offtake term sheets provide access to major global markets

-- SO4 has secured 220,000t per annum of offtake to industry leading partners representing 90% of total planned production for five and ten year terms from commencement of shipping in Q1 2021, with take or pay arrangements on product resale

-- Final purchase agreements based on the executed term sheets are well advanced with each of the offtake couterparties

-- Binding agreements support SO4's strategy of diversifying distribution across key global premium SOP seaborne markets

Native Title Land Access Agreement executed for Lake Way Project

-- SO4 and Tarlka Matuwa Piarku (Aboriginal Corporation) RNTBC (TMPAC) executed the Native Title Land Access Agreement (LAA) that covers the whole of the Lake Way Project

-- Execution of the LAA is a key milestone enabling the rapid development of the Project

Australian Institutional Placement and Debt Facility Extension

-- SO4 secured further funding for the Project via a placement and debt facility extension for total A$45.5 million

-- The Placement further strengthens SO4's share register with strong demand from new and existing institutional investors

-- Taurus continued their strong support of the Project by agreeing to extend the Stage 1 Facility by US$15 million (A$22 million) to a revised total of US$45 million ahead of finalising the main Project Development Facility

-- The combined additional funding ensures the Company is well placed to continue with the rapid development of the Lake Way Project, including the Stage 2 On-lake construction which is nearing completion and commencement of Process Plant and NPI construction in early 2020

-- A$57.6 million in combined available funding at 31 December 2019 ahead of anticipated finalisation of full Project funding in the coming months

Completion of BFS for the commercial scale development of the 245,000t per annum Lake Way SOP Project demonstrating outstanding economic returns

-- Exceptional economics with estimated project post-tax (real) NPV8 of A$479 million (pre-tax NPV8 of A$696 million) and post-tax IRR of 28% (pre-tax IRR 38%)

-- Steady state Project EBITDA of A$111 million annually and average annual after tax free cash flow of A$78 million (A$83 million during first 5 years)

-- Strong cash flow and low capital costs result in early payback period of 3.5 years

-- First quartile operating costs for global SOP producers with a C1 cash cost estimate of A$302/t (US$205/t)

-- Low development capital requirements of approximately A$254 million (US$173 million), including contingency of A$21 million, which is supported by the close proximity to infrastructure

Anticipated milestones in the coming months

-- Finalisation of full Project funding

-- Completion of Stage 2 on lake civil construction

-- Commencement of Process Plant and NPI site works

-- Execution of final purchase agreements based on the binding Offtake term sheets

-- Completion of the permanent on-site accommodation

-- Procurement of final long lead packages for the Process Plant and NPI in line with the advanced Project Schedule

lake way Project Overview

Lake Way is located in the Northern Goldfields Region of Western Australia, less than 15km south of Wiluna. The Lake Way Project tenements comprise approximately 386km(2) .

SO4 currently holds nine Mining Leases and seven Exploration Licences which cover the whole of the Lake Way surface and key strategic areas off-lake, including the extensive paleochannel and proposed process plant and village area. The Company has secured various Miscellaneous Licenses within the surrounding Lake Way area to support key infrastructure including process water bore fields, gas pipelines and access roads.

The recently completed transaction with Blackham Resources Ltd (Blackham), the owner of the adjacent Matilda-Wiluna Gold Operation, has secured access to process water rights in the Southern Borefield, as well as the acquisition of additional key tenements.

The October 2019 Bankable Feasibility Study for the commercial scale development of a 245,000t per annum Sulphate of Potash (SOP) operation at Lake Way demonstrates that the Project will generate outstanding returns with low operating costs and capital intensity.

SO4 has significantly advanced development of the Project, including completion of the Stage 1 125ha of evaporation ponds which are now filled with high grade brine (25kg/m(3) SOP) from the Williamson Pit and commencement of Stage 2 on-lake construction. This has provided the Company with additional insight into the critical evaporation processes and provided opportunities to further improve design and construction of the remaining evaporation pond network.

Bankable feasibility study

In October 2019, the Company reported the results of its Bankable Feasibility Study (BFS) for the commercial scale development of its 245,000t per annum Sulphate of Potash (SOP) project at Lake Way (Project).

Table 1: Key Project Metrics

 
 Element                                       Unit       Value 
=========================================  ===========  ======== 
 Physical 
=========================================  ===========  ======== 
 Life of mine                                 years        20 
=========================================  ===========  ======== 
 Annual SOP production                         tpa       245,000 
=========================================  ===========  ======== 
 Production plan 
=========================================  ===========  ======== 
 Ore reserve 
=========================================  ===========  ======== 
     Brine volume                               GL         474 
=========================================  ===========  ======== 
     Brine grade (LOM average)              kg/m(3) K      5.0 
=========================================  ===========  ======== 
     Contained potassium                        Mt         2.4 
=========================================  ===========  ======== 
 Production method(1) 
=========================================  ===========  ======== 
     Trenches                                   km         132 
=========================================  ===========  ======== 
     Bores                                     No.         18 
=========================================  ===========  ======== 
 Evaporation ponds 
=========================================  ===========  ======== 
     Halite ponds                               ha         686 
=========================================  ===========  ======== 
     Harvest ponds                              ha         96 
=========================================  ===========  ======== 
     Recovery of potassium from brine           %          91% 
=========================================  ===========  ======== 
 Process plant 
=========================================  ===========  ======== 
 Operating time                              hours/yr     7,600 
=========================================  ===========  ======== 
 Harvest salt to plant                         Mtpa       2.27 
=========================================  ===========  ======== 
 KCl addition                                  tpa       42,360 
=========================================  ===========  ======== 
 Recovery of potassium from harvest salt        %          84% 
=========================================  ===========  ======== 
 Operating and capital costs 
=========================================  ===========  ======== 
 Operating costs 
=========================================  ===========  ======== 
     Mine gate cash operating cost             A$/t        240 
=========================================  ===========  ======== 
     Transport and handling cost               A$/t        62 
=========================================  ===========  ======== 
     C1 cash cost                              A$/t        302 
=========================================  ===========  ======== 
 Capital costs 
=========================================  ===========  ======== 
     Direct cost                               A$m         157 
=========================================  ===========  ======== 
     Indirect cost                             A$m         76 
=========================================  ===========  ======== 
     Contingency                               A$m         21 
=========================================  ===========  ======== 
     Total capital cost                        A$m         254 
=========================================  ===========  ======== 
 Financial performance 
=========================================  ===========  ======== 
 Price (FOB)                                  US$/t        550 
=========================================  ===========  ======== 
 Exchange rate                                A$/US$      0.68 
=========================================  ===========  ======== 
 Discount rate                                  %          8% 
=========================================  ===========  ======== 
 NPV(8) (post-tax)                             A$m         479 
=========================================  ===========  ======== 
 IRR (post-tax)                                 %          28% 
=========================================  ===========  ======== 
 NPV(8) (pre-tax)                              A$m         696 
=========================================  ===========  ======== 
 IRR (pre-tax)                                  %          38% 
=========================================  ===========  ======== 
 EBITDA(2)                                     A$m         111 
=========================================  ===========  ======== 
 Post tax annual cash flow(2)                  A$m         78 
=========================================  ===========  ======== 
 Payback                                      years        3.5 
=========================================  ===========  ======== 
 

