VANCOUVER, BC, Feb. 20, 2024 /PRNewswire/ -- (TSX: LUC) (BSE:
LUC) (Nasdaq Stockholm: LUC)
Lucara Diamond Corp. ("Lucara" or the "Company") today reports
its results for the year and quarter ended December 31, 2023. All amounts are in U.S.
dollars unless otherwise noted. View PDF
FISCAL 2023 HIGHLIGHTS
- The recovery of a 1,080 carat Type IIA white gem quality
diamond in August 2023, followed by a
recovery of a 692 carat Type IIA diamond later in the month. The
fourth +1000 carat stone recovered from the Karowe Mine.
- The Karowe Mine recorded record plant throughput of 2.8 million
tonnes milled for the year.
- In January 2024, the successful
execution of an amended project financing debt package of
$220 million to amend the repayment
profile in line with the rebase schedule released in July 2023 for the Karowe Underground Project
("UGP").
- On February 18, 2024, the Company
announced the signing of a new definitive sales agreement ("NDSA")
with HB Trading BV ("HB") in respect of all qualifying diamonds
produced in excess of 10.8 carats in size from the Karowe
Mine.
- Total revenue of $177.4 million
for 2023, in line with revised guidance.
- Cash flow generated from operating activities of $63.4 million for 2023.
- 2023 operating cash cost of $28.75 per tonne of ore
processed(1).
- Investment of $101.3 million in
the Karowe UGP in 2023. Significant sinking progress was made in
both the production and the ventilation shafts during the second
half of 2023.
William Lamb, President & CEO commented: "2023 was a
challenging year for Lucara. Although mining activities in the open
pit continued to show ongoing sustainable improvements, including
record production through the mill, the development on the UGP
experienced delays in the early part of the year. Positive progress
was made in the sinking of both the production and the ventilation
shafts resulting in both shafts starting lateral development at the
670 level at the end of the year. The Company has dedicated
significant effort and resources to focus on the UGP as this
project represents a very exciting and valuable future for
Lucara.
The diamond market in general remains a volatile environment
with market challenges coming from multiple areas. Lucara remains
well positioned to meet these market challenges head on due to its
unique high value production mix and its ability to provide
provenance for its diamonds through its well-defined sales
channels. Our sales strategy which focuses on gaining access to the
upstream value chain from polished diamonds is well aligned to the
strategies of the Government of the Republic of Botswana. The Company aims to continue working
toward long-term sustainable business practices to provide value
for all our stakeholders."
(1) See "Non-IFRS
Financial Performance Measures"
|
REVIEW FOR THE YEAR ENDED DECEMBER 31,
2023
- Operational highlights from the Karowe Mine for 2023 included:
- Ore and waste mined of 2.7 million tonnes ("Mt") (2022: 3.3Mt)
and 3.1 million tonnes (2022: 1.5Mt), respectively.
- 2.8 million tonnes (2022: 2.8Mt) of ore processed.
- A total of 395,134 carats recovered, including 18,509 carats
from the processing of historic recovery tailings, (2022: 335,769
carats) at a recovered grade of 13.2 carats per hundred tonnes
("cpht") of direct milled ore (2022: 12.1 cpht).
- A total of 602 Specials (stones larger than 10.8 carats in
size) were recovered, with 22 diamonds greater than 100 carats
including five diamonds greater than 300 carats.
- Recovered Specials equated to 5.3% of the total recovered
carats from ore processed during 2023 (2022 – 7.2%).
- The Karowe Mine has operated continuously for over three years
without a lost time injury.
