Q1 2024 Production Report
Kenmare Resources plc
(“Kenmare” or “the Company” or “the Group”)
11 April 2024
Q1 2024 Production Report
Kenmare Resources plc (LSE:KMR, ISE:KMR), one of
the leading global producers of titanium minerals and zircon, which
operates the Moma Titanium Minerals Mine (the "Mine" or "Moma") in
northern Mozambique, is pleased to provide a trading update for the
quarter ending 31 March 2024 (“Q1 2024”).
Statement from Michael Carvill, Managing
Director:
“Our team at the Moma Mine has now worked
for over six months without incurring a Lost Time Injury and I
would like to congratulate all of our employees for this
exceptional achievement.
Production in Q1 was in line with our
expectations and consistent with guidance. We anticipate production
will strengthen through the rest of the year, due to a stronger
grade profile and typically fewer seasonal power
interruptions.
The markets for our products were
encouraging in Q1, with stronger than expected demand, particularly
for ilmenite. This was driven by recovering titanium pigment demand
and the continued growth of the titanium metal market.”
Overview
- Improved Lost Time Injury Frequency
Rate (“LTIFR”) of 0.09 per 200,000 hours worked on a 12-month
rolling basis (Q1 2023: 0.15) and zero Lost Time Injuries (“LTIs”)
in Q1 2024
- Heavy Mineral Concentrate (“HMC”)
production in Q1 2024 of 316,400 tonnes, in line with Q1 2023
(315,000 tonnes)
- Ilmenite production of 205,500
tonnes, in line with Q1 2023 (204,300 tonnes)
- Reduced production of other
finished products due to significant maintenance work underway in
the Mineral Separation Plant (“MSP”), including primary zircon
production of 8,300 tonnes (Q1 2023: 11,400 tonnes), rutile
production of 1,500 tonnes (Q1 2023: 1,700 tonnes), and
concentrates production of 9,600 tonnes (Q1 2023: 10,100
tonnes)
- Total shipments of 242,900 tonnes
in Q1 2024, down 11% on Q1 2023 (271,700 tonnes), excluding
approximately 34,000 tonnes that were loaded in Q1 but shipped in
Q2
- Encouraging product market
conditions in Q1 2024, with higher than expected demand, and
Kenmare has a strong order book for Q2
-
As announced on 15 March 2024, Managing Director Michael Carvill
will step down from his executive role and Board position later
this year – a process to appoint his successor is underway
- Kenmare is on track to achieve its
2024 guidance, with production still expected to be weighted
towards the second half of the year
Operations update
Operational results from the Moma Mine in Q1
2024 were as follows:
|
Q1 2024 |
Q1 2023 |
Variance |
Q4 2023 |
Variance |
tonnes |
tonnes |
% |
tonnes |
% |
Excavated ore1 |
9,215,000 |
9,258,000 |
0% |
9,348,000 |
-1% |
Grade1 |
4.15% |
4.13% |
0% |
4.83% |
-14% |
Production |
|
|
|
|
|
HMC production |
316,400 |
315,000 |
0% |
399,800 |
-21% |
HMC processed |
307,800 |
314,800 |
-2% |
399,800 |
-23% |
Ilmenite |
205,500 |
204,300 |
1% |
269,600 |
-24% |
Primary zircon |
8,300 |
11,400 |
-27% |
14,000 |
-41% |
Rutile |
1,500 |
1,700 |
-12% |
2,100 |
-29% |
Concentrates2 |
9,600 |
10,100 |
-5% |
10,500 |
-9% |
Shipments |
242,900 |
271,700 |
-11% |
324,900 |
-25% |
- Excavated ore and grade prior
to any floor losses.
- Concentrates include secondary
zircon and mineral sands concentrate.
In late February 2024, Kenmare passed three
million hours worked without an LTI. No LTIs were incurred in Q4
2023 or Q1 2024 and the Company’s rolling 12-month LTIFR improved
to 0.09 per 200,000 hours worked (31 March 2023: 0.15).