Note 1: Refers to initial trench and bore development included in the capital cost estimate. Note 2: Refers to average annual Project cash flows during steady-state production.

STAGE 2 CONSTRUCTION UPDATE

SO4 is using a staged approach to pond construction that aligns with the process plant ramp-up schedule and steady-state production requirements, enabling some initial capital expenditure to be deferred for a period of up to 12 months.

The first stage of solar evaporation ponds (125ha) were completed in June 2019 and are now filled with high grade brine (25kg/m(3) SOP) from the Williamson Pit. These ponds have now been in operation for over 6 months, and have provided the Company with additional insight into the critical evaporation processes and provided opportunities to further improve design and construction of the remaining evaporation pond network.

Stage 2 of on-lake construction commenced during Q4 2019. Approximately 275ha of evaporation pond area and accompanying brine extraction trenches will be constructed as part of Stage 2 on-lake construction.

The Stage 2 evaporation ponds are being constructed using a combination of PVC sheet piles and traditional bulk earthworks. Material to form access around the perimeter of the ponds and the internal pond walls have been constructed using pre-strip material sourced from Blackham's Williamson Pit pre-strip mining operation. Keller, one of the largest specialist geotechnical contractors in Australia, is installing specially designed PVC sheet piles to create the perimeter/external wall of the ponds. The construction methodology adopted has resulted in a compression of the project schedule compared to traditional earthwork berms.

As at 31 December 2019, in line with the Project schedule, the civil construction team completed over 100ha of Stage 2 evaporation ponds. These ponds have been pre-soaked and filled with brine from the expanding trench network. The ponds completed during the quarter take the total under operation to 225ha. A further 175ha of evaporation ponds will be completed and transferred to operations over the next few weeks, taking the total evaporation ponds in operation to over 400ha.

Construction of the brine extraction trench network on the lake playa continued on schedule during the quarter, with trenches constructed at an average depth of more than 4m.

To operate the brine abstraction trench network and evaporation pond system, a specialised pipe network and pumping system has been designed and constructed to suit the unique site environment. In excess of 12,000m of brine transfer piping has been installed with pump capacity of 600l/s.

In early January 2020, the Lake Way site received approximately 62mm of rain over a seven (7) day period.

The rain event was timely such that it positively assisted to pre-soak the newly constructed Stage 2 on-lake evaporation ponds prior to filling with potassium rich brine from trenches. In addition, the rain also filled the trench network and recharged the surface playa aquifer in the areas on lake where water flow moved.

The very high evaporation rates experienced during summer ensure that the rain received has had minimal ongoing impact on the construction schedule.

lake way operations

SO4's Operations team have been managing the 125ha Stage 1 evaporation ponds since June 2019.

During Q4 2019, the completed Stage 2 evaporation ponds were commissioned and handed over to operations. Approximately 2.1GL of Lake Way brine had been transferred into evaporation ponds by the end of December 2019, including 1.2GL from the Williamson Pit.

Average chemistry of lake playa brine pumped from Brine Extraction Trenches was 6.8 Kg/m(3) of Potassium (K) (15.2 Kg/m(3) SOP) in line with expectations. Brine chemistry is performing as expected within evaporation ponds and the system commenced precipitating Potassium salts during the quarter as planned.

Handover of the brine extraction trench network to the operations team and ramp up of brine production capacity is ongoing.

Process Plant

The Company has engaged GR Engineering Services Limited (GRES) to design, procure and manage construction of the process plant under an early services arrangement whilst a major contract is finalised between the parties. Wood Group PLC has been engaged as the process engineer.

The site clearance for the Process Plant commenced in January 2020 and construction is expected to commence during Q1 2020.

Other key engineering activities undertaken during the quarter include:

-- Veolia continued detailed design of the crystalliser package and fabrication commenced in January 2020;

-- Continued the detailed process design, including mechanical and piping layout design, as well as finalising equipment selection and tender assessments for vendor supply packages;

-- Progressed pumping calculations and definition of design parameters for the steel tanks;

-- Electrical design work progressed for switchroom layouts, load lists and cable schedules.

Non-Process Infrastructure (NPI)

SO4 awareded a number of key contracts for the installation and supply of key NPI and services during Q4 2019.

Construction and installation of an Accommodation Village was awarded to the Complete Group (Complete). The permanent camp will be acquired under a build, own, transfer (BOT) contract. The scope of works includes the design, engineering, supply and installation of buildings, detailed site works, services and commissioning for the construction of the village.

Complete progressed the detailed design and procurement for the accommodation village during the quarter. Installation of the village is expected to commence on site during Q1 2020.

Power West has been engaged for the supply of power to the Project under a 10-year Power Purchase Agreement (PPA). The PPA provides gas generated power with containerised alternate fuel source co-generation to allow for early commissioning.

Other packages awarded during Q4 2019 included:

-- Reverse Osmosis Water Treatment Plant contract awarded for the design, supply and installation of the Brackish Water Reverse Osmosis Treatment Plant including tanks, pipes and pumps.

-- Wastewater Treatment Plant contract awarded for the design, supply and installation of the Moving Bed Bioreactor Plus Sewerage Treatment Plant including the treated effluent discharge system.

-- Communication System, including Telstra contract to supply sitewide communications, and backhaul to Wiluna, and the fixed communications tower contract.