- Financial highlights for 2023 included:
- Revenues of $177.4 million (2022:
$212.9 million) achieved despite a
weaker rough diamond market. Fourth quarter pricing stabilized in
smaller goods and increases of 5% were observed compared to the
third quarter of 2023, albeit approximately 19% below prices
observed in the fourth quarter of 2022. Revenue reflects the
weighting of Lucara's revenue towards larger goods where pricing
was observed to be more stable. The performance further reflects
the increased volume of material processed from the North and
Centre lobes in the first half of the year. During 2023, 26% of the
carats processed were recovered from the Centre Lobe, 3% from the
North Lobe and 71% were recovered from South Lobe ore (2022: 100%
South Lobe ore). In comparison to the revenue earned in 2022,
current year revenues reflected a more diverse product mix with a
return to Centre and North Lobe processing during the year.
- Operating margins of 56% were achieved (2022: 63%). A strong
operating margin continues to be achieved through cost reduction
initiatives assisted by a strong U.S. dollar.
- Adjusted EBITDA(1) was $54.4
million (2022: $86.7 million),
with the decrease attributable to the change in revenue.
- Net loss was $20.2 million (2022:
net income of $40.4 million),
resulting in a loss per share of $0.04 (2022: earnings of $0.09). The change to a net loss is due to the
decrease in revenue, an impairment of intangible assets, and a
significant non-cash deferred tax expense as the investment in the
underground expansion project continues.
- The Company identified an impairment indicator for the
Company's Clara sales platform and completed an impairment test
based on the fair value less cost of disposal expected to be
derived from the platform. An impairment was recognized on the
intangible asset by $11.2 million in
Q4 2023.
- Cash flow from operating activities was $63.4 million (2022: $96.2
million).
(1) See "Non-IFRS
Financial Performance Measures"
|
- During 2023, the Company invested $101.3
million into the Karowe UGP, including capitalized borrowing
costs:
- Shaft sinking, lateral development and grouting programs were
the focus in both the ventilation and production shafts in Q4 2023.
At the end of 2023, the production and ventilation shafts were both
at 348 metres below collar or 666 metres above sea level ("masl")
and the process of establishing the first shaft stations and
lateral connection between the two shafts (670 level) had
commenced.
- During Q4 2023, the ventilation shaft sank 76 metres, the 718
slinging cubby was completed, the 670-level station catwalk was
established and the lateral station development commenced. Total
lateral development in Q4 2023 was 97 metres. During the quarter,
development equipment, including a Kubota, a Sandvik DD321 boom
jumbo drill and a Caterpillar R1300G 7-tonne load, haul, dump unit
were mobilized at the 670-level for lateral development mining.
Sinking and lateral development was in the Thlabala mudstones in
dry conditions.
- Production shaft activities included sinking a total of 114
metres and establishing the 670-level station catwalk and
initiating lateral development. A total of 30 metres of lateral
development was completed.
- Commissioning of the temporary bulk air coolers at each shaft
was completed and construction of the permanent bulk air coolers at
the production shaft continued.
- Detailed engineering and fabrication of the permanent men and
materials winder commenced during the quarter, representing the
last major component for the permanent winders.
- Cash position and liquidity at December
31, 2023:
- Cash and cash equivalents of $13.3
million.
- Working capital deficit (current assets less current
liabilities) of $16.6 million.
- Cost overrun facility ("COF") of $18.6
million.
- $90.0 million drawn on the
$170.0 million Project Loan ("Project
Loan") for the Karowe UGP.
- $35.0 million drawn on the
$50.0 million working capital
facility ("WCF").
- On January 9, 2024, the Company
announced that it had signed amended documentation in relation to
the senior secured project financing debt package of $220.0 million (the "Facilities") executed in
July 2021 (the "Rebase Amendments").
The project facility portion had been increased from $170.0 million to $190.0
million, while the working capital facility had been
decreased from $50.0 million to
$30.0 million. While the total
quantum of the Facilities has not changed, the repayment profile
has been extended in line with the rebase schedule released on
July 17, 2023, and the maturity of
the WCF has been extended to June 30,
2031.
- During 2023, the Company announced the appointment of William
Lamb as Chief Executive Officer, effective August 17, 2023, and Glenn Kondo, as Chief Financial Officer,
effective January 1, 2024. Eira
Thomas and Zara Boldt departed
during 2023.
