Clogau Operational
Update
Alba Mineral Resources Plc (AIM:
ALBA) is pleased to provide this operational report on the
Company's Clogau-St David's Gold Project in Wales ("Clogau" or the
"Project").
Level 5 Blasting
In the first phase of the blasting
programme at Clogau, a total of 123 tonnes of ore was removed to
surface, a combination of newly blasted ore and historic material
left behind or deposited during previous mining periods.
Processing and Refining
Since the completion of the first
phase of blasting, the focus has been on processing and
refining. From the processing of 11.6 tonnes of newly blasted
ore, 108.6 kg of concentrates have been sent to the Company's usual
third party refiner and all these concentrates have now been
refined, recovering 11.58 grams of gold. In that regard, it
should be noted that the Level 5 blasting programme has not yet
reached the proposed first incline raise (see Figure 1). Therefore,
the blasted material to date does not represent the projected
high-grade zone. The incline raises are designed to intersect the
projected payshoot, thereby maximising the prospects of recovering
economic grades and quantities of gold.

Figure 1: Section through
Llechfraith showing the 5 Level development in relation to the
projected pay shoot. Blasting has taken place at the Drive West and
the Drive East. 4.5 Level drive is off-reef which means that Raise
1 can be commenced from closer to the current No.5 Level Drive West
position.
As indicated in our last operational
update, the Company has been making improvements to the Company's
pilot processing plant to improve the efficiency and recovery of
processing. The improvements have included:
- Repositioning of
the wave table in front of the shaking table, involving the
installation of a new concrete plinth for the wave
table.
- Installation of
a trommel to screen out oversize and enable a fine-grained delivery
to the tables (Figure 2).
-
Modifications to the hammer mill screens in order
to limit oversize material.

Figure 2: Newly installed
trommel.
Blasting Programme
Given the slower than anticipated
progress of the first blasting programme, as outlined in our
announcement of 11 December 2024, following a further review by our
technical team it has been decided to reposition the first raise so
as to be able to commence it much sooner in the planned
blasting programme than previously planned (see Figure 1).
Raise 1
can be commenced within 5 metres from the current face position of
the No.5 Level Drive West. This will result in an earlier transect
across the projected payshoot. The raise will be developed at an
angle of +50° so that it will be self-cleaning, eliminating the
need for time-consuming mucking out.
Revised Work Programme
Alba's planned ongoing work
programme can be summarised as follows:
· Firstly, complete the processing of the current surface
stockpiles comprising the balance of the Waste Tip trenching
material and No.5 Level blasted and historical material, totalling
around 145 tonnes.
· Secondly, given the success of the Waste Pit sampling
programme to date, where bulk grades of up to 3 g/t gold were
defined, complete the Waste Pit trenching programme.
· Thirdly, resume the underground development programme on No.5
Level to complete the planned 1-2 incline raises.
Appointment of Chief Mining
Engineer
The Company is very pleased to
announce the appointment of Dr. Peter Bolt as Chief Mining Engineer
for the Clogau Gold Mine. Peter Bolt is a highly experienced mining
engineer, with a degree and PhD from Cardiff University. He worked
for a decade at SRK (UK) Ltd, becoming Principal Mining Engineer.
Between 2002-7 he worked as a director of AIM-quoted mining
companies, including managing the underground development programme
at the Quintana Gold Mine in Colombia. In 2007 Peter joined
Continental Gold as VP Operations, responsible for their
exploration and development projects in Colombia, including the
Buritica, Machuca and El Limon mines. In recent years, Peter worked
as an independent consultant on mining projects in Europe and
Africa and was a consultant with WSP for 6 years. He has previously
consulted to the Company in relation to the Clogau Gold
Project.

