Metallurgical Testing
07 Giugno 2010 - 9:01AM
UK Regulatory
TIDMBKY
RNS Number : 1515N
Berkeley Resources Limited
07 June 2010
7 June 2010
BERKELEY RESOURCES LIMITED
Salamanca Uranium Project
Metallurgical Test Work Update
Berkeley Resources Limited is pleased to announce the commencement of the
metallurgical test work and initial results from the Salamanca Uranium Project
in Spain. The first round of dynamic leach tests have produced encouraging
results with uranium extraction up to 93% generated in acid batch leach tests
for bulk samples from Palacios and Sageras. Acid leach is a proven technology
and was previously used in the Salamanca Operation (from 1994 to 2003) at the
Quercus Processing Plant.
The key results from the test work completed to date at the SGS Lakefield
Laboratory in Perth, Australia, are summarised below:
· Leach recoveries greater than 93% at Palacios and 87% at Sageras using an
acid based process;
· A relatively coarse grind at a P80 of approximately 750 microns;
· Rapid leach times - approximately 6 hours at Palacios and 12 hours at
Sageras;
· Leach temperature ambient;
· Low reagent consumptions at Sageras of 15-20 kg/t and moderate consumption
at Palacios;
· The tests are based on a simplified extraction flow sheet, similar to the
operational process steps utilized at the Quercus Plant;
· Minimal recovery of impurities with the acid leach;
· Reduction of environmental issues with the generation of "dry" leach
residue.
It is important to note that these results are preliminary and leach parameters
have not yet been optimized.
Phase 1 of the metallurgical test work is focusing on a production rate of 2.1
Mlbs (0.95 Kt) of U3O8 per annum using the Palacios and Sageras deposits as the
initial feed to the Quercus Plant.
However, test work has also commenced on Phase 2 which is reviewing the
production options ranging up to 5 Mlbs (2.3 Kt) of U3O8 per annum. Preliminary
bottle roll tests for Alameda South are very encouraging with uranium
extractions up to 91% and low acid consumption. These extraction levels are
consistent with previously reported extractions in excess of 90% from Retortillo
column leach tests in 2009.
Commenting on the above results, the Managing Director of Berkeley Resources Mr.
Ian Stalker said:
"These initial non-optimized results from the Palacios and Sageras deposits are
encouraging and assist in confirming the potential use of a dynamic leach
process using the Quercus Plant.
The preliminary bottle roll results from the Alameda South samples are equally
promising. This deposit, although not previously treated via the Quercus Plant,
has similar mineralogy to the Palacios and Sageras mineralisation and appears
likely to assist in maintaining a relatively low level of capital expenditure
going forward.
We have now commenced detailed metallurgical test work related to Phase 2 which
is based on developing both the Retortillo and Alameda South Deposits as
separate feed sources of concentrate following initial on-site treatment.
It is not anticipated that this additional metallurgical test work will impact
on plans to recommence mining operations at Salamanca, currently targeted for
the end of 2012."
Enquiries - Managing Director: Ian Stalker Tel: +34
608 221 497
RBC Capital Markets: Martin Eales Tel:
+44 20 7029 7881
Introduction
The Salamanca Uranium Project consists of four separate areas containing a
number of metasedimentary hosted uranium deposits located in the western part of
the Salamanca Province in Spain. These deposits are near surface accumulations
of open pittable uranium within close proximity to the Quercus uranium ore
processing plant.
Berkeley commenced a Feasibility Study in 2009 which was initially focused on
the Águila (Palacios and Sageras deposits) but has now been extended to include
the Alameda (Alameda South deposit) and Retortillo (Retortillo and Santidad
deposits) areas.
In February 2010, 2,000kg of representative samples taken from diamond drill
core was sent to the SGS Metallurgical Laboratories in Perth, Australia for a
comprehensive metallurgical test work campaign supervised by Aker Solutions and
Orway Mineral Consultants (WA) Pty Ltd. The material was selected on the basis
of lithology, oxidation and grade from the Sageras, Palacios and Alameda South
deposits (Table 1).