DIAMOND MARKET
The long-term outlook for natural diamond prices remains
positive, anchored on improving fundamentals around supply and
demand as many of the world's largest mines reach their end of
life. Currently, slower than anticipated economic growth in
China and a voluntary import ban
on rough diamonds into India in Q4
2023 dampened the recovery of rough diamond prices towards the end
of 2023. Changes in global economic conditions, consumer demand,
geopolitical events, and industry-specific dynamics resulted in a
challenging market in 2023 with reduced demand and downward
pressure on both polished and rough diamond pricing, especially in
the smaller size classes. Restricted supply by the largest
producers towards the end of 2023, together with the Group of Seven
discussions surrounding sanctions on rough diamonds from
Russia, resulted in low levels of
price recovery at the end of 2023.
Sales of lab-grown diamonds increased steadily through 2023 with
many smaller retail outlets increasingly adopting these diamonds as
a product. Lab-grown stones have established themselves in the
marketplace and is expected to continue to take up increasing
market share in the smaller to medium sized goods over time. The
longer-term market fundamentals for natural diamonds remain
positive, pointing to continued price growth as demand is expected
to outstrip future supply, which is now declining globally.
2024 OUTLOOK
This section of the press release provides management's
production and cost estimates for 2024. These are "forward-looking
statements" and subject to the cautionary note regarding the risks
associated with forward-looking statements. Diamond revenue
guidance does not include revenue related to the sale of
exceptional stones (an individual rough diamond which sells for
more than $10 million), or the
Sethunya. No changes have been made to the Company's Guidance which
was released in November 2023.
Karowe Diamond
Mine
|
2024
|
In millions of U.S.
dollars unless otherwise noted
|
Full Year
|
Diamond revenue
(millions)
|
$220 to $250
|
Diamond sales
(thousands of carats)
|
345 to 375
|
Diamonds recovered
(thousands of carats)
|
345 to 375
|
Ore tonnes mined
(millions)
|
2.8 to 3.2
|
Waste tonnes mined
(millions)
|
0.8 to 1.4
|
Ore tonnes processed
(millions)
|
2.6 to 2.9
|
Total operating cash
costs(1) including waste mined (per tonne
processed)
|
$28.50 to
$33.50
|
Underground
Project
|
Up to $100
million
|
Sustaining
capital
|
Up to $10
million
|
Average exchange rate –
Botswana Pula per United States Dollar
|
12.5
|
(1) Operating cash
costs are a non-IFRS measure. See "Non-IFRS Financial
Performance Measures".
|
DIAMOND SALES
Karowe diamonds are sold through three separate and distinct
sales channels, namely through the HB sales agreement, on the Clara
digital sales platform and through quarterly tenders.
SALES FOR +10.8 CARAT DIAMOND PRODUCTION FROM KAROWE
Karowe's large, high value diamonds have historically accounted
for approximately 60% to 70% of Lucara's annual revenues. In
September 2023, Lucara terminated the
definitive sales agreement executed with HB in November 2022 (for all +10.8 carat diamonds
recovered from Karowe) due to HB's material breach of its financial
commitments. The rough diamonds delivered to HB prior to the
termination of the agreement continued to be manufactured and sold
as polished diamonds. The Company retains a contractual right to
receive "top-up" payments from polished diamond sales for goods
delivered prior to the termination of the agreement. The Company
continued to sell its +10.8 carat production through this
established sales channels while it continued to work with the
management of HB on options for a new Diamond Sales Agreement which
is subject to pre-approval from the Government of the Republic of
Botswana.
For the three months ended December 31,
2023, the Company recorded revenue of $17.4 million from the HB arrangements (inclusive
of top-up payments of $6.8 million),
as compared to revenue of $24.1
million (inclusive of top-up payments of $3.6 million) for the three months ended
December 31, 2022. The fourth quarter
saw a reduction in the goods delivered to HB as a result of the
termination of the agreement at the end of the third quarter.