Figure 3: Peter Bolt and
Mark Austin inspecting underground development (11 March
2025)
George Frangeskides, Executive Chairman,
commented:
"We are delighted to welcome Dr Peter Bolt to our team. Peter
has a wealth of knowledge as a senior mining engineer, notably in
relation to underground gold mines and processing operations, and
we have already begun to see the benefits of that in terms of our
formulation of a forward plan for Clogau.
"While the gold recovered to date from the processing and
refining of the newly blasted material from No.5 Level is modest,
the first phase of the blasting programme did not reach the
proposed first incline raise and so the blasted material to date
does not represent the projected high-grade zone within the
Llechfraith Target, our primary gold target within Clogau. As such,
the gold grades in that key zone remain to be
ascertained."
Forward Looking
Statements
This announcement contains
forward-looking statements relating to expected or anticipated
future events and anticipated results that are forward-looking in
nature and, as a result, are subject to certain risks and
uncertainties, such as general economic, market, financial and
business conditions, competition for and availability of qualified
staff and contractors, regulatory processes and actions, technical
issues, new legislation, uncertainties resulting from potential
delays or changes in plans, uncertainties resulting from working in
a new political jurisdiction, uncertainties regarding the results
of exploration, uncertainties regarding the timing and granting of
prospecting rights, uncertainties regarding the timing and granting
of regulatory and other third party consents and approvals,
uncertainties regarding the Company's or any third party's ability
to finance, execute and implement future plans and programmes, and
the occurrence of unexpected events. Actual results achieved may
vary from the information provided herein as a result of numerous
known and unknown risks and uncertainties and other
factors.
Competent Person
Declaration
The information in this release that relates to Exploration
Results has been reviewed by Mr Mark Austin. Mr Austin is a member
of SACNASP (Reg. No. 400235/06), Fellow of The Geological Society
and Fellow of the Geological Society of South Africa. He has a
B.Sc. Honours in Geology with 40 years'
experience.
Mark Austin has sufficient experience that is relevant to the
style of mineralisation and type of deposit under consideration and
to the activity being undertaken to qualify as a Competent Person
as defined in the 2012 Edition of the 'Australasian Code for
Reporting of Exploration targets, Exploration Results, Mineral
Resources and Ore Reserves', also known as the JORC Code. The JORC
code is a national reporting organisation that is aligned with
CRIRSCO. Mr Austin consents to the inclusion in the announcement of
the matters based on his information in the form and context in
which they appear.
**ENDS**
Engage with Alba by asking
questions, watching video summaries and reading what other
shareholders have to say. Navigate to our interactive Investor Hub
here:
https://albamineralresources.com/link/4r8ldr
For further information, please
visit the Alba Mineral Resources plc
investor website (www.albamineralresources.com)
and sign up to receive news and engage with the Alba management
team. Subscribe to
our news alert service (https://alba-l.investorhub.com/auth/signup)
and visit @AlbaMinerals on X (formerly
Twitter).
Contact
Details
|
Alba Mineral Resources
plc
George Frangeskides, Executive
Chairman
|
+44 20
3950 0725
|
SPARK Advisory Partners Limited
(Nomad)
Andrew Emmott
|
+44 20
3368 3555
|
CMC Markets plc (Broker)
Thomas Smith / Douglas
Crippen
|
+44 20
3003 8632
|
Alba's
Projects & Investments
|
Projects Operated by Alba
|
Location
|
Ownership
|
Clogau (gold)
|
Wales
|
100%
|
Dolgellau Gold Exploration
(gold)
|
Wales
|
100%
|
Gwynfynydd (gold)
|
Wales
|
100%
|
Investments Held by Alba
|
Location
|
Ownership
|
GreenRoc Strategic Materials Plc (graphite -
anode)
|
Greenland
|
28.14%
|
Horse Hill (oil)
|
England
|
11.765%
|
Earn-in Projects
|
Location
|
Earn-in Rights
|
Finnsbo (rare earths, copper,
gold)
|
Sweden
|
Up to 100%
|
Optioned Projects
|
Location
|
Further details
|
Norrby (gold, other
metals)
|
Sweden
|
RNS 6/11/24
|
Glava (copper,
gold)
|
Sweden
|
RNS 6/11/24
|