Discussions regarding the Gas Transport Agreement progressed during the December Quarter, with an early services agreement awarded to progress design of the Goldfields Gas Pipeline tie in, the lateral pipeline together with associated infrastructure and commencement of necessary approval activities. Agreements for the supply of natural gas were also progressed.

The design for the main intersection roadworks at the Goldfields Highway progressed with Mainroads WA approval allowing finalisation of construction planning.

Acquisition of strategic tenement package

In July 2019, SO4 and Blackham entered into a Sales Agreement whereby SO4 will acquire a package of tenements and other key assets for the Lake Way Project. The conditions precedent to the Sales Agreement were satisfied and the transaction has completed in early October 2019. The acquisition is another important step in providing the Company with certainty over tenure, timing and capital expenditure required to bring the Lake Way Project into production.

During the Q4 2019, SO4 exercised its option under the Sales Agreement to acquire Blackham's southern water borefield infrastructure outright, securing long term water supply. The Company is required to make a A$3m payment to Blackham by 30 June 2020.

Approvals

Lake Way is located in an area with a long history of minerals exploration and associated environmental assessment. SO4 has taken advantage of existing environmental knowledge to support the permitting of its early works programme and focus additional investigations required for permitting of full-scale operations.

Environmental work to date has not identified any social or environmental factors that could constitute fatal flaws or insurmountable obstacles to gaining necessary statutory approvals. The final outstanding approvals for the Lake Way Project are currently being progressed.

The pond and trench construction activities for Stage 2 Project development works commenced in Q4 2019 after receipt of the Project Management Plan approval from Department of Mines, Industry Regulation and Safety (DMIRS). These are the construction activities which were determined by the Environmental Protection Agency (EPA) to not require formal assessment under Part IV of the Environmental Protection Act 1986 and have an approved Mining Proposal from the Department of Mines, Industry Regulation and Safety (DMIRS) and a Works Approval from the Department of Water and Environmental Regulation (DWER). These approvals include a disturbance area to construct ponds and trenches totalling up to 757ha.

Further approvals are required for the full scope of the Project with allowance for these approvals included in the Project schedule. The EPA has determined that the full project scope requires formal assessment with no public review. This assessment process is progressing well with a draft scoping document accepted and the commencement of the additional studies required.

Greenhouse gas emissions studies completed to date show Scope 1 CO(2) emissions are significantly less than the proposed EPA threshold emission level of 100,000t CO(2) equivalent, which would require formal assessment.

The recent rainfall received in January 2020 has created opportunities for SO4 to undertake additional studies to be undertaken in Q1 2020. The studies to be conducted include: Aquatic Lake Invertebrate survey, Short Range Endemic survey, targeted Tecticornia survey, Noise study, targeted Flora and Fauna surveys and Flood study.

In respect of the Processing Plant construction, the Company received a Mining Permit approval from Department of Mines, Industry Regulation and Safety (DMIRS) and Native Vegetation Clearing Permit has been approved. These approvals have allowed the bulk earthworks for the plant site to commence.

The Company has continued to obtain Ministerial consent to use the land under section 18 of the Aboriginal Heritage Act 1972, for additional development as needed to meet ongoing project requirements.

SO4 has obtained the necessary water licences to extract process water and for brine extraction from the lake. Final brine extraction licences are being sought. Project approvals for the construction of the initial paleo bores to obtain brine from the paleo channel are imminent.

Native Title and Heritage

In November 2019, the Company executed the Native Title Land Access Agreement (LAA) with Tarlka Matuwa Piarku (Aboriginal Corporation) RNTBC (TMPAC) for the whole of the Lake Way Project.

The landmark LAA will provide for the continuing development of the Lake Way Project and significant benefits to TMPAC and the broader community. TMPAC have entered into the LAA with SO4 on behalf of the Wiluna People who are the recognised Native Title Holders of the land covering the Lake Way Project area.

The LAA provides tenure and native title approval security to SO4 for the duration of the Project and covers the whole of the Lake Way Project area. In line with customary industry standards, TMPAC and the broader Wiluna Community will receive significant economic, social and environmental benefits, including:

   --    Royalty payments; 
   --    Community support programs; 
   --    Employment & training; 
   --    Aboriginal business development and contracting opportunities; 
   --    Heritage protection and land management opportunities. 

The LAA includes an agreed procedure for the grant of any necessary statutory Aboriginal heritage consents for project operations as well as exclusion zones to protect areas of particular cultural sensitivity, all of which sit outside the footprint of proposed operations.

The execution of the LAA is a major milestone for the Lake Way Project and ensures remaining Mining Leases and associated tenure will be granted to support the rapid development of the Lake Way Project.

SO4 has been actively engaging with TMPAC and the broader Wiluna community for over 18 months as part of its commitment to establish early consultation and engagement into the design and implementation of the Lake Way Project.

Offtake

During the Q4 2019, the Company signed binding term sheets for the sale of 220,000t per annum of premium SOP from the Lake Way Project, including:

o HELM AG - 50,000t per annum for 10 years in South East Asia and the Middle East

o Unifert - 60,000t per annum for 5 years in the Middle East and Africa

o Indagro - 50,000t per annum for 5 years in North America and Europe

o Fertisur - 60,000t per annum for 5 years in South America

Supported by the extensive test work and samples produced to date from Lake Way harvested salts, SO4 is planning to deliver a high quality, premium grade SOP to the market. Initially the Project will produce two products, (i) a high potassium content standard powder SOP (SSOP) and (ii) fertigation grade water soluble SOP (WSSOP). SO4 intends to increase the product offering to include a granular grade after production has commenced.

SO4's marketing strategy for the sale and distribution of its premium grade SOP is to work with selected industry leading partners targeting high growth markets and focussing on geographical areas with the highest concentration of crops which benefit from SOP fertilisers.

SO4 has been working with each of the offtake counterparties to execute final purchase agreements, based upon the binding terms sheets.

Discussions are also advanced with an additional Tier-1 fertiliser company for the sale of further premium SOP from the Lake Way Project and the Company continues to engage with a number of other potential customers.

Project Funding

In December 2019, SO4 secured further funding for the Project via an institutional placement and debt facility extension for a total of A$45.5 million in additional available funding.