Revenue was affected by a 92% recovery factor achieved in 2023, 8%
below plan. Revenue in the fourth quarter was also affected by the
natural variability in the value of large stones recovered in any
given period. As a result of these factors, revenue from HB
decreased to 48% of total revenue recognized in the fourth quarter
of 2023 (Q4 2022 - 60%). The product mix in Q4 2023 was
predominantly from the South Lobe ore body, with some contribution
from the Centre Lobe (Q4 2022 – 100% South Lobe ore).
CLARA SALES PLATFORM
During Q4 2023, the sales volume transacted was $2.3 million (Q4 2022: $6.6 million), as lower volumes and lower valued
goods were placed for sale (due to the shift in product mix from
the Karowe Mine). Some sales are recognized on a net revenue
basis. A softer market was observed with the voluntary import
ban on rough diamonds into India
during the fourth quarter. Prices increased 5% overall in December
with a resumption of purchasing across most size categories;
however, prices remain lower than Q4 2022. Price stability
continues to be observed in the stones between 5 to 10.8 carats in
size.
QUARTERLY TENDER
A total of 108,137 carats were sold in the December 2023 tender, generating revenues of
$16.9 million or $156 per carat (Q4 2022 tender: $12.2 million from the sale of 76,264 carats or
$133 per carat). Rough diamond prices
saw a strong rebound in the fourth quarter of 2023 following the
significant decrease observed earlier in 2023 as market
fundamentals strengthened. A 19% increase from the third quarter
tender was observed owing to price increases and product mix
offered in the fourth quarter tender.
SUBSEQUENT EVENT
On February 18, 2024, the Company
announced the signing of a NDSA with HB in respect of all
qualifying diamonds produced in excess of 10.8 carats in size from
the Karowe Mine. The NDSA is subject to the approval of the
Company's project lenders. Upon such approval the agreement terms
will be effective retroactively from December 1, 2023. Since that time, Lucara has
continued to supply qualifying rough diamonds to HB in order to
fund its operations and the Karowe UGP.
KAROWE UNDERGROUND EXPANSION UPDATE
The Karowe UGP is designed to access the highest value portion
of the Karowe orebody, with initial underground carat production
predominantly from the highest value eastern magmatic/pyroclastic
kimberlite (south) ("EM/PK(S)") unit. The underground
expansion is expected to extend mine life to at least 2040.
On July 16, 2023, an update to the
Karowe UGP schedule and budget was announced (Press Release). This
update was initiated in response to slower than planned ramp up to
expected sinking rates in 2022, and, to account for time incurred
to complete grouting programs while mining through the
water-bearing geological zones. These chemical grouting programs
took longer than anticipated due to a combination of high-water
volumes in the sandstone lithologies between 870 and 752 metres
above sea level in depth (144 metres to 262 metres below the shaft
collar) and technical challenges associated with the transition to
main sinking.
The updated schedule incorporates a 28% increase in the duration
of construction, extending the anticipated commencement of
production from the underground from H2 2026 to H1 2028. The
revised forecast of costs at completion is $683.0 million (including contingency), a 25%
increase to the May 2022 estimated
capital cost of $547 million. The
forecasted increase of $136.0 million
in estimated capital to reach project completion is predominantly
related to increased schedule duration and related labour costs
(approximately 56% of the total increase), grouting costs
(approximately 20% of the total increase), with the balance of the
increase attributable to owner's costs, procurement, and indirect
project costs. As at December 31,
2023, capital expenditures of $310.5
million had been incurred and capital commitments of
$77.2 million had been
made.
During the year ended December 31,
2023, a total of $101.3
million was spent on the Karowe UGP development, capitalized
borrowing costs, surface infrastructure, grouting programs, and
ongoing shaft sinking activities. The following activities were
completed during Q4 2023:
- Main sinking in the production and ventilation shafts:
- The ventilation shaft reached 348 metres below collar, with a
planned final depth of 731 metres. The shaft is currently 61 metres
or approximately 26 days ahead of the July
2023 schedule update (combined vertical and lateral
metres).
