TeraWulf Inc. (Nasdaq: WULF) (“TeraWulf” or the “Company”), a
leading owner and operator of vertically integrated, domestic
bitcoin mining facilities powered by predominantly zero-carbon
energy, today provided an unaudited monthly production and
operations update for August 2024.
August 2024 Production and Operations
Highlights
- Self-Mined
Bitcoin: TeraWulf mined 184 bitcoin in August, achieving
an average production rate of approximately 5.9 bitcoin per
day.
- Operating
Capacity: The Company's installed and operational
self-mining capacity reached approximately 10.0 EH/s, representing
a 100.0% increase year-over-year.
- Power
Cost: The average cost per bitcoin mined was $35,407 in
August, reflecting an approximate rate of $0.044/kWh. This excludes
the benefit from expected demand response and ancillary services
proceeds, which are anticipated to be substantial, as outlined
below.
- Demand
Response: TeraWulf’s Lake Mariner facility curtailed over
1,200 MWh in August as part of its demand response activities. This
is expected to reduce power costs by approximately $0.007/kWh for
the month, representing a value equivalent of approximately 16 BTC,
based on August’s “Value per Bitcoin Self-Mined.”
Key Metrics1 |
August 2024 |
July 2024 |
Bitcoin Self-Mined Lake Mariner |
|
147 |
|
155 |
Bitcoin Self-Mined Nautilus |
|
37 |
|
40 |
Value per Bitcoin Self-Mined2 |
$ |
60,025 |
$ |
62,887 |
Power Cost per Bitcoin Self-Mined |
$ |
35,407 |
$ |
36,346 |
Avg. Operating Hash Rate (EH/s)3 |
|
8.2 |
|
8.0 |
Nameplate Miner Efficiency (J/TH)4 |
|
24.6 |
|
24.6 |
Management Commentary
“During August, TeraWulf mined 184 bitcoin,
maintaining an average production rate of nearly 6 bitcoin per
day,” said Sean Farrell, Senior Vice President of Operations at
TeraWulf. “This underscores our continued operational
optimizations, particularly during peak summer temperatures and
demand response events, and is evidenced by an improved average
operating hash rate compared to July.”
Farrell added, "We have made significant progress
at the Lake Mariner site on our 2 MW ‘WULF Den’ proof-of-concept
project for WULF Compute, designed to house high-density GPUs. The
project remains on track for completion in early September, with
chillers and low-voltage transformers installed, and wiring and
piping work to deliver power and cooling to the AI room well
underway. Additionally, construction of CB-1, our 20 MW AI/HPC
building at Lake Mariner, is advancing as planned, with targeted
completion by year-end5."
Production and Operations
Update
As of August 31, 2024, TeraWulf's operational
infrastructure capacity included 195 MW at the Lake Mariner
facility and 50 MW at the Nautilus facility. The Company's total
self-mining hash rate stands at approximately 10.0 EH/s. In August,
TeraWulf's miners operated at an average of 8.2 EH/s, influenced by
demand response events and performance tuning strategies designed
to maximize profitability.
On the WULF Compute front, the Company continues to
make steady progress on its large-scale AI/HPC project at the Lake
Mariner facility. This includes ongoing construction of a 2 MW
AI/HPC digital infrastructure proof-of-concept building, designed
to support both current and next-generation GPU technology.
Additionally, TeraWulf is developing a 20 MW colocation pilot
project, “CB-1,” at Lake Mariner. This building is engineered to
support 16 MW of critical IT load with liquid cooling and
redundancy features typical of a Tier 3 data center, and it remains
on track to be operational by year-end.
About TeraWulf
TeraWulf owns and operates vertically integrated,
environmentally clean data center infrastructure in the United
States, which is currently deployed to mine bitcoin sustainably.
Led by an experienced group of energy entrepreneurs, the Company
currently has two facilities: the wholly owned Lake Mariner
facility in New York, and Nautilus Cryptomine facility in
Pennsylvania, a joint venture with Cumulus Coin, LLC. Today,
TeraWulf generates domestically produced bitcoin powered by
predominantly zero carbon energy resources, including nuclear and
hydro, with a long-term goal of utilizing 100% zero-carbon energy.
With a core focus on ESG that ties directly to its business
success, TeraWulf aims to provide industry leading mining and data
center economics at an industrial scale.
Forward-Looking Statements
This press release contains forward-looking
statements within the meaning of the “safe harbor” provisions of
the Private Securities Litigation Reform Act of 1995, as amended.