The combined additional funding ensures the Company is well placed to continue with the rapid development of the Lake Way Project, including the Stage 2 on-lake construction which is substantially advanced and commencement of process plant construction in Q1 2020.

Institutional Placement

The Company agreed to place approximately 33.6 million shares to a number of new Australian institutional investors and existing institutional shareholders at A$0.70 each to raise A$23.5 million before costs.

The Placement has contributed to the continued rapid development of the Lake Way Project, including construction of Stage 2 on-lake infrastructure and commencement of site works for the process plant in early 2020, along with ongoing exploration of other lakes and general working capital.

Stage 1 Facility Extension

In August 2019, SO4 announced that it had mandated Taurus Funds Management (Taurus or the Lenders), to provide up to US$150m project financing for the Lake Way Project.

The Stage 1 Facility (Facility) provided initial access to funding for early construction works for the Lake Way Project and enabled completion of the BFS prior to drawdown of the main Project Development Facility (PDF). The Facility is also funding civil works including the second stage of trenches and key evaporation ponds currently under construction, which will provide the initial harvest salts to enable the feed for plant commissioning. Given the lead-time required to generate harvest salts, the Facility is a crucial part of accelerating Lake Way's development towards commercial SOP production.

To fund the ongoing construction of key infrastructure prior to drawdown of the PDF, the parties agreed to a US$15m extension to the Facility. Terms and conditions of the extension to the Facility are consistent with the original terms. The extended Facility will be refinanced upon drawdown of the PDF.

Following completion of the BFS, SO4 has been working with Taurus to complete documentation and satisfy the conditions precedent to the PDF. In addition to the PDF, the Company is assessing a range of alternative and complementary funding options to ensure that it is fully funded in the coming months to complete construction in line with the Project schedule.

LAKE MARMION EXPLORATION PROGRAM

The Company continued to progress its assessment of the other lakes in its portfolio in order to prioritise future potential development. During Q4 2019 exploration activities commenced at Lake Marmion with a view to reporting a maiden mineral resource estimate.

Work at Lake Marmion consisted of the following:

-- Drilling, completion and development of 37 100mm diameter auger holes as piezometers between 3m and 7m depth;

-- Installation of 17 piezometers with pressure transducers to monitor long term water level variations;

   --    Carrying out of Slug Tests for hydraulic conductivity estimation on 19 piezometers; 

-- Installation of 20 piezometers at the test trench location to monitor the change in water level due to the trench test pumping;

   --    Digging of 2 trenches and 5 test pits with an amphibious excavator for test pumping; 

-- 36 insitu core samples from the piezometers, 20 of which have been sent to a laboratory for porosity, hydraulic conductivity and specific yield determination;

   --    21 grab samples for soil analysis; 

-- 8 Column samples of which 6 were sent to a laboratory to assess the impact of dilution in response to recharge events;

-- 62 brine samples for grade analysis, including duplicates, collected from piezometers, pits and hand dug pits.

Results from this program are pending and will be reported when available.

For further information please visit www.so4.com.au or contact:

 
 Tony Swiericzuk / Clint McGhie                  Salt Lake Potash Limited                    Tel: +61 8 6559 5800 
 Colin Aaronson / Richard Tonthat / Ben          Grant Thornton UK LLP (Nominated Adviser)   Tel: +44 (0) 20 7383 5100 
 Roberts 
 Derrick Lee / Peter Lynch                       Cenkos Securities plc (Joint Broker)        Tel: +44 (0) 131 220 6939 
 Rupert Fane / Ernest Bell                       Hannam & Partners (Joint Broker)            Tel: +44 (0) 20 7907 8500 
 

This announcement has been authorised for release by the Board of Directors.

The information contained within this announcement is deemed to constitute inside information as stipulated under the Market Abuse Regulations (EU) No. 596/2014. Upon the publication of this announcement, this inside information is now considered to be in the public domain.

Appendix A - Competent Person Statement and Disclaimer

Competent Persons Statement

The information in this announcement that relates to Production Targets and Ore Reserves for Lake Way is extracted from the announcement entitled 'Outstanding Bankable Feasibility Results for Lake Way' dated 11 October 2019. This announcement is available to view on www.so4.com.au. The information in the original ASX Announcement that related to Production Targets and Ore Reserves was based on, and fairly represents, information compiled by Mr Ben Jeuken, who is a member of the Australasian Institute of Mining and Metallurgy and a member of the International Association of Hydrogeologists, and Mr Robert Kinnell, who is a member of the Australasian Institute of Mining and Metallurgy and a Fellow of the Geological Society of London. Mr Jeuken is employed by Groundwater Science Pty Ltd, an independent consulting company. Mr Kinnell is a full time employee of Salt Lake Potash Limited. Mr Jeuken and Mr Kinnell have sufficient experience, which is relevant to the style of mineralisation and type of deposit under consideration and to the activity, which they are undertaking to qualify as a Competent Person as defined in the 2012 Edition of the 'Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves'. Salt Lake Potash Limited confirms that it is not aware of any new information or data that materially affects the information included in the original market announcement. Salt Lake Potash Limited confirms that the form and context in which the Competent Person's findings are presented have not been materially modified from the original market announcement.

The information in this announcement that relates to Exploration Results and Mineral Resources for Lake Way is extracted from the announcement entitled 'Outstanding Bankable Feasibility Results for Lake Way' dated 11 October 2019. This announcement is available to view on www.so4.com.au. The information in the original ASX Announcement that related to Exploration Results and Mineral Resources was based on, and fairly represents, information compiled by Mr Ben Jeuken, who is a member of the Australasian Institute of Mining and Metallurgy and a member of the International Association of Hydrogeologists. Mr Jeuken is employed by Groundwater Science Pty Ltd, an independent consulting company. Mr Jeuken has sufficient experience, which is relevant to the style of mineralisation and type of deposit under consideration and to the activity, which he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the 'Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves'. Salt Lake Potash Limited confirms that it is not aware of any new information or data that materially affects the information included in the original market announcement. Salt Lake Potash Limited confirms that the form and context in which the Competent Person's findings are presented have not been materially modified from the original market announcement.

