Calibre Continues Strong Progress at the Fully Funded Valentine Gold Mine; Construction 64% Complete, Engineering 98% Complete, Operational Leadership Hired, Pre-Commissioning Underway, On Track For Q2 2025 Gold Production
14 Maggio 2024 - 11:00PM
Calibre Mining Corp. (TSX: CXB; OTCQX: CXBMF) (“Calibre” or the
“Company”) is pleased to announce a construction and capital cost
update on the Valentine Gold Mine (“Valentine” or “VGM”), located
in the central region of Newfoundland & Labrador, Canada. All
figures in Canadian Dollars (“C$”) unless otherwise stated.
Darren Hall, President and Chief
Executive Officer of Calibre, stated: “I am pleased to
announce that construction of our fully funded Valentine Gold Mine
is 64% complete and we have progressed detailed engineering to 98%
from 60%, with the later having formed the basis of the previously
disclosed Marathon Gold capital estimates. With the first gold pour
scheduled in Q2 2025, the delivery of Valentine is a paradigm shift
for Calibre as we transition to a quality mid-tier gold producer
unlocking significant value for all stakeholders.
Since acquiring Valentine in January 2024 we
have re-baselined the project schedule, significantly progressed
detailed engineering, awarded all major contracts, connected site
to permanent power, delivered critical path items including mills
and motors, employed the operations leadership team, and commenced
pre-commissioning and commissioning activities.
Our project optimization and derisking efforts,
combined with accelerating a portion of Phase 2 expansion capital,
results in an initial capital cost of C$653 million, a C$145
million increase over Marathon Gold’s Q3 2023 update. With a C$279
million cost to complete as of April 30, 2024 and approximately
C$400 million of cash and restricted cash, we are fully funded. In
addition, the Company has substantial cash flows from
operations.
I am confident the Valentine gold property has
district-scale potential, and we anticipate accelerating our
exploration efforts in the near term. The Valentine Gold Mine and
surrounding property offers a robust resource base and significant
discovery opportunities with an extremely prospective array of
exploration targets with similar geology to the prolific Val-d’Or
and Timmins camps in the Abitibi gold belt.”
Initial Capital Cost Update
- First gold
production scheduled for Q2 2025;
- Updated initial
capital cost estimate of C$653 million, an increase of C$145
million versus last reported C$508 million by Marathon Gold
Corporation (“Marathon”) in Q3 2023;
- The updated
estimate is consistent with Calibre’s pre-acquisition due diligence
and consists of three primary components:
- Marathon’s Schedule
and Cost Underestimation of C$70 million;
- Calibre’s Project
Optimization & Derisking of C$40 million; and
- Calibre Advancing
Operations & Phase 2 Expansion Capital of C$35 million
- With a C$279
million cost to complete as of April 30, 2024 and approximately
C$400 million of cash and restricted cash, we are fully funded. In
addition, the company has substantial cash flows from
operations.
Construction and Operational Readiness
Highlights
- Overall
construction progress 64% complete;
- Detailed
engineering progressed to 98%;
- Tailings Management
Facility starter dam embankment complete and approved by the
Engineer of Record and liner placement has commenced;
- Critical path
items, including mills and motors, delivered to Newfoundland;
- Site connected to
permanent hydroelectric power;
- Mill building
enclosed;
- Structural
Mechanical Piping (“SMP”) and Electrical and Instrumentation
(“E&I”) contracts awarded;
- Pre-commissioning
and commissioning contract awarded; and
- Operations
leadership team employed.
Exploration Highlights
- 50,000 metre RC
drilling completed at Leprechaun pit and underway at the Marathon
pit;
- Diamond drilling
recently completed at the Leprechaun SW discovery (see news release
dated April 3, 2024);
- Significant
district scale exploration potential across 64 km shear zones;
- Target delineation
drilling across the shear zones commencing this summer;
- Exceptional
exploration potential over the 250 km2 property with similar
geology to the prolific Val-d’Or and Timmins camps in the Abitibi
gold belt; and
- Strong potential
down plunge of existing open pits demonstrates an additional
underground mining opportunity outside of the current open pit mine
plan.