- The production shaft reached 348 metres below collar, with a
planned final depth of 765 metres. The production shaft is 11
metres or approximately 24 days behind the July 2023 schedule update (combined vertical and
lateral) mainly due to an unscheduled grouting event in Q3 2024.
The production shaft is not on the project schedule critical
path.
- At the end of 2023, both shaft bottoms were at 348 metres below
collar (666 masl) having completed the first shaft stations at the
670-level and engaged in the start of 670-level lateral
development.
- During Q4 2023, the ventilation shaft sank 76 metres, completed
the 718 slinging cubby and established the 670-level station,
catwalk and was engaged in level development. Total lateral
developed in Q4 2023 was 97 metres. During the quarter, a Kubota,
Sandvik DD321 two boom jumbo drill and a Caterpillar RG1300G
7-tonne LHD were slung down in the ventilation shaft to the
670-level for lateral development mining.
- Production shaft activities included sinking a total of 114
metres and establishing the 670-level station, catwalk and
initiating lateral development. A total of 30 metres of lateral
development was completed.
- Commissioning of the temporary bulk air coolers at each shaft
was completed and construction of the permanent bulk air coolers at
the production shaft continued.
- Detailed engineering and fabrication of the permanent men and
materials winder commenced during the quarter, representing the
last major component for the permanent winders.
- Both shafts have completed sinking through the water-bearing
Ntane and Mosolotane sandstones. Sinking and lateral development
during the fourth quarter took place in the Thalbala mudstone in
dry conditions.
- Contract for fabrication of the permanent men and materials
winder was signed during the quarter, representing the last major
component for the permanent winders.
- Mining engineering advanced with a focus on supporting shaft
sinking, underground infrastructure engineering and finalizing
level plans.
- The impact of implementing a behavioural-based safety training
program, Safe Start®, in Q4 2022 has been evident in 2023. During
2023, the UGP achieved a twelve-month rolling Total Recordable
Injury Frequency Rate of 0.19. Project to date Total Recordable
Injury Frequency Rate at December 31,
2023 was 0.55.
The capital cost for the underground expansion in 2024 is
expected to be up to $100 million –
see "2024 Outlook". Activities for the Karowe UGP in Q1 2024 are
expected to include the following:
- Resumption of sinking within the ventilation and production
shafts.
- Completion of mining and construction activities on the 670
level station, including connection of the two shafts and
establishment of electrical substation, sump and de-watering pumps
and ventilation doors.
- Planned grouting events at the base of the Tlapana carbonaceous
shale and top of Mea formation is expected during the period in the
production shaft.
- Procurement of underground equipment, including dewatering
pumps, underground crush and convey systems and the permanent stage
winder.
- Commissioning of the permanent bulk air cooler system.
- Preparation of tender documents for the underground lateral
development work; and,
- Continuation of detailed design and engineering of the
underground mine infrastructure and layout.
FINANCIAL HIGHLIGHTS – Q4 2023
|
|
|
|
|
|
|
|
|
Three months
ended
December 31,
|
|
Year ended
December 31,
|
In millions of U.S.
dollars, except carats or otherwise noted
|
|
2023
|
2022
|
|
2023
|
2022
|
|
|
|
|
|
|
|
Revenues
|
$
|
36.5
|
42.5
|
$
|
177.4
|
212.9
|
Operating
expenses
|
|
(22.3)
|
(18.5)
|
|
(78.6)
|
(79.3)
|
Net income for the
period
|
|
(36.7)
|
7.1
|
|
(20.2)
|
40.4
|
Earnings per share
(basic and diluted)
|
|
(0.07)
|
0.02
|
|
(0.04)
|
0.09
|
Operating cash flow per
share(1)
|
|
0.00
|
0.03
|
|
0.11
|
0.19
|
Cash on hand
|
|
13.3
|
26.4
|
|
13.3
|
26.4
|
Cost overrun facility
(restricted cash)
|
|
18.6
|
-
|
|
18.6
|
-
|
Amounts drawn on
working capital facility(2)
|
|
35.0
|
15.0
|
|
35.0
|
15.0
|
Amounts drawn on
project finance facility
|
|
90.0
|
65.0
|
|
90.0
|
65.0
|
Karowe
Revenue
|
|
36.3
|
40.1
|
|
172.4
|
203.8
|
Carats sold
|
|
111,523
|
81,264
|
|
379,287
|
327,028
|
(1)
|
Operating cash flow
per share before working capital adjustments is a non-IFRS measure.