The information in this announcement that relates to Processing and the Process Plant is extracted from the announcement entitled 'Outstanding Bankable Feasibility Results for Lake Way' dated 11 October 2019. This announcement is available to view on www.so4.com.au. The information in the original ASX Announcement that related to Processing and the Process Plant was based on, and fairly represents, information provided by Mr Kevin Martina, Professional Engineer, who is a Member of the Association of Professional Engineers and Geoscientists of Saskatchewan (APEGS), a 'Recognised Professional Organisation' (RPO) included in a list promulgated by the ASX from time to time. Mr Martina is employed by Wood Canada Limited, Saskatoon. Wood is engaged as a consultant by Salt Lake Potash Limited. Mr Martina has sufficient experience, which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking, to qualify as a Competent Person as defined in the 2012 Edition of the 'Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves'. Salt Lake Potash Limited confirms that it is not aware of any new information or data that materially affects the information included in the original market announcement. Salt Lake Potash Limited confirms that the form and context in which the Competent Person's findings are presented have not been materially modified from the original market announcement.

Production Target

The Lake Way 245ktpa Production Target stated in this presentation is based on the Company's Bankable Feasibility Study as released to the ASX on 11 October 2019. The information in relation to the Production Target that the Company is required to include in a public report in accordance with ASX Listing Rule 5.16 and 5.17 was included in the Company's ASX Announcement released on 11 October 2019. The Company confirms that the material assumptions underpinning the Production Target referenced in the 11 October 2019 release continue to apply and have not materially changed.

Forward Looking Statements

This announcement may include forward-looking statements. These forward-looking statements are based on Salt Lake Potash Limited's expectations and beliefs concerning future events. Forward looking statements are necessarily subject to risks, uncertainties and other factors, many of which are outside the control of Salt Lake Potash Limited, which could cause actual results to differ materially from such statements. Salt Lake Potash Limited makes no undertaking to subsequently update or revise the forward-looking statements made in this announcement, to reflect the circumstances or events after the date of that announcement.