HMC production in Q1 2024 was 316,400 tonnes, in
line with Q1 2023 (315,000 tonnes), due to seasonal power
interruptions as a result of the southern hemisphere rainy season.
The cumulative impact of the power interruptions in Q1 2024 was
greater than the downtime caused by the severe lightning strike in
February 2023 and materially exceeded the average impact on
operations experienced during the first quarter of the past five
years. Production of HMC, and consequently all finished products,
was lower in Q1 2024 than in the previous quarter due primarily to
expected lower ore grades.
HMC processed in Q1 2024 was 307,800 tonnes, a
2% decrease compared to Q1 2023 (314,800 tonnes). HMC processed was
3% lower (8,600 tonnes) than HMC produced in Q1 due to significant
maintenance work taking place in the MSP. The aim of this work was
to address underperformance in various circuits, so HMC was held
back from processing until the work was completed. Another
contributing factor to the lower HMC processed was the reliability
of one of the four engines in the Rotary Uninterruptible Power
Supply (“RUPS”). All four engines were working for over 60% of the
quarter, however for the periods without the fourth engine, the
RUPS’ ability to mitigate power interruptions was reduced. An
investigation is underway to determine the repair time for the
fourth engine.
Ilmenite production in Q1 2024 was 205,500
tonnes, in line with Q1 2023 (204,300 tonnes). Ilmenite production
benefitted from the processing of intermediate stockpiles,
offsetting the slight reduction in HMC processed. Intermediate
stockpiles are comprised of partially processed materials in the
MSP that have not yet been fully separated into one of Kenmare’s
four product streams. The Company draws on this material to
optimise the separation process in the MSP.
Primary zircon production was 8,300 tonnes in Q1
2024, a 27% decrease on Q1 2023 (11,400 tonnes), due to challenges
in the zircon circuit. This resulted in lower recoveries and higher
than usual quantities of material being sent to the intermediate
stockpiles, which will be processed in the coming quarters.
Rutile production was 1,500 tonnes, a 12%
decrease (Q1 2023: 1,700 tonnes), and concentrates production was
9,600 tonnes, a 5% decrease (Q1 2023: 10,100 tonnes). These product
streams were impacted by the same challenges in the MSP.
Concentrates production benefitted from lower recoveries in primary
zircon and rutile production.
At the end of Q1, Kenmare is on track to achieve
its 2024 guidance on all stated metrics. Production is forecast to
strengthen from Q2 onwards due to improved power stability in the
dry season and higher expected grades in H2.
Shipments were 242,900 tonnes in Q1 2024, down
11% compared to Q1 2023 (271,700 tonnes). However, an additional
34,000 tonnes that were loaded in March are not included as the
shipments were not completed until early April, so these tonnes
will be reflected in the Q2 shipment volumes. If these additional
tonnes are taken into consideration, Q1 2024 shipments are in line
with Q1 2023. Shipments were comprised solely of ilmenite during
the quarter.
Closing stock of HMC at the end of Q1 2024 was
25,300 tonnes, compared with 16,700 tonnes at year-end 2023. This
stock build was due to the difference between HMC produced and HMC
processed in the quarter, as a result of maintenance work in the
MSP. Closing stock of finished products at the end of Q1 2024 was
241,800 tonnes (Q4 2023: 259,100 tonnes), including the 34,000
tonnes of shipments that completed in early April.
Capital projects
Preparations continue for the upgrade of Wet
Concentrator Plant (“WCP”) A ahead of its transition to the large
Nataka ore zone. WCP A will complete its current mine path in
Namalope in late 2025 and then mine its way to Nataka, where it
will operate for the remainder of its economic life. Nataka
represents over 70% of Moma’s Mineral Resources and transitioning
WCP A to this ore zone is key to securing production from Moma for
decades to come.