Marathon Initial Capital Cost Estimate
History
Updated Feasibility Study (1)
|
C$463 million |
- First gold in January 2025
|
Q2 2023 Construction Report
(2) |
C$504 million |
- C$41 million increase
- C$113 million spent as of June 30,
2023
- C$391 million cost to complete
- First gold Q1 2025
|
Q3 2023 Construction Report
(3) |
C$508 million |
- C$4 million increase
- C$190 million spent as of September
30, 2023
- C$318 million cost to complete
- First gold Q1 2025
|
Calibre Initial Capital Cost
Estimate
May 14, 2024 Initial Capital Cost |
C$653 million |
- Overall project completion at
64%
- Detailed engineering at 98%
- C$374 million spent as of April 30,
2024
- C$279 million cost to complete
- Fully funded with ~C$400 million in
cash, and restricted cash
- First gold Q2 2025
|
C$145 million increase vs Marathon’s Q3
2023 estimate due to:
Marathon’s Schedule and Cost Underestimation |
C$70 million |
- First gold shift to Q2 2025
- Labour costs due to the schedule extension
- Engineering progressed from 60% to 98%
- Scope definition increases to major contracts including the SMP
and E&I
- Increased volumes of concrete, steel, etc
- Inflationary pressures on consumables
- Increased camp services and related costs
|
Calibre’s Project Optimization and Derisking |
C$40million |
- Pre commissioning & commissioning contract awarded, and
activities commenced
- Site access upgrade and maintenance
- Process plant & site infrastructure modifications
- Employed the operations leadership team
|
Calibre Advancing Operations and Phase 2 Expansion
Capital |
C$35 million |
- Advanced Phase 2 CIL & cyanide destruct tanks in
preparation of the increase from 2.5 to 4.0Mtpa
- Advanced process plant effluent treatment plant
- Advanced permanent mobile equipment maintenance and associated
facilities
- Accommodation upgrades; including air conditioning and
telecommunications
- Advanced critical spares
|
Calibre will also increase working capital over
the next 12 months to materially de-risk the execution of the
production ramp-up. Areas of focus for working capital include:
- Critical inventory
of consumables and critical spares for mining and processing;
and
- Development of open
pit ore stockpiles to provide consistent and uninterrupted feed to
the process plant.
Qualified Person
Mr. Paolo Toscano, P. Eng (Ont.), SVP
Engineering, Projects and Construction, is a “qualified person” as
set out under NI 43-101 and has reviewed and approved the
scientific and technical information in this press release.
About Calibre
Calibre is a Canadian-listed, Americas focused,
growing mid-tier gold producer with a strong pipeline of
development and exploration opportunities across Newfoundland &
Labrador in Canada, Nevada and Washington in the USA, and
Nicaragua. Calibre is focused on delivering sustainable value for
shareholders, local communities and all stakeholders through
responsible operations and a disciplined approach to growth. With a
strong balance sheet, a proven management team, strong operating
cash flow, accretive development projects and district-scale
exploration opportunities Calibre will unlock significant
value.
ON BEHALF OF THE BOARD
“Darren Hall”
Darren Hall, President & Chief Executive Officer
For further information, please contact:
Ryan KingSVP Corporate Development & IRT:
604.628.1012E: calibre@calibremining.comW:
www.calibremining.com
Calibre’s head office is located at Suite 1560,
200 Burrard St., Vancouver, British Columbia, V6C 3L6.
X / Facebook / LinkedIn / YouTube
The Toronto Stock Exchange has neither reviewed
nor accepts responsibility for the adequacy or accuracy of this
news release.
Cautionary Note Regarding Forward
Looking Information
This news release includes certain
“forward-looking information” and “forward-looking statements”
(collectively “forward-looking statements”) within the meaning of
applicable Canadian securities legislation, including statements
regarding the plans, intentions, beliefs and current expectations
of Calibre with respect to future business activities and operating
performance. All statements in this news release that address
events or developments that Calibre expects to occur in the future
are forward-looking statements. Forward-looking statements are
statements that are not historical facts and are often identified
by words such as "expect", "plan", "anticipate", "project",
"target", "potential", "schedule", "forecast", "budget",
"estimate", "intend" or "believe" and similar expressions or their
negative connotations, or that events or conditions "will",
"would", "may", "could", "should" or "might" occur, and include
information regarding: (i) expectations regarding the ability of
the Company to successfully achieve business objectives, including
the effects of unexpected costs, liabilities or delays, (ii)
expectations regarding future exploration and development, growth
potential for Calibre’s operations, and (iv) expectations for other
economic, business, and/or competitive factors. For a listing of
risk factors applicable to the Company, please refer to Calibre's
annual information form for the year ended December 31, 2023, and
its management discussion and analysis for the year ended December
31, 2023, all available on the Company’s SEDAR+ profile at
www.sedarplus.ca. This list is not exhaustive of the factors that
may affect Calibre's forward-looking statements such as potential
sanctions implemented as a result of the United States Executive
Order 13851 dated October 24, 2022.
Calibre’s forward-looking statements are based
on the applicable assumptions and factors management considers
reasonable as of the date hereof, based on the information
available to management of Calibre at such time. Calibre does not
assume any obligation to update forward-looking statements if
circumstances or management’s beliefs, expectations or opinions
should change other than as required by applicable securities laws.
There can be no assurance that forward-looking statements will
prove to be accurate, and actual results, performance or
achievements could differ materially from those expressed in, or
implied by, these forward-looking statements. Accordingly, undue
reliance should not be placed on forward-looking statements.
Footnotes:
- See Marathon Gold
press release dated December 7, 2022, available at
www.calibremining.com or www.sedarplus.ca
- See Marathon Gold press release
dated August 2, 2023, available at www.calibremining.com or
www.sedarplus.ca
- See Marathon Gold press release
dated October 23, 2023, available at www.calibremining.com or
www.sedarplus.ca
A photo accompanying this announcement is available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/5880d528-e9f7-4c73-9080-905232e16f55
Grafico Azioni Calibre Mining (TSX:CXB)
Storico
Da Ott 2024 a Nov 2024
Grafico Azioni Calibre Mining (TSX:CXB)
Storico
Da Nov 2023 a Nov 2024