Appendix 2 - Summary of Exploration and Mining Tenements as at 31 DECEMBER 2019

 
       Project            Status      Type of Change    License Number    Interest (%)   Interest (%) 
                                                                            30-Sep-19      31-Dec-19 
 Western Australia 
====================  =============  ================  ================  =============  ============= 
 Lake Way 
====================  =============  ================  ================  =============  ============= 
  Central                Granted             -             E53/1878           100%           100% 
====================  =============  ================  ================  =============  ============= 
  East                   Granted             -             E53/2057           100%           100% 
====================  =============  ================  ================  =============  ============= 
  South                  Granted             -             E53/1897           100%           100% 
====================  =============  ================  ================  =============  ============= 
  South                  Granted             -             E53/2059           100%           100% 
====================  =============  ================  ================  =============  ============= 
  South                  Granted             -             E53/2060           100%           100% 
====================  =============  ================  ================  =============  ============= 
  West                 Application           -              L53/208           100%           100% 
====================  =============  ================  ================  =============  ============= 
  Central              Application           -             M53/1102           100%           100% 
====================  =============  ================  ================  =============  ============= 
  Central              Application      Application        M53/1103            -             100% 
====================  =============  ================  ================  =============  ============= 
  Central              Application      Application        M53/1104            -             100% 
====================  =============  ================  ================  =============  ============= 
  Central              Application      Application        M53/1105            -             100% 
====================  =============  ================  ================  =============  ============= 
  Central              Application      Application        M53/1106            -             100% 
====================  =============  ================  ================  =============  ============= 
  Central              Application      Application        M53/1107            -             100% 
====================  =============  ================  ================  =============  ============= 
  Central                Granted        Acquisition        E53/1862                          100% 
====================  =============  ================  ================  =============  ============= 
  West                   Granted        Acquisition        E53/1863            -             100% 
====================  =============  ================  ================  =============  ============= 
  North                Application      Acquisition        E53/1905                          100% 
====================  =============  ================  ================  =============  ============= 
  North                Application      Acquisition        E53/1952            -             100% 
====================  =============  ================  ================  =============  ============= 
  West                 Application      Acquisition        E53/1966                          100% 
====================  =============  ================  ================  =============  ============= 
  North                Application      Acquisition        E53/2049                          100% 
====================  =============  ================  ================  =============  ============= 
  North                  Granted        Acquisition        P53/1642                          100% 
====================  =============  ================  ================  =============  ============= 
  West                   Granted        Acquisition        P53/1643                          100% 
====================  =============  ================  ================  =============  ============= 
  West                   Granted        Acquisition        P53/1644                          100% 
====================  =============  ================  ================  =============  ============= 
  West                   Granted        Acquisition        P53/1645                          100% 
====================  =============  ================  ================  =============  ============= 
  Central                Granted        Acquisition        P53/1666            -             100% 
====================  =============  ================  ================  =============  ============= 
  Central                Granted        Acquisition        P53/1667                          100% 
====================  =============  ================  ================  =============  ============= 
  Central                Granted        Acquisition        P53/1668                          100% 
====================  =============  ================  ================  =============  ============= 
  North                  Granted        Acquisition         M53/121            -             100% 
====================  =============  ================  ================  =============  ============= 
  West                   Granted        Acquisition         M53/122            -             100% 
====================  =============  ================  ================  =============  ============= 
  West                   Granted        Acquisition         M53/123            -             100% 
====================  =============  ================  ================  =============  ============= 
  West                   Granted        Acquisition         M53/147            -             100% 
====================  =============  ================  ================  =============  ============= 
  Central                Granted        Acquisition         M53/253            -             100% 
====================  =============  ================  ================  =============  ============= 
  Central                Granted        Acquisition         M53/796            -             100% 
====================  =============  ================  ================  =============  ============= 
  Central                Granted        Acquisition         M53/797            -             100% 
====================  =============  ================  ================  =============  ============= 
  Central                Granted        Acquisition         M53/798            -             100% 
====================  =============  ================  ================  =============  ============= 
  Central                Granted        Acquisition         M53/910            -             100% 
====================  =============  ================  ================  =============  ============= 
  West                   Granted        Acquisition         L53/51             -             100% 
====================  =============  ================  ================  =============  ============= 
  West                 Application      Acquisition         L53/207            -             100% 
====================  =============  ================  ================  =============  ============= 
  West                 Application           -              L53/211           100%           100% 
====================  =============  ================  ================  =============  ============= 
  North                Application           -              L53/212           100%           100% 
====================  =============  ================  ================  =============  ============= 
  West                 Application      Application         L53/214            -             100% 
====================  =============  ================  ================  =============  ============= 
  West                 Application      Application         L53/215            -             100% 
====================  =============  ================  ================  =============  ============= 
  North                Application      Application         L53/216            -             100% 
====================  =============  ================  ================  =============  ============= 
  West                 Application      Application         L53/217            -             100% 
====================  =============  ================  ================  =============  ============= 
  West                 Application      Application         L53/218            -             100% 
====================  =============  ================  ================  =============  ============= 
  West                 Application      Application         L53/210            -             100% 
====================  =============  ================  ================  =============  ============= 
 Lake Wells 
====================  =============  ================  ================  =============  ============= 
  Central                Granted             -             E38/2710           100%           100% 
====================  =============  ================  ================  =============  ============= 
  South                  Granted             -             E38/2821           100%           100% 
====================  =============  ================  ================  =============  ============= 
  North                  Granted             -             E38/2824           100%           100% 
====================  =============  ================  ================  =============  ============= 
  Outer East             Granted             -             E38/3055           100%           100% 
====================  =============  ================  ================  =============  ============= 
  Single Block           Granted             -             E38/3056           100%           100% 
====================  =============  ================  ================  =============  ============= 
  Outer West             Granted             -             E38/3057           100%           100% 
====================  =============  ================  ================  =============  ============= 
  North West             Granted             -             E38/3124           100%           100% 
====================  =============  ================  ================  =============  ============= 
  West                   Granted             -              L38/262           100%           100% 
====================  =============  ================  ================  =============  ============= 
  East                   Granted             -              L38/263           100%           100% 
====================  =============  ================  ================  =============  ============= 
  South West             Granted             -              L38/264           100%           100% 
====================  =============  ================  ================  =============  ============= 
  South                  Granted             -              L38/287           100%           100% 
====================  =============  ================  ================  =============  ============= 
  South Western          Granted             -             E38/3247           100%           100% 
====================  =============  ================  ================  =============  ============= 
  South                  Granted             -             M38/1278           100%           100% 
====================  =============  ================  ================  =============  ============= 
  Central              Application           -             E38/3380           100%           100% 
====================  =============  ================  ================  =============  ============= 
 Lake Ballard 
====================  =============  ================  ================  =============  ============= 
  West                   Granted             -              E29/912           100%           100% 
====================  =============  ================  ================  =============  ============= 
  East                   Granted             -              E29/913           100%           100% 
====================  =============  ================  ================  =============  ============= 
  North                  Granted             -              E29/948           100%           100% 
====================  =============  ================  ================  =============  ============= 
  South                  Granted             -              E29/958           100%           100% 
====================  =============  ================  ================  =============  ============= 
  South East             Granted             -             E29/1011           100%           100% 
====================  =============  ================  ================  =============  ============= 
  South East             Granted             -             E29/1020           100%           100% 
====================  =============  ================  ================  =============  ============= 
  South East             Granted             -             E29/1021           100%           100% 
====================  =============  ================  ================  =============  ============= 
  South East             Granted             -             E29/1022           100%           100% 
====================  =============  ================  ================  =============  ============= 
  South                  Granted             -             E29/1067           100%           100% 
====================  =============  ================  ================  =============  ============= 
  South                  Granted             -             E29/1068           100%           100% 
====================  =============  ================  ================  =============  ============= 
  East                 Application           -             E29/1069           100%           100% 
====================  =============  ================  ================  =============  ============= 
  North                  Granted             -             E29/1070           100%           100% 
====================  =============  ================  ================  =============  ============= 
 Lake Irwin 
====================  =============  ================  ================  =============  ============= 
  West                   Granted             -             E37/1233           100%           100% 
====================  =============  ================  ================  =============  ============= 
  Central                Granted             -             E39/1892           100%           100% 
====================  =============  ================  ================  =============  ============= 
  East                   Granted             -             E38/3087           100%           100% 
====================  =============  ================  ================  =============  ============= 
  North                  Granted             -             E37/1261           100%           100% 
====================  =============  ================  ================  =============  ============= 
  Central East           Granted             -             E38/3113           100%           100% 
====================  =============  ================  ================  =============  ============= 
  South                  Granted             -             E39/1955           100%           100% 
====================  =============  ================  ================  =============  ============= 
  North West             Granted             -             E37/1260           100%           100% 
====================  =============  ================  ================  =============  ============= 
  South West             Granted             -             E39/1956           100%           100% 
====================  =============  ================  ================  =============  ============= 
 Lake Minigwal 
====================  =============  ================  ================  =============  ============= 
  West                   Granted             -             E39/1893           100%           100% 
====================  =============  ================  ================  =============  ============= 
  East                   Granted             -             E39/1894           100%           100% 
====================  =============  ================  ================  =============  ============= 
  Central                Granted             -             E39/1962           100%           100% 
====================  =============  ================  ================  =============  ============= 
  Central East           Granted             -             E39/1963           100%           100% 
====================  =============  ================  ================  =============  ============= 
  South                  Granted             -             E39/1964           100%           100% 
====================  =============  ================  ================  =============  ============= 
  South West             Granted             -             E39/1965           100%           100% 
====================  =============  ================  ================  =============  ============= 
 Lake Marmion 
====================  =============  ================  ================  =============  ============= 
  North                  Granted             -             E29/1000           100%           100% 
====================  =============  ================  ================  =============  ============= 
  Central                Granted             -             E29/1001           100%           100% 
====================  =============  ================  ================  =============  ============= 
  South                  Granted             -             E29/1002           100%           100% 
====================  =============  ================  ================  =============  ============= 
  West                   Granted             -             E29/1005           100%           100% 
====================  =============  ================  ================  =============  ============= 
  West                 Application           -             E29/1069           100%           100% 
====================  =============  ================  ================  =============  ============= 
 Lake Noondie 
====================  =============  ================  ================  =============  ============= 
  North                  Granted             -             E57/1062           100%           100% 
====================  =============  ================  ================  =============  ============= 
  Central                Granted             -             E57/1063           100%           100% 
====================  =============  ================  ================  =============  ============= 
  South                  Granted             -             E57/1064           100%           100% 
====================  =============  ================  ================  =============  ============= 
  West                   Granted             -             E57/1065           100%           100% 
====================  =============  ================  ================  =============  ============= 
  East                   Granted             -              E36/932           100%           100% 
====================  =============  ================  ================  =============  ============= 
  Central              Application      Application         E36/984            -             100% 
====================  =============  ================  ================  =============  ============= 
  Central              Application      Application         E36/984            -             100% 
====================  =============  ================  ================  =============  ============= 
 Lake Barlee 
====================  =============  ================  ================  =============  ============= 
  North                  Granted             -              E30/495           100%           100% 
====================  =============  ================  ================  =============  ============= 
  Central                Granted             -              E30/496           100%           100% 
====================  =============  ================  ================  =============  ============= 
  South                  Granted             -             E77/2441           100%           100% 
====================  =============  ================  ================  =============  ============= 
 Lake Raeside 
====================  =============  ================  ================  =============  ============= 
  North                  Granted             -             E37/1305           100%           100% 
====================  =============  ================  ================  =============  ============= 
 Lake Austin 
====================  =============  ================  ================  =============  ============= 
  North                Application           -              E21/205           100%           100% 
====================  =============  ================  ================  =============  ============= 
  West                 Application           -              E21/206           100%           100% 
====================  =============  ================  ================  =============  ============= 
  East                   Granted             -              E58/529           100%           100% 
====================  =============  ================  ================  =============  ============= 
  South                  Granted             -              E58/530           100%           100% 
====================  =============  ================  ================  =============  ============= 
  South West             Granted             -              E58/531           100%           100% 
====================  =============  ================  ================  =============  ============= 
 Lake Moore 
====================  =============  ================  ================  =============  ============= 
    Central              Granted             -             E59/2344           100%           100% 
====================  =============  ================  ================  =============  ============= 
 Northern Territory 
====================  =============  ================  ================  =============  ============= 
 Lake Lewis 
====================  =============  ================  ================  =============  ============= 
  South                  Granted             -             EL 29787           100%           100% 
====================  =============  ================  ================  =============  ============= 
  North                  Granted             -             EL 29903           100%           100% 
====================  =============  ================  ================  =============  ============= 
 

