--Fortescue lifts infrastructure budget to US$9 billion, up from US$8.4 billion

--Increased capex requirements largely the result of increased costs at Solomon Hub

--Miner is talks on additional funding sources, it says

--Reports record shipments of 17.8 million tons in June quarter, up 42%

(Adds comments and details on budget and funding throughout, including comments from CEO in fifth paragraph.)

 
   By Rhiannon Hoyle 
 

SYDNEY--Australia's third-largest iron ore miner Fortescue Metals Group Ltd. (FMG.AU) is assessing its funding options after a detailed review of major new projects prompted the company to increase its infrastructure budget 7% to US$9 billion.

Fortescue, which aims to expand its production in the Pilbara region of Western Australia state to 155 million metric tons a year by mid-2013, Tuesday said the capital required to achieve this will outstrip its previous US$8.4 billion estimate thanks largely to a jump in costs at its Solomon Hub project in Western Australia.

The company has lifted its expected capital expenditure for Solomon by US$500 million, to US$3.2 billion. It cited design and scope changes, increased on-site housing costs and delays in offloading equipment at the Port Hedland port as reasons for the rise.

Fortescue's recent review of its expansion plans also resulted in a US$200 million increase in the budget for its port and rail operations--although there was a US$100 million reduction in expected spending for the Chichester Hub project.

"There were pluses and minuses in the cost results," Chief Executive Neville Power said on a conference call.

Funding for the additional US$600 million needed in the infrastructure budget is now under review, Fortescue said. "The company is in discussions regarding additional funding sources to maintain overall liquidity levels," it said in a quarterly report.

Fortescue is vying with ArcelorMittal (MT) to be the world's fourth largest producer of iron ore. In May, the company entered into a US$965m lease facility to secure additional funding options for the mining fleet associated with its expansion program. In June, it announced a further US$490m in corporate senior debt facilities supported by European export credit agencies.

It said it would spend about US$4.2 billion of the budget in the 2013 financial year, up from US$4 billion in 2012. Around US$400 million will be spent in 2014, with US$400 million having already been spent in 2011.

Fortescue said it has "an absolute focus" to ensure the ramp up of its Solomon infrastructure is completed on time to meet the company's 2013 production targets.

Mr. Power said the initial cost estimates on the project had been "very aggressive."

"If you look at the cost of the Solomon development, even with this change in price, it is very, very competitive," he said.

The company meanwhile announced record quarterly iron ore shipments of 17.8 million metric tons, up 42% on-quarter. Its mining operations rebounded from a rain-affected March quarter, with total mined volumes of 19.2 million tons up 41% on the prior period.

It achieved an average sales price of around US$125 a dry metric ton at destination ports during the quarter. This compares to an average benchmark price of US$141 a ton.

The sales price was down only slightly from US$126 a ton in the March quarter.

"Overall the stability of the iron ore price during the last six months has been a positive for the industry, given the relative volatility of other commodities across international markets," Fortescue said.

Cash costs fell to US$46.04 a ton from US$52.56 a ton over the same period "as the scale benefits of strong production pushed down unit costs," it said.

Write to Rhiannon Hoyle at rhiannon.hoyle@wsj.com

Grafico Azioni Arcelor Mittal (NYSE:MT)
Storico
Da Giu 2024 a Lug 2024 Clicca qui per i Grafici di Arcelor Mittal
Grafico Azioni Arcelor Mittal (NYSE:MT)
Storico
Da Lug 2023 a Lug 2024 Clicca qui per i Grafici di Arcelor Mittal