Such forward-looking statements include statements concerning
anticipated future events and expectations that are not historical
facts. All statements, other than statements of historical fact,
are statements that could be deemed forward-looking statements. In
addition, forward-looking statements are typically identified by
words such as “plan,” “believe,” “goal,” “target,” “aim,” “expect,”
“anticipate,” “intend,” “outlook,” “estimate,” “forecast,”
“project,” “continue,” “could,” “may,” “might,” “possible,”
“potential,” “predict,” “should,” “would” and other similar words
and expressions, although the absence of these words or expressions
does not mean that a statement is not forward-looking.
Forward-looking statements are based on the current expectations
and beliefs of TeraWulf’s management and are inherently subject to
a number of factors, risks, uncertainties and assumptions and their
potential effects. There can be no assurance that future
developments will be those that have been anticipated. Actual
results may vary materially from those expressed or implied by
forward-looking statements based on a number of factors, risks,
uncertainties and assumptions, including, among others: (1)
conditions in the cryptocurrency mining industry, including
fluctuation in the market pricing of bitcoin and other
cryptocurrencies, and the economics of cryptocurrency mining,
including as to variables or factors affecting the cost, efficiency
and profitability of cryptocurrency mining; (2) competition among
the various providers of cryptocurrency mining services; (3)
changes in applicable laws, regulations and/or permits affecting
TeraWulf’s operations or the industries in which it operates,
including regulation regarding power generation, cryptocurrency
usage and/or cryptocurrency mining, and/or regulation regarding
safety, health, environmental and other matters, which could
require significant expenditures; (4) the ability to implement
certain business objectives and to timely and cost-effectively
execute integrated projects; (5) failure to obtain adequate
financing on a timely basis and/or on acceptable terms with regard
to growth strategies or operations; (6) loss of public confidence
in bitcoin or other cryptocurrencies and the potential for
cryptocurrency market manipulation; (7) adverse geopolitical or
economic conditions, including a high inflationary environment; (8)
the potential of cybercrime, money-laundering, malware infections
and phishing and/or loss and interference as a result of equipment
malfunction or break-down, physical disaster, data security breach,
computer malfunction or sabotage (and the costs associated with any
of the foregoing); (9) the availability, delivery schedule and cost
of equipment necessary to maintain and grow the business and
operations of TeraWulf, including mining equipment and
infrastructure equipment meeting the technical or other
specifications required to achieve its growth strategy; (10)
employment workforce factors, including the loss of key employees;
(11) litigation relating to TeraWulf and/or its business; and (12)
other risks and uncertainties detailed from time to time in the
Company’s filings with the Securities and Exchange Commission
(“SEC”). Potential investors, stockholders and other readers are
cautioned not to place undue reliance on these forward-looking
statements, which speak only as of the date on which they were
made. TeraWulf does not assume any obligation to publicly update
any forward-looking statement after it was made, whether as a
result of new information, future events or otherwise, except as
required by law or regulation. Investors are referred to the full
discussion of risks and uncertainties associated with
forward-looking statements and the discussion of risk factors
contained in the Company’s filings with the SEC, which are
available at www.sec.gov.
Company Contact:Jason
AssadDirector of Corporate Communications assad@terawulf.com(678)
570-6791
________________________________
1 The Company’s share of the earnings or losses
from operations at the Nautilus Cryptomine facility is reflected
within “Equity in net income (loss) of investee, net of tax” in the
consolidated statements of operations. Accordingly, operating
results of the Nautilus Cryptomine facility are not reflected in
revenue, cost of revenue or cost of operations lines in TeraWulf’s
consolidated statements of operations. The Company uses these
metrics as indicators of operational progress and effectiveness and
believes they are useful to investors for the same purposes and to
provide comparisons to peer companies. All figures except Bitcoin
Self-Mined are estimates and remain subject to standard month-end
adjustments. 2 Computed as the weighted-average opening price of
bitcoin on each respective day the Bitcoin Self-Mined is earned.3
While nameplate mining inventory as of August 31, 2024 for
WULF’s two facilities is estimated at 10.0 EH/s, actual monthly
hash rate performance depends on a variety of factors, including
(but not limited to) performance tuning to increase efficiency and
maximize margin, scheduled outages (scopes to improve reliability
or performance), unscheduled outages, curtailment due to
participation in various cash generating demand response programs,
derate of ASICS due to adverse weather and ASIC maintenance and
repair.4 Nameplate miner efficiency excludes auxiliary load.5 The 2
MW AI/HPC digital infrastructure within the WULF Den pilot project
and the 16 MW AI/HPC building at the Lake Mariner facility are IT
Load (compute).
Grafico Azioni TeraWulf (NASDAQ:WULF)
Storico
Da Dic 2024 a Gen 2025
Grafico Azioni TeraWulf (NASDAQ:WULF)
Storico
Da Gen 2024 a Gen 2025