Solaris Resources Inc. (TSX: SLS; NYSE: SLSR)
(“Solaris” or the “Company”) is pleased to provide an operations
update, including site optimization efforts that have resulted in
significantly improved productivity and cost savings under new
Chief Operating Officer (“COO”), Mr. Javier Toro, as well as the
appointment of leading independent consultants in support of the
Environmental Impact Assessment (“EIA”) in H2/24 and
Pre-Feasibility Study (“PFS”) in H2/25 for the Warintza Project
(“Warintza” or “the Project”) in southeastern Ecuador.
Project Update and
Milestones
- Drilling continues to ramp up with
six rigs having completed over 5,400m in April, nearly a new
monthly record for the Project, toward a minimum program of 30km of
resource growth and infill drilling budgeted for 2024
- EIA on track for completion in
H2/24, with studies and work programs ongoing under the direction
of a proven Ecuadorian environmental consulting firm who has
supported Ecuador’s largest copper and gold mines, ESSAM Cía. Ltda.
(“ESSAM”)
- PFS on track for completion in
H2/25, with support of leading international consulting firms,
including: Ausenco Engineering (“Ausenco”) for infrastructure and
processing; Knight Piésold Consulting (“Knight Piésold”) for
technical studies and engineering designs; and AMC Consultants
(“AMC”) and Minsys Mining Systems (“Minsys”) for mining
- Significantly increased site
productivity and efficiency of operations from infrastructure
development and optimization, logistics and practices, generating a
26% reduction in drilling costs to US$229/m and contributing to
significant savings against the Q1/24 budget
- Funding in place for planned 2024
and 2025 programs through the offtake financing package announced
in December, with the strategic investment announced in January
intended to support an expansion of activities and continued
consolidation of the surrounding district
Mr. Javier Toro, COO, commented: “We are excited
with the improvements we have made at site where our team is
approaching record monthly drilling rates with significantly fewer
rigs than at prior peaks. We are also pleased to be making progress
in advancing studies and work programs to support the completion of
the EIA in H2/24 and PFS in 2025. Warintza is a very unique project
given its global scale and location in a mining district adjacent
to infrastructure at low elevation.”
Project Update
Drilling – Drilling continues
to ramp up, with six rigs having completed over 5,400m in April,
nearly a new record monthly meterage for the Project. A minimum of
30km is budgeted in 2024 for resource growth and infill drilling,
with some of these holes doubling to provide technical data for
mine design and mine planning purposes to support technical
studies. In addition, the updated mineral resource is on track for
completion at the end of June for release in early July by Mr.
Mario E. Rossi, FAusIMM, SME, IAMG, of Geosystems International
Inc. who is a leading porphyry specialist and completed the prior
estimate.
EIA – Solaris has engaged
ESSAM, an Ecuadorian environmental consultant accredited by the
Ministry of Environment of Ecuador, to assist in finalizing and
submitting the EIA for the exploitation phase of the Warintza
Project for regulatory review and approval in H2/24, after more
than three years of baseline environmental monitoring, data
collection and studies from prior permitting efforts. ESSAM has
been involved with Ecuador’s largest copper and gold mines
supporting in environmental audits, monitoring and studies.
Metallurgy & Processing –
Ausenco has been appointed to conduct metallurgical studies and
process plant design for the Project. Activities are focused on
throughput definition, metallurgical recovery for copper,
molybdenum and gold to supplement the test work completed in 2023
(refer to press release dated January 23, 2023), in addition to
tailings testing and process plant design. Metallurgical drilling
holes are already underway and laboratory testing is planned during
May.
Technical & Engineering –
Knight Piésold has been appointed to carry out detailed
geotechnical, hydrogeological, geochemistry, and design studies for
the pit, Waste Rock Facility (“WRF”) and Tailings Management
Facility (“TMF”). Knight Piésold has reviewed the drilling plan for
the geotechnical and hydrogeological pit design and dewatering with
this drilling already underway. Drilling plans have been reviewed
for the TMF and WRF with this drilling program expected to start at
the end of May. A site-wide water balance and water management plan
study is currently underway. In addition, Knight Piesold has
carried out the preliminary Project description report that will
provide the baseline for the EIA.
Mine Planning – AMC and Minsys
have been appointed to undertake mine scheduling and related
trade-off studies. This work will develop mine plans and assess the
impact of different mining rates, mill throughput rates, cut-off
grades and stockpiling strategies in order to optimize the capital
efficiency and IRR and NPV of the Project.
Infrastructure – In addition,
Ausenco has been appointed to oversee the initial internal and
external infrastructure assessments including mine infrastructure,
offices, logistics, power, roads and port facilities. The Company
is continuing to coordinate with Electric Corporation of Ecuador to
provide renewable hydroelectric-power as the primary power source
for the Project, with the first phase of the adjacent Santiago G8
project (1,200MW) projected to be in operation late this
decade.
Funding
As at March 31, the Company had an unaudited
cash balance of approximately US$29 million, with an additional
US$40 million expected from the offtake financing package (refer to
press release dated December 11, 2023) to fund the planned 2024 and
2025 programs. Upon closing the strategic investment announced in
January, the Company plans to expand activities and continue
consolidation of the surrounding district.