See "Use of Non-IFRS Performance Measures" below.
|
(2)
|
Excludes amounts
drawn from the Clara revolving credit facility.
|
QUARTERLY RESULTS OF OPERATIONS – KAROWE MINE,
BOTSWANA
|
UNIT
|
Q4-23
|
Q3-23
|
Q2-23
|
Q1-23
|
Q4-22
|
Sales
|
|
|
|
|
|
|
Revenues from the sale
of Karowe diamonds
|
US$M
|
36.3
|
56.2
|
38.6
|
41.3
|
40.1
|
Karowe carats
sold
|
Carats
|
111,523
|
111,673
|
72,717
|
83,374
|
81,264
|
Production
|
|
|
|
|
|
|
Tonnes mined
(ore)
|
Tonnes
|
607,101
|
869,188
|
682,636
|
541,400
|
484,705
|
Tonnes mined
(waste)
|
Tonnes
|
456,880
|
954,226
|
907,051
|
761,295
|
199,385
|
Tonnes processed
|
Tonnes
|
703,472
|
724,640
|
720,345
|
700,678
|
690,946
|
Average grade
processed(1)
|
cpht
(*)
|
14.0
|
13.6
|
12.6
|
12.8
|
12.5
|
Carats
recovered(1)
|
Carats
|
98,177
|
98,311
|
90,497
|
89,640
|
86,655
|
Costs
|
|
|
|
|
|
|
Operating cost per
tonne of ore processed(2)
|
US$
|
31.96
|
28.62
|
27.97
|
26.65
|
26.20
|
|
|
|
|
|
|
|
Capital
Expenditures
|
|
|
|
|
|
|
Sustaining capital
expenditures
|
US$M
|
8.0
|
3.2
|
2.4
|
0.8
|
9.9
|
Underground expansion
project(3)
|
US$M
|
28.0
|
20.3
|
22.5
|
30.5
|
22.3
|
(*) carats per hundred
tonnes
|
(1)
|
Average grade
processed is from direct milling carats and excludes carats
recovered from re-processing historic recovery tailings from
previous milling.
|
(2)
|
Operating cost per
tonne of ore processed is a non-IFRS measure. See "Use of Non-IFRS
Performance Measures" below.
|
(3)
|
Includes qualifying
borrowing cost capitalized in each quarter.
|
CONFERENCE CALL
The Company will host a conference call and webcast to discuss
the results on Wednesday, February 21,
2024 at 6:00am Pacific,
9:00am Eastern, 2:00pm UK, 3:00pm
CET. To join the conference call please use the following
link https://emportal.ink/48xMjQ6 or the phone numbers listed
below.
Conference ID:
26126065 / Lucara Diamond
Dial-In Numbers:
Toll-Free Participant Dial-In North
America
(+1) 888 390 0605
UK Toll free
0800
652 2435
Local Toronto
(+1) 416
764 8609
Webcast:
To view the live webcast presentation, please
log on using this direct link:
https://app.webinar.net/lrAM9b291Zz The presentation slideshow
will also be available in PDF format for download from the Lucara
website (Link to presentation).
Conference Replay:
A replay of the telephone
conference will be available two hours after the completion of the
call until February 28, 2024.
