Firering Strategic
Minerals plc / EPIC: FRG / Market: AIM / Sector: Mining
28 August 2024
Firering Strategic Minerals plc
("Firering" or "the
Company")
Quicklime Operational Update
Rapidly advancing lime plant
refurbishment
Firering Strategic Minerals plc, an emerging
quicklime production and critical mineral exploration company, is
pleased to announce an operational update with regards to its
quicklime project in Zambia ("Limeco"), which is being refurbished
with the goal of commencing phased production during Q4 this
year.
HIGHLIGHTS
Engineering work at
quicklime plant advancing:
· New kiln feed
conveyor belt installed and commissioned.
· New brakes
installed at skip hoist motor.
· Rebricking of
damaged areas and repairing damaged bridges inside Kiln 1
completed.
· Widening of
the discharge end of Kiln 1 completed.
· Foundation
work for the first gasifier almost complete.
· Excavation
work for coal storage facility commenced.
· First of two
gasifiers on its way to Limeco; each gasifier supports 4 kilns.
· Several dry
runs completed successfully.
Crushing plant
modifications fully operational:
· Double roll
crusher replaced with impact crusher.
· Flow sheet
partially optimised for efficient production of kiln feedstock in
the right size fraction.
· Crushing of
the correct quality limestone commenced to build a kiln feed pile
ahead of firing Kiln 1 in Q4 of 2024.
· Waste
stockpile renamed 'secondary stockpile' due to finding large
quantities of good material suitable for kiln feed.
On-site laboratory
operational:
· All new
laboratory equipment arrived on site and installed.
· Testwork
focusing on calcium carbonate ("CaCO3") and quicklime
("CaO") content with high purity levels achieved.
· Purity level
specifications are required as part of ongoing discussions with
off-takers.
Yuval Cohen, Chief
Executive of Firering and Limeco, said: "I am very pleased with the progress being
made at Limeco where engineers are rapidly completing the
modifications to the lime plant. Key to this plan has been the
manufacturing of the coal gasifier parts, which are now on their
way to Limeco having left the Port of Mundra, India, on 23 August
2024. Notably, work on the gas ducting required to convey the hot
gas from the gasifier to the kilns has also
started.
"Having replaced
the double roll crusher with an impact crusher, the crushing plant
is performing well and being used to build a kiln feed pile of the
right quality limestone with a size fraction of -90mm to 60mm.
Undersize of -60mm is guided back to the triple deck screen
and split into three different aggregate streams for sale to our
customers.
"Major progress has
also been made at Limeco's onsite laboratory with the arrival of
all outstanding test equipment. Accordingly, testwork to understand
the impact of the different limestone qualities and burning times
on the production of quicklime is in full swing with encouraging
initial results showing high available quicklime
content.
"I look forward to
further updating the market on the arrival of our first gasifier
and subsequent installation and commissioning of the system and the
firing of our first kiln using this new system during Q4
2024."
DETAILS
Lime
plant
A new conveyor belt has been installed (Figure 1)
that will feed crushed limestone to the skip hoist, which
transports the materials to a 25t hopper at the top of the lime
plant. From there, the limestone will be fed first to Kiln 1 and
later, once operational, to Kiln 2.
Figure 1: View of newly installed conveyor belt
(left) and feeding arrangement into skip hoist (right).
Two new brakes for the skip hoist motor arrived on-site in early
August 2024 and have since been installed (Figure 2), replacing the
original single brake. Brake testwork is planned for September
2024.
Figure 2: View of newly installed brakes for the skip
hoist motor.
Repair work inside Kiln 1 has been completed
including the repair of cracks, burner port, the bridge and arches
underneath the bridge. Additionally, foundation work for the first
gasifier is advancing (Figure 3) with the last rebar reinforcement
being installed and final concrete of 1050mm poured by the first
week of September 2024.
Figure 3: Preparation work at gasifier foundation ahead of final
concrete pour.
Excavation work for the coal storage facility that will hold the
coal stock that will be fed to the gasifier has commenced (Figure
4).
Figure 4: View of excavation work at coal storage
facility.
