16 May 2024
EnergyPathways
plc
("EnergyPathways" or the
"Company")
Company
Update
EnergyPathways plc (AIM: EPP), an
integrated energy transition company, is pleased to provide the
following update on its plans to deliver clean, home-grown energy
for the UK.
Key
Highlights
· EnergyPathways
continues to make solid progress on the planned development of its
flagship Marram energy storage project ("Marram" or the "Marram
Project"), a fully appraised 'Ready to go' low-cost development
that can provide critical gas supply and storage infrastructure for
the UK, targeting first gas in 2025
· Ongoing
engineering and design work confirms the feasibility of
EnergyPathways' plan to develop the Marram Project for future gas
storage use and to integrate it into a wider UK Irish Sea energy
storage project, incorporating other geo-storage reservoirs,
storage infrastructure and hydrogen production to support the UK
energy market's future needs
· "Out of Round"
requests for gas production and gas storage licences are
progressing with the North Sea Transition Authority ("NSTA"), the
UK's oil and gas, offshore hydrogen, and gas and carbon storage
industries regulator
· The Company was outbid for the Castletown discovery block
application made in the 33rd licensing round
· Discussions are
progressing with a major regional wind company for the supply of
renewable wind power to the planned Marram Project and an expanded
UK Irish Sea energy storage project
· Engineering
studies have substantially confirmed the potential to fully
electrify EnergyPathways' Marram Project and a UK Irish Sea energy
storage project
· Discussions are
progressing well on both debt and equity financing
Marram Update
The Company continues to make solid
progress on the planned development of its flagship Marram Project
in the UK Irish Sea that contains up to 35.3 Bcf of undeveloped gas
2P Reserves and 11 Bcf of 2C Contingent Resources in high-quality
reservoirs and shallow water, and its subsea tieback development
opportunity in close proximity to existing gas and electricity
infrastructure (circa 15-25km) that has available capacity. The
development is expected to comprise two shallow short lateral
production wells and targeting first gas as early as
2025.
Ongoing engineering and design work
have confirmed the feasibility of EnergyPathways' plan to develop
Marram for future gas storage use and into a UK Irish Sea energy
storage project involving potential other geo-storage reservoirs,
storage infrastructure and hydrogen
production to support the UK energy
market's future needs.
The first phase of this wider energy
storage project concept is the development of the Marram gas field,
initially for gas production before it is transitioned for gas
storage use and hydrogen operations. EnergyPathways has requested a
licence extension to the Marram block area so there is more than
adequate time to update its Field Development Plan for its
decarbonisation and storage initiatives.
Once the Marram Gas field is in
operation, it will initially increase domestic gas supply before
transitioning to storage operations and hydrogen production which
is expected to enhance UK energy market security and efficiency
while supporting the UK's transition to renewable
energy.
In parallel to progressing Front End
Engineering Design (FEED) works on the proposed Marram Gas field
development, negotiations are progressing on an offer to purchase
all gas produced from the Marram Field and the Board of
EnergyPathways are optimistic of seeking expressions of interest in
relation to foundation storage contracts.
Engineering studies with leading
technical contractors continue to support a
fully-electrified-development approach for Marram's proposed
initial gas development and future storage. EnergyPathways is
working to establish an alliance with leading engineering
contractors to design the electrification of wellhead control
systems which will be connected to dedicated renewable power
sources and battery storage solutions. The assessment is also
considering electrically powered gas compression solutions for
Marram gas production and future gas storage use.
On available funding sources for the
proposed Marram Project development, EnergyPathways is engaged in
ongoing discussions and confidential negotiations regarding debt
financing options for Marram and the acquisition of regional energy
infrastructure assets. In parallel, the Company has received
expressions of partnership interest from energy sector companies
providing additional optionality for development financing.
These discussions are early stage, however, management are
encouraged by the level of interest it has received from the
various funding sources and is actively pursuing all possible
alternatives.
UK
Irish Sea Licence Applications
As previously announced,
EnergyPathways has submitted "Out of Round" licence requests to the
NSTA regulator for licences EnergyPathways' plans to incorporate
into its UK Irish Sea Energy Storage Project. The "Out of Round"
licences requests include; gas production licences for the "ready
for development" Knox and Lowry fields, and gas storage licences
for the Marram, Knox and Lowry fields. Following the completion of
the 33rd Licensing Round, we anticipate that the NSTA
will start evaluating these "Out of Round" licence
requests.
The Company also submitted a
33rd Licencing round application for the Castletown
discovery block in the UK Irish Sea. While EnergyPathways' bid was
unsuccessful, feedback from the NSTA indicates that the Company
submitted a strong technical and financial bid.
Commenting on the update, CEO Ben
Clube said:
"This continues to be a very active
period for EnergyPathways as we progress, as a priority, the
development of the Marram energy storage project to provide
critical gas supply and storage infrastructure for the UK. Good
progress has also been made in developing our vision of an expanded
UK Irish Sea energy storage project, and with the conclusion of the
UK 33rd Licensing Round, it is expected the NSTA will
shortly start the evaluation of "Out of Round" licence requests
including our gas production and gas storage licence
requests. Like Marram, the Knox and Lowry licence requests
are also "ready for development" meaning they will not require
appraisal drilling and would therefore likely require significantly
lower levels of pre-development investment than Castletown would
have required. The engineering studies for the initial
development of Marram gas and energy storage project and the wider
energy storage project concept are progressing well and we are
encouraged by the nature of the ongoing discussions with all
relevant stakeholders as we seek to bring the Marram Project into
production and then give life to the energy storage project concept
that we believe will support all the key elements of UK energy
policy."
The Directors of the Company are
responsible for the release of this announcement.
This announcement contains inside information for the purposes
of Article 7 of EU Regulation 596/2014 (which forms part of
domestic UK law pursuant to the European Union
(Withdrawal) Act 2018).
Enquiries:
EnergyPathways
Ben Clube / Ben Hodges
|
Tel: +44 (0)20 7466 5000, c/o
Buchanan (Financial PR)
Email :
info@energypathways.uk
|
Cairn Financial Advisers LLP (Nominated
Adviser) Jo Turner / Louise
O'Driscoll / Sandy Jamieson
|
Tel: +44 (0)20 7213 0880
|
SP
Angel Corporate Finance LLP (Joint Broker)
Richard Hail / Adam Cowl
|
Tel: +44 (0)20 3470 0470
|
Optiva Securities Limited (Joint Broker)
Christian Dennis / Daniel Ingram
|
Tel: +44 (0)20 3137 1903
|
Global Investment Strategy UK Limited (Joint
Broker) Callum Hill / James
Sheehan
|
Tel: +44 (0)20 7048 9000
|
For further information on
EnergyPathways visit www.energypathways.uk and
@energy_pathways on X (formerly Twitter).
Forward Looking Statements
This announcement contains
forward-looking statements relating to expected or anticipated
future events and anticipated results that are forward-looking in
nature and, as a result, are subject to certain risks and
uncertainties, such as general economic, market and business
conditions, competition for qualified staff, the regulatory process
and actions, technical issues, new legislation, uncertainties
resulting from potential delays or changes in plans, uncertainties
resulting from working in a new political jurisdiction,
uncertainties regarding the results of exploration, uncertainties
regarding the timing and granting of prospecting rights,
uncertainties regarding the timing and granting of regulatory and
other third party consents and approvals, uncertainties regarding
the Company's or any third party's ability to execute and implement
future plans, and the occurrence of unexpected
events.
Actual results achieved may vary
from the information provided herein as a result of numerous known
and unknown risks and uncertainties and other factors.