The pass code for the replay is: 126065 #
Replay number (Toll Free North America)
(+1) 888 390 0541
Replay number
(Local)
(+1) 416 764 8677
On behalf of the Board,
William Lamb
President and Chief Executive Officer
Follow Lucara Diamond on Facebook, Instagram, and LinkedIn
ABOUT LUCARA
Lucara is a leading independent producer of large exceptional
quality Type IIa diamonds from its 100% owned Karowe Diamond Mine
in Botswana. The Karowe Mine has
been in production since 2012 and is the focus of the Company's
operations and development activities. Clara Diamond Solutions
Limited Partnership ("Clara"), a wholly-owned subsidiary of Lucara,
has developed a secure, digital sales platform which ensures
diamond provenance from mine to finger. Lucara has an
experienced board and management team with extensive diamond
development and operations expertise. Lucara and its
subsidiaries operate transparently and in accordance with
international best practices in the areas of sustainability, health
and safety, environment, and community relations. Lucara has
adopted the IFC Performance Standards and the World Bank Group's
Environmental, Health and Safety Guidelines for Mining
(2007). Accordingly, the development of the Karowe
underground expansion project ("UGP") adheres to the Equator
Principles. Lucara is committed to upholding high standards while
striving to deliver long-term economic benefits to Botswana and the communities in which the
Company operates.
The information is information that Lucara is obliged to make
public pursuant to the EU Market Abuse Regulation and the Swedish
Securities Markets Act. This information was submitted for
publication, through the agency of the contact person set out
above, on February 20, 2024 at
2:00pm Pacific Time.
NON-IFRS FINANCIAL PERFORMANCE MEASURES
This news release refers to certain financial measures, such as
adjusted EBITDA, adjusted operating earnings, operating cash flow
per share, operating margin per carat sold and operating cost per
tonne of ore processed, which are not measures recognized under
IFRS and do not have a standardized meaning prescribed by IFRS.
These measures may differ from those made by other corporations and
accordingly may not be comparable to such measures as reported by
other corporations. These measures have been derived from the
Company's financial statements, and applied on a consistent basis,
because the Company believes they are of assistance in the
understanding of the results of operations and financial position.
Please refer to the Company's MD&A for the year ended
December 31, 2023 for an explanation
of non-IFRS measures used.
CAUTIONARY NOTE REGARDING FORWARD LOOKING STATEMENTS
Certain of the statements made herein contain certain
"forward-looking information" and "forward-looking statements" as
defined in applicable securities laws. Generally, any statements
that express or involve discussions with respect to predictions,
expectations, beliefs, plans, projections, objectives, assumptions
or future events or performance and often (but not always) using
forward-looking terminology such as "expects", "is expected",
"anticipates", "believes", "plans", "projects", "estimates",
"budgets", "scheduled", "forecasts", "assumes", "intends",
"strategy", "goals", "objectives", "potential", "possible" or
variations thereof or stating that certain actions, events,
conditions or results "may", "could", "would", "should", "might" or
"will" be taken, occur or be achieved, or the negative of any of
these terms and similar expressions) are not statements of
historical fact and may be forward-looking statements.