+----------+---------+--------+------+--------+------+-------+--------+
| Metallurgical test work sample composition- PALACIOS - |
| SAGERAS - ALAMEDA |
+---------------------------------------------------------------------+
| Deposit |Average | Grade of oxidation | | |
| name | grade | | | |
+----------+---------+-------------------------------+-------+--------+
| Hole | (ppm | partially | primary |TOTAL | % |
| ID's | U3O8) | oxidized | | | |
+----------+ +---------------+---------------+-------+ +
| | |weight | % |weight | | % |weight |
| | | (kg) | | (kg) | | | (kg) |
+----------+---------+--------+------+--------+------+-------+--------+
|PALACIOS | 200 - | 199 | 33% | 75 | 12% | 274 | 45% |
| | 300 | | | | | | |
+----------+---------+--------+------+--------+------+-------+--------+
| Holes | 300 - | - | - | 75 | 12% | 75 | 12% |
|1-2-5-12 | 500 | | | | | | |
+----------+---------+--------+------+--------+------+-------+--------+
| | > 500 | 263 | 43% | - | - | 263 | 43% |
+----------+---------+--------+------+--------+------+-------+--------+
| | | 462 | 76% | 150 | 24% | 612 | 100% |
+----------+---------+--------+------+--------+------+-------+--------+
| | | | | | | | |
+----------+---------+--------+------+--------+------+-------+--------+
| SAGERAS | | | | | | | |
+----------+---------+--------+------+--------+------+-------+--------+
| Holes | 200 - | 71 | 11% | 149 | 21% | 220 | 32% |
| 1-3-5 | 300 | | | | | | |
+----------+---------+--------+------+--------+------+-------+--------+
| | 300 - | 190 | 27% | - | | 190 | 27% |
| | 500 | | | | | | |
+----------+---------+--------+------+--------+------+-------+--------+
| | > 500 | 141 | 20% | 148 | 21% | 289 | 41% |
+----------+---------+--------+------+--------+------+-------+--------+
| | | 402 | 58% | 297 | 42% | 699 | 100% |
+----------+---------+--------+------+--------+------+-------+--------+
| | | | | | | | |
+----------+---------+--------+------+--------+------+-------+--------+
| ALAMEDA | | | | | | | |
+----------+---------+--------+------+--------+------+-------+--------+
| Hole 3 | 200 - | 172 | 27% | - | - | 172 | 27% |
| | 300 | | | | | | |
+----------+---------+--------+------+--------+------+-------+--------+
| | 300 - | 214 | 33% | - | - | 214 | 33% |
| | 500 | | | | | | |
+----------+---------+--------+------+--------+------+-------+--------+
| | > 500 | 257 | 40% | - | - | 257 | 40% |
+----------+---------+--------+------+--------+------+-------+--------+
| | | 643 |100% | - | - | 643 | 100% |
+----------+---------+--------+------+--------+------+-------+--------+
| | | 1508 | | 447 | | 1954 | 100% |
| | | kg | | kg | | kg | |
+----------+---------+--------+------+--------+------+-------+--------+
Table 1 - Metallurgical Test Work Samples
Current Work
The primary objective of the Phase 1 metallurgical test work currently being
undertaken at SGS is to optimise the process conditions for treating the uranium
ore lithologies at Sageras and Palacios in a tank leach configuration. The
results of the current work will be used for the re-commissioning of the Quercus
Processing Plant at a capacity of 2.1Mlbs (0.95 Kt) of U3O8 per annum.
Phase 2 of metallurgical test work has also commenced with the objective to
undertake test work on uranium ore lithologies from the satellite deposits of
Alameda South and Retortillo. This additional test work is examining uranium
concentration by either flotation or heap leaching and ion exchange with
possible eluate or resin transfer.
The Phase 1 test work campaign commenced in March 2010 and is scheduled to be
completed in the 3rd quarter 2010 with the following test work in progress:
· Preliminary mineralogy on the various ore types;
· Communition (crushing & grinding);
· Preliminary ore sorting;
· Flotation;
· Tank leaching;
· Heap leaching;
· Thickening and filtration;
· Solvent extraction;
· Geotechnical and geochemical testing of the final process residues, and
· Effluent neutralisation.
Initial Results
The current dynamic leach test work has delivered uranium extraction rates in
excess of 93% at Palacios and 87% at Sageras. All the tests to date have used a
coarse grind to the leach feed of P80 (750 microns) with the aim of minimising
energy requirements in the comminution circuit.
The leach times to achieve these extraction rates are relatively short from 6
hours at Palacios to 12 hours at Sageras.
The reagent consumption is low at Sageras which consumes 15 - 20 kg of acid per
tonne of ore and approximately double this at Palacios.
The tank leach test work completed to date has supported the conceptual flow
sheet using a relatively simple acid leach process common to many existing
uranium mines.
The Alameda South static heap leach test work program has commenced with a suite
of bottle roll leach tests as a precursor to future column tests. The
preliminary results are encouraging with extractions ranging up to 91% and acid
consumptions varying between 17 and 24 kg/tonne. These tests are continuing and
a comprehensive program of column leaching is planned to determine optimum leach
parameters.
Future Work
Phase 1 of the tank leach test work program is expected to be completed in the
3rd quarter 2010. Future work in the Phase 1 program of test work is aimed at:
· Optimising the ore sorting process.
· Determining optimal process conditions in dynamic leaching.
· Confirming the agitation system for a coarse grind to be employed in the
leach circuit.
· Optimising equipment selection for separating the leach residue from the
uranium rich leach liquors.
· Confirming requirements for a pre-concentration of liquors prior to
solvent extraction.
Additional representative drill core is currently being selected prior to
shipping to SGS for Phase 2 in order to better understand the communition and
ore sorting requirements and to provide additional material for column leach and
flotation test work.
The column leach and flotation test work will extend into 2011 with a view to
identifying the optimal concentration process for the satellite deposits of
Alameda South and Retortillo.
Preliminary engineering design will commence in June 2010 to develop the process
engineering data for the study.
A full version of this announcement including images can be downloaded from
Berkeley's website at www.berkeleyresources.com.au.
This information is provided by RNS
The company news service from the London Stock Exchange
END
MSCEAKKXESXEEEF
Grafico Azioni Berkeley Energia (LSE:BKY)
Storico
Da Giu 2024 a Lug 2024
Grafico Azioni Berkeley Energia (LSE:BKY)
Storico
Da Lug 2023 a Lug 2024