Appendix 3 - asx aPPIX 5B

Appendix 5B

Mining exploration entity and oil and gas exploration entity quarterly report

Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10, 01/05/13, 01/09/16

 
 Name of entity 
----------------------------------------------------- 
 Salt Lake Potash Limited 
 ABN                Quarter ended ("current quarter") 
---------------    ---------------------------------- 
 98 117 085 748                      31 December 2019 
                   ---------------------------------- 
 
 
 Consolidated statement of cash                Current quarter    Year to date 
  flows                                             $A'000          (6 months) 
                                                                      $A'000 
 1.     Cash flows from operating 
         activities 
 1.1    Receipts from customers 
 1.2    Payments for 
        (a) exploration & evaluation                  (18,348)          (27,388) 
        (b) development (1)                            (5,472)           (7,668) 
        (c) production                                       -                 - 
        (d) staff costs                                (3,069)           (5,287) 
        (e) administration and corporate 
         costs                                           (991)           (1,628) 
 1.3    Dividends received (see note                         -                 - 
         3) 
 1.4    Interest received                                   31                78 
        Interest and other costs of 
 1.5     finance paid                                      (2)               (5) 
 1.6    Income taxes paid                                    -                 - 
 1.7    Research and development refunds                     -                 - 
        Other (provide details if 
 1.8     material) 
          - Business Development                       (1,023)           (1,481) 
         - Security Deposits                             (126)             (126) 
                                              ----------------  ---------------- 
        Net cash from / (used in) 
 1.9     operating activities                         (29,000)          (43,505) 
-----  -------------------------------------  ----------------  ---------------- 
 
 2.       Cash flows from investing 
           activities 
 2.1      Payments to acquire: 
          (a) property, plant and equipment              (329)             (487) 
          (b) tenements (see item 10)                  (7,000)          (10,000) 
          (c) investments                                    -                 - 
          (d) other non-current assets                       -                 - 
 2.2      Proceeds from the disposal 
           of: 
          (a) property, plant and equipment                 35                35 
          (b) tenements (see item 10)                        -                 - 
          (c) investments                                    -                 - 
          (d) other non-current assets                       -                 - 
 2.3      Cash flows from loans to                           -                 - 
           other entities 
 2.4      Dividends received (see note                       -                 - 
           3) 
 2.5      Other (provide details if                          -                 - 
           material) 
                                              ----------------  ---------------- 
          Net cash from / (used in) 
 2.6       investing activities                        (7,294)          (10,452) 
-------  -----------------------------------  ----------------  ---------------- 
 
 3.       Cash flows from financing 
           activities 
 3.1      Proceeds from issues of shares                23,008            30,416 
 3.2      Proceeds from issue of convertible                 -                 - 
           notes 
 3.3      Proceeds from exercise of                          -                 - 
           share options 
          Transaction costs related 
           to issues of shares, convertible 
 3.4       notes or options                              (762)             (859) 
 3.5      Proceeds from borrowings                      29,226            44,043 
 3.6      Repayment of borrowings                          (1)              (40) 
          Transaction costs related 
 3.7       to loans and borrowings                       (671)           (2,411) 
 3.8      Dividends paid                                     -                 - 
 3.9      Other (provide details if                          -                 - 
           material) 
                                              ----------------  ---------------- 
          Net cash from / (used in) 
 3.10      financing activities                         50,800            71,149 
-------  -----------------------------------  ----------------  ---------------- 
 
 4.       Net increase / (decrease) 
           in cash and cash equivalents 
           for the period 
          Cash and cash equivalents 
 4.1       at beginning of period                       21,989            19,304 
          Net cash from / (used in) 
           operating activities (item 
 4.2       1.9 above)                                 (29,000)          (43,505) 
          Net cash from / (used in) 
           investing activities (item 
 4.3       2.6 above)                                  (7,294)          (10,452) 
          Net cash from / (used in) 
           financing activities (item 
 4.4       3.10 above)                                  50,800            71,149 
          Effect of movement in exchange 
 4.5       rates on cash held                            (289)             (290) 
                                              ----------------  ---------------- 
          Cash and cash equivalents 
 4.6       at end of period                             36,206            36,206 
-------  -----------------------------------  ----------------  ---------------- 
 