The upgrade of WCP A consists of three key
elements and their status is as follows:
1) Replacing
existing two dredges with new, higher capacity dredges – new
dredges ordered in September 2023 and fabrication commenced in Q1
2024
2) Installing
upfront desliming circuit to more effectively manage slimes at
Nataka – fabrication of desliming circuit commenced in early Q1
2024
3) Introduction
of a Tailings Storage Facility (“TSF”) to replace complex paddock
system – detailed design of TSF is underway and community
engagement is in progress
The Definitive Feasibility Study for the additional infrastructure
for WCP A’s transition to Nataka remains on track to be completed
in Q2 2024. Work is also continuing on the Pre-Feasibility Study
for Congolone, a potential future growth opportunity for Kenmare,
and this is also scheduled for completion in Q2.
Market update
The market for Kenmare’s products was robust in
Q1 2024, with stronger than expected demand, particularly for the
Company’s ilmenite products. Spot prices for ilmenite have been
stable since early Q4 2023, however average received prices were
lower in Q1 compared to the previous quarter. This was due to lower
contracted prices reflecting the softer market conditions in H2
2023.
Demand from the titanium pigment industry
rebounded more strongly than expected in Q1 2024. Pigment producers
ramped up production in response to an improving sales outlook,
most notably in Europe and North America, and ilmenite inventories
are at low levels. Demand for titanium feedstocks from the titanium
metal sector remains strong.
Supply of titanium feedstocks remains at a high
level but production disruptions due to the suspension of some
operations in Mozambique and Sierra Leone are causing uncertainty
in the market.
The zircon market has shown some positive signs
of recovery following the Lunar New Year. Supply of high-quality
products is constrained, leading to stronger prices in the spot
market. This has been supported by growing demand in India, however
demand in Europe remains relatively weak.
Kenmare has a strong order book for Q2 2024 and
expects to continue to draw down product inventories to meet this
demand.
Corporate update
As announced on 15 March 2024, Managing Director
Michael Carvill will step down from his executive role and Board
position later this year. Subject to re-appointment at the
Company’s Annual General Meeting on 10 May 2024, it is expected
that Michael will remain on the Board and in his executive role
until the Company’s Interim Results in August. Following this, and
to support an orderly transition process, Michael will continue to
be available to the Company in a consultancy capacity until at
least the end of 2024.
Kenmare’s Nomination Committee has commenced a
process to appoint Michael’s successor and will consider both
internal and external candidates. The result of this process will
be announced in due course.
For further information, please contact:
Kenmare Resources plc
Jeremy Dibb / Katharine Sutton / Michael Starke
Investor Relations
ir@kenmareresouces.com
Tel: +353 1 671 0411
Mob: +353 87 943 0367 / +353 87 663 0875
Murray (PR advisor)
Paul O’Kane
pokane@murraygroup.ie
Tel: +353 1 498 0300
Mob: +353 86 609 0221
About Kenmare Resources
Kenmare Resources plc is one of the world's
largest producers of mineral sands products. Listed on the London
Stock Exchange and the Euronext Dublin, Kenmare operates the Moma
Titanium Minerals Mine in Mozambique. Moma's production accounts
for approximately 7% of global titanium feedstocks and the Company
supplies to customers operating in more than 15 countries. Kenmare
produces raw materials that are ultimately consumed in everyday
quality-of life items such as paints, plastics and ceramic
tiles.
All monetary amounts refer to United States dollars unless
otherwise indicated.
Forward Looking Statements
This announcement contains some forward-looking
statements that represent Kenmare's expectations for its business,
based on current expectations about future events, which by their
nature involve risks and uncertainties. Kenmare believes that its
expectations and assumptions with respect to these forward-looking
statements are reasonable. However, because they involve risk and
uncertainty, which are in some cases beyond Kenmare's control,
actual results or performance may differ materially from those
expressed or implied by such forward-looking information.
Grafico Azioni Kenmare Resources (LSE:KMR)
Storico
Da Dic 2024 a Gen 2025
Grafico Azioni Kenmare Resources (LSE:KMR)
Storico
Da Gen 2024 a Gen 2025