Crushing
plant
The new impact crusher arrived at Limeco in May and
has been successfully installed (Figure 5). The primary stockpile
feed first goes through the primary crusher before being processed
by the impact crusher. The resulting material is then directed to a
double-deck screen, with -90mm to 60mm fractions conveyed to the
kiln feed pile (Figures 6 and 7), and undersized material (-60mm)
sent to a triple-deck screen for sorting into three aggregate
streams for Limeco's clients.
Figure 5: View of the newly installed impact
crusher.
Figure 6: Belt feeding the -90mm to
60mm size fraction to the kiln feed pile.
Figure 7: View of the kiln feed stockpile.
The stockpile near the quarry, originally referred to
as the waste stockpile, was opened up for further examination to
assess its contents. Observations (Figure 8) and testwork on
samples from this stockpile revealed that a large portion comprises
good quality limestone suitable for kiln feed. As a result, the
stockpile has been renamed 'secondary' stockpile with the 'primary'
stockpile located near the ramp leading to the jaw crusher.
Figure 8: View of good quality oversize on the
'secondary' stockpile and lime plant.
Laboratory
Limeco's laboratory has received all outstanding
equipment required to carry out testwork and populate a database
for its limestone qualities. Figure 9 shows part of the
laboratory equipment and the new oven that was recently
installed.
As part of ongoing discussions with off takers,
purity level specifications are required. Accordingly, Limeco's
laboratory staff successfully produced the first 10kg of quicklime,
part of which will be sent to an external accredited laboratory for
independent analysis (Figure 10).
Figure 9: View of some of the lab equipment (left)
and new oven (right).
Figure 10: Laboratory staff showing the first 10kg of
quicklime produced at the lab.
Issue of
Equity
Application will be made to the London Stock Exchange
for the admission of a total of 454,545 ordinary shares of €0.001
each ("Ordinary Shares") issued to an adviser at an issue price of
3.3 pence in settlement of fees for services provided of £15,000
("Admission"). It is expected that Admission will become effective
on or around 4 September 2024. Following Admission, the Company's
issued share capital will consist of 184,246,077 Ordinary Shares
which may be used by shareholders as the denominator for the
calculations by which to determine if they are required to notify
their interest in, or a change to their interest in, the Company
under the FCA's Disclosure Guidance and Transparency Rules.
THIS ANNOUNCEMENT CONTAINS INSIDE INFORMATION AS STIPULATED
UNDER THE UK VERSION OF THE MARKET ABUSE REGULATION NO 596/2014
WHICH IS PART OF ENGLISH LAW BY VIRTUE OF THE EUROPEAN (WITHDRAWAL)
ACT 2018, AS AMENDED. ON PUBLICATION OF THIS ANNOUNCEMENT VIA
A REGULATORY INFORMATION SERVICE, THIS INFORMATION IS CONSIDERED TO
BE IN THE PUBLIC DOMAIN.
*** ENDS ***
For further information visit www.fireringplc.com or
contact:
Firering Strategic
Minerals
Yuval Cohen
|
E:
info@firering-holdings.com
|
SPARK Advisory
Partners Limited (Nominated Adviser)
Neil Baldwin / James Keeshan / Adam Dawes
|
T: +44 20 3368 3550
|
Optiva Securities
Limited (Joint Broker)
Christian Dennis / Daniel Ingram
|
T: +44 20 3137 1903
|
Shard Capital
Partners LLP (Joint Broker)
Damon Heath / Erik Woolgar
|
T: +44 20 7186 9950
|
St Brides Partners
Limited (Financial PR)
Isabel de Salis / Susie Geliher
|
E: firering@stbridespartners.co.uk
|
Notes
Firering Strategic Minerals plc is an AIM-listed
resource company set to commence commissioning its significant
quicklime project in Zambia in Q4 2024 to produce 600-800 tonnes of
quicklime per day along with ancillary products. With over US$100
million in historical investment, the project is strategically
positioned to support the expanding copper producers in the Zambian
Copper Belt, which are currently reliant on imported quicklime from
South Africa. Firering currently holds an SPA over a 20.5%
stake in Limeco Resources Limited ("Limeco") with 10% already paid
and an option to increase this to 45%. Additionally, the Company is
advancing the Atex Lithium-Tantalum Project in northern Côte
d'Ivoire, an exploration project rich in lithium and
tantalum-niobium, with drilling results indicating significant
resource potential in this established mining jurisdiction.