 
 
 5.    Reconciliation of cash and           Current quarter   Previous quarter 
        cash equivalents                         $A'000            $A'000 
        at the end of the quarter 
        (as shown in the consolidated 
        statement of cash flows) to 
        the related items in the accounts 
 5.1   Bank balances                                 36,206             21,862 
 5.2   Call deposits                                      -                127 
 5.3   Bank overdrafts                                    -                  - 
 5.4   Other (provide details)                            -                  - 
                                           ----------------  ----------------- 
       Cash and cash equivalents 
        at end of quarter (should 
 5.5    equal item 4.6 above)                        36,206             21,989 
----  -----------------------------------  ----------------  ----------------- 
 
 
 6.     Payments to directors of the entity and          Current quarter 
         their associates                                     $A'000 
        Aggregate amount of payments to these parties 
 6.1     included in item 1.2                                      (136) 
                                                        ---------------- 
 6.2    Aggregate amount of cash flow from loans                       - 
         to these parties included in item 2.3 
                                                        ---------------- 
 6.3    Include below any explanation necessary to understand 
         the transactions included in items 6.1 and 6.2 
-----  ----------------------------------------------------------------- 
 Payments include salaries, director and consulting fees and 
  superannuation. 
 
 
 7.    Payments to related entities of the entity      Current quarter 
        and their associates                                $A'000 
 7.1   Aggregate amount of payments to these parties                 - 
        included in item 1.2 
                                                      ---------------- 
 7.2   Aggregate amount of cash flow from loans                      - 
        to these parties included in item 2.3 
                                                      ---------------- 
 7.3   Include below any explanation necessary to understand 
        the transactions included in items 7.1 and 7.2 
----  ---------------------------------------------------------------- 
 Not applicable. 
 
 
 8.    Financing facilities available        Total facility      Amount drawn 
        Add notes as necessary for          amount at quarter    at quarter end 
        an understanding of the position           end               $A'000 
                                                 $A'000 
 8.1   Loan facilities                                 64,230            42,820 
                                          -------------------  ---------------- 
 8.2   Credit standby arrangements                          -                 - 
                                          -------------------  ---------------- 
 8.3   Other (please specify)                               -                 - 
                                          -------------------  ---------------- 
 8.4   Include below a description of each facility above, including 
        the lender, interest rate and whether it is secured or 
        unsecured. If any additional facilities have been entered 
        into or are proposed to be entered into after quarter 
        end, include details of those facilities as well. 
----  ------------------------------------------------------------------------- 
 The Company has mandated Taurus Funds Management (as manager 
  of the Taurus Mining Finance Fund L.P., Taurus Mining Finance 
  Annex Fund L.P. and Taurus Mining Finance Fund No. 2 L.P.) 
  to provide up to US$150m project financing for the Lake Way 
  Project. 
 
  The Stage 1 Facility was extended from US$30 million to US$45 
  million as announced to the market on 6 December 2020 and continues 
  to be drawn down. The facility is secured and interest is payable 
  at 9.75% pa. 
 
  The Project Development Facility (PDF) for up to US$150m (A$214m) 
  will be used to refinancing the Stage 1 Facility and for project 
  development and working capital associated with the development 
  of the Lake Way Project. Draw down of the PDF is subject to 
  a number of Conditions Precedent, The PDF will be secured and 
  interest will be payable at 9.00% pa. 
 
  As the loan is denominated in USD, the facility amount and 
  amount drawn down has been converted at an FX rate of $0.7006 
  USD/AUD, being the FX crossrate at 31 December 2019. 
 
 
 9.    Estimated cash outflows for next        $A'000 
        quarter 
 9.1   Exploration and evaluation                   400 
 9.2   Development                               36,000 
 9.3   Production                                     - 
 9.4   Staff costs                                3,200 
 9.5   Administration and corporate costs           800 
 9.6   Other (provide details if material) 
         - Property Plant & Equipment             1,400 
         - Business Development                     500 
         - Finance expenses                       1,500 
         - Loan funds draw down                (21,410) 
                                            ----------- 
 9.7   Total estimated cash outflows             22,390 
----  ------------------------------------  ----------- 
 
 
 10.    Changes in tenements   Tenement        Nature of interest   Interest        Interest 
         (items 2.1(b)          reference                            at beginning    at end 
         and 2.2(b) above)      and location                         of quarter      of quarter 
 10.1   Interests in                           Refer to Appendix 
         mining tenements                       2 
         and petroleum 
         tenements lapsed, 
         relinquished 
         or reduced 
-----  ---------------------  --------------  -------------------  --------------  ------------ 
 10.2   Interests in 
         mining tenements 
         and petroleum 
         tenements acquired 
         or increased 
-----  ---------------------  --------------  -------------------  --------------  ------------ 
 

Compliance statement

1 This statement has been prepared in accordance with accounting standards and policies which comply with Listing Rule 19.11A.

   2        This statement gives a true and fair view of the matters disclosed. 

Sign here: ............................................................ Date: 31 January 2020

(Director/Company secretary)

   Print name:     Clint McGhie 

Notes

1. The quarterly report provides a basis for informing the market how the entity's activities have been financed for the past quarter and the effect on its cash position. An entity that wishes to disclose additional information is encouraged to do so, in a note or notes included in or attached to this report.

2. If this quarterly report has been prepared in accordance with Australian Accounting Standards, the definitions in, and provisions of, AASB 6: Exploration for and Evaluation of Mineral Resources and AASB 107: Statement of Cash Flows apply to this report. If this quarterly report has been prepared in accordance with other accounting standards agreed by ASX pursuant to Listing Rule 19.11A, the corresponding equivalent standards apply to this report.

3. Dividends received may be classified either as cash flows from operating activities or cash flows from investing activities, depending on the accounting policy of the entity.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

END

DOCBBMATMTMJMAM

(END) Dow Jones Newswires

January 31, 2020 02:00 ET (07:00 GMT)

Grafico Azioni Salt Lake Potash (LSE:SO4)
Storico
Da Mar 2024 a Apr 2024 Clicca qui per i Grafici di Salt Lake Potash
Grafico Azioni Salt Lake Potash (LSE:SO4)
Storico
Da Apr 2023 a Apr 2024 Clicca qui per i Grafici di Salt Lake Potash