Tonbridge Power Inc. (TSX VENTURE:TBZ), ("Tonbridge Power" or the "Company"),
100% controlling shareholder of the Montana Alberta Tie Ltd. ("MATL")
transmission line project to interconnect the electricity markets of Alberta and
the US through a 300 MW transmission line is pleased to announce that today the
Montana Department of Environmental Quality ("DEQ") issued a Record of Decision
("ROD") authorizing the construction of MATL's 230kV merchant transmission line
in Montana.


The specific authorization granted in the ROD is a Certificate of Compliance as
required under the Montana Major Facilities Siting Act (MFSA) and is the state
permit required to proceed with the project.


The ROD was issued 20 days after the DEQ and the Department of Energy, ("DOE"),
jointly issued the environmental impact statement, ("EIS") for the MATL line on
October 1, 2008. The Governor of Montana, Brian Schweitzer, presented the permit
to Johan van t Hof, Chief Executive Officer of Tonbridge Power at a press
conference in Helena Montana this morning.


The Certificate of Compliance authorizes the construction of a transmission line
along the preferred alternative that was selected by the DEQ and the US
Department of Energy ("DOE") and was described in the Final Environmental Impact
Statement. The preferred alternative is a combination of MATL's proposed
alternative and an alternative developed by the agencies with some local routing
options.


The only outstanding permit required before construction can begin is the
Presidential Permit. This permit allows the Company to construct, operate,
maintain and connect the MATL line across the US-Canadian border and its
issuance is the responsibility of the DOE. Legislation requires that the DOE
wait at least 30 days post issuance of the EIS before their ROD and Presidential
Permit can be issued, which period expires in early November 2008.


MATL received all the Canadian permits required to build the line earlier this year.

"We are truly appreciative of the great effort that has gone into this
permitting process from all stakeholders," remarked Johan van't Hof, CEO,
Tonbridge Power Inc. "The affected land owners, the regulatory professionals and
the responsible officials worked very hard to ensure this project would be
properly vetted. Special recognition goes out to the Governor's office which,
under Governor Brian Schweitzer's guidance, gave us tremendous support in
guiding a project to benefit the citizens of Montana."


Tonbridge Power is a Toronto-based developer of electrical transmission assets,
whose principal asset is a 100% interest in MATL. Shares of the Company are
traded on the TSX Venture Exchange under the symbol "TBZ".


Should you wish to receive company notices via email please notify us at
info@tonbridgepower.com.


Grafico Azioni DEQ Systems Corp. (TSXV:DEQ)
Storico
Da Giu 2024 a Lug 2024 Clicca qui per i Grafici di DEQ Systems Corp.
Grafico Azioni DEQ Systems Corp. (TSXV:DEQ)
Storico
Da Lug 2023 a Lug 2024 Clicca qui per i Grafici di DEQ Systems Corp.