In particular, forward-looking information and forward-looking
statements may include, but are not limited to, information or
statements with respect to the Company's ability to continue as a
going concern, the project schedule and capital costs for the
Karowe UGP, the diamond sales, projection and outlook disclosure
under "2024 Outlook", the Company's ability to fund the COF, the
impact of supply and demand of rough or polished diamonds,
expectations regarding top-up values, estimated capital costs, the
timing, scope and cost of additional grouting events at the Karowe
UGP, the Company's ability to comply with the terms of the
Facilities which are required to construct the Karowe UGP,
including future funding requirements to the COF, that expected
cash flow from operations, combined with external financing will be
sufficient to complete construction of the Karowe UGP, that
the estimated timelines to achieve mine ramp up and full production
from the Karowe UGP can be achieved, that sufficient stockpiled ore
will be available to generate revenue prior to the achievement of
commercial production of the Karowe underground mine, the economic
potential of a mineralized area, the size and tonnage of a
mineralized area, anticipated sample grades or bulk sample diamond
content, expectations that the Karowe UGP will extend mine life,
forecasts of additional revenues, future production activity, that
depletion and amortization expense on assets will be affected by
both the volume of carats recovered in any given period and the
reserves that are expected to be recovered, the future price and
demand for, and supply of, diamonds, expectations regarding the
scheduling of activities for the Karowe UGP in 2024, future
forecasts of revenue and variable consideration in determining
revenue, the impact of the termination of the HB sales agreement on
the Company's projected revenue and sales channels, estimation of
mineral resources, exploration and development plans, cost and
timing of the development of deposits and estimated future
production, interest rates, including expectations regarding the
impact of market interest rates on future cash flows and the fair
value of derivative financial instructions, currency exchange
rates, rates of inflation, credit risk, price risk, requirements
for and availability of additional capital, capital expenditures,
operating costs, timing of completion of technical reports and
studies, production and cost estimates, tax rates, timing of drill
programs, government regulation of operations, environmental risks
and ability to comply with all environmental regulations,
reclamation expenses, title matters including disputes or claims,
limitations on insurance coverage, the profitability of Clara and
the Clara Platform, and the scaling of the digital platform for the
sale of rough diamonds owned by Clara, the expected use of the
Clara Facility, that the Company intends to continue to seek
additional supply, both from third-party producers and the
secondary market for Clara, and the potential impacts of COVID-19,
economic and geopolitical risks, including potential impacts from
the Russian military invasion of Ukraine and the escalating conflict between
Israel and Hamas.
Forward-looking information and statements are based on the
opinions and estimates of management as of the date such statements
are made, and they are subject to several known and unknown risks,
uncertainties and other factors which may cause the actual results,
performance or achievements of the Company to be materially
different from any future results, performance or achievement
expressed or implied by such forward-looking statements. The
Company believes that expectations reflected in this
forward-looking information are reasonable, but no assurance can be
given that these expectations will prove to be correct.
Certain risks which could impact the Company are discussed under
the heading "Risks and Uncertainties" in the Company's most
recently filed Annual MD&A and, in the Company's most recent
Annual Information Form available at http://www.sedar.com (the
"AIF").
The foregoing is not exhaustive of the factors that may affect
any of our forward-looking statements. Forward-looking statements
are statements about the future and are inherently uncertain, and
our actual achievements or other future events or conditions may
differ materially from those reflected in the forward-looking
statements due to a variety of risks, uncertainties, and other
factors, including, without limitation, those referred to in this
news release.
Although the Company has attempted to identify important factors
that could cause actual actions, events, or results to differ
materially from those described in forward-looking statements,
there may be other factors that cause actions, events or results
not to be as anticipated, estimated or intended. The
forward-looking statements contained in this news release are based
on the beliefs, expectations, and opinions of management as of the
date of this disclosure. There can be no assurance that
forward-looking statements will prove to be accurate, as actual
results and future events could differ materially from those
anticipated in such statements. Accordingly, readers and investors
should not place undue reliance on forward-looking statements.
Forward-looking information and statements are made as of the date
of this disclosure and accordingly are subject to change after such
date. Except as required by law, the Company disclaims any
obligation to revise any forward-looking information and statements
to reflect events or circumstances after the date of such
information and statements. All forward-looking information and
statements contained or incorporated by reference in this news
release are qualified by the foregoing cautionary statements.
Hannah Reynish, Investor
Relations & Communications, +1 604 674 0272,
info@lucaradiamond.com; Sweden Robert Eriksson, Investor Relations
& Public Relations, +46 701 112615, reriksson@rive6.ch; UK
Public Relations Charles Vivian / Jos Simson, Tavistock, +44 778 855 4035,
lucara@tavistock.co.uk
View original
content:https://www.prnewswire.co.uk/news-releases/lucara-announces-year-end-2023-results-continued-development-of-the-underground-project-302066654.html