PFS Project Team
To support the PFS expected in H2/25, the
Company has appointed leading international consulting firms, with
relevant expertise applicable to the development and optimization
of large-scale copper mining operations in the Americas. These
independent consultants will supplement an in-house team led by Mr.
Javier Toro, which already includes key technical staff recruited
from senior copper mining companies.
Area of Responsibility |
Qualified Person Consultant |
Scope |
Resource Estimate |
Geosystems International Inc. |
Update mineral resource estimation |
Metallurgy and Processing |
Ausenco Engineering |
Metallurgical studies and process plant design |
Mine Planning |
AMC Consultants and Minsys Mining Systems |
Strategic and Life of Mine planning |
Internal and External Infrastructure |
Ausenco Engineering |
Internal: Mine infrastructure, offices, logisticsExternal: Power,
roads, ports |
Technical studies (Geotech, Hydrogeologic, Chemical) |
Knight Piésold Consulting |
Drilling, sampling, testing; water balance, water management |
Engineering studies (Pit, WRF, TMF) |
Knight Piésold Consulting |
Civil and geotechnical design |
Environment |
ESSAM Cía. Ltda. |
Environmental impact studies in support of the EIA |
Social |
ESSAM Cía. Ltda. |
Social impact studies in support of the EIA |
Qualified Person
The scientific and technical content of this
press release has been reviewed and approved by Jorge Fierro,
M.Sc., DIC, PG, Vice President Exploration of Solaris who is a
“Qualified Person” as defined in National Instrument 43-101
Standards of Disclosure for Mineral Projects. Jorge Fierro is
a Registered Professional Geologist through the SME (registered
member #4279075).
On behalf of the Board of Solaris
Resources Inc.
“Daniel Earle”President & CEO, Director
For Further Information
Jacqueline Wagenaar, VP Investor RelationsDirect: 416-366-5678
Ext. 203Email: jwagenaar@solarisresources.com
About Solaris Resources
Inc.
Solaris is advancing a portfolio of copper and
gold assets in the Americas, which includes a world class copper
resource with expansion and discovery potential at its Warintza
Project in Ecuador; a series of grass roots exploration projects
with discovery potential in Peru and Chile; and significant
leverage to increasing copper prices through its 60% interest in
the La Verde joint-venture project with a subsidiary of Teck
Resources in Mexico.
Cautionary Notes and Forward-looking
Statements
This document contains certain forward-looking
information and forward-looking statements within the meaning of
applicable securities legislation (collectively “forward-looking
statements”). The use of the words “will” and “expected” and
similar expressions are intended to identify forward-looking
statements. These statements include statements that the
Environmental Impact Assessment is due in H2/24 and Pre-Feasibility
Study in H2/25, site optimization efforts have resulted in
significantly improved productivity and cost savings under new
Chief Operating Officer, a minimum program of 30km of resource
growth and infill drilling budgeted for 2024, EIA on track for
completion in H2/24, with studies and work programs ongoing under
the direction of ESSAM Cía. Ltda., PFS is on track for completion
in H2/25, with support of leading international consulting firms,
including: Ausenco Engineering for infrastructure and processing;
Knight Piésold Consulting for technical studies and engineering
design; and AMC Consultants and Minsys Mining Systems for mining,
significantly increased site productivity and efficiency of
operations from infrastructure development and optimization,
logistics and practices, generating a 26% reduction in drilling
costs to US$229/m and contributing to significant savings against
the Q1/24 budget, funding in place for planned 2024 and 2025
programs through the offtake financing package announced in
December, with the strategic investment announced in January
intended to support an expansion of activities and continued
consolidation of the surrounding district, a minimum of 30km is
budgeted in 2024 for resource growth and infill drilling, with some
of these holes doubling to provide technical data for mine design
and mine planning purposes to support technical studies, the
updated mineral resource is on track for completion at the end of
June for release in early July, Ausenco has been appointed to
conduct metallurgical studies and process plant design for the
Project with activities focused on throughput definition,
metallurgical recovery for copper, molybdenum and gold in addition
to tailings testing and process plant design, metallurgical
drilling holes are already underway and laboratory testing is
planned during May, Knight Piésold has been appointed to carry out
detailed geotechnical, hydrogeological, geochemistry and design
studies for the pit, Waste Rock Facility and Tailings Management
Facility, AMC and Minsys have been appointed to undertake mine
scheduling and related trade-off studies and will develop mine
plans and assess the impact of different mining rates, mill
throughput rates, cut-off grades and stockpiling strategies in
order to optimize the capital efficiency and IRR and NPV of the
Project, Ausenco has been appointed to oversee the initial internal
and external infrastructure assessments including mine
infrastructure, offices, logistics, power, roads and port
facilities and the Company is continuing to coordinate with
Electric Corporation of Ecuador to provide renewable
hydroelectric-power as the primary power source for the Project, As
at March 31, the Company had an unaudited cash balance of
approximately US$29 million, with an additional US$40 million
expected from the offtake financing package to fund the planned
2024 and 2025 programs, and upon closing the strategic investment
announced in January, the Company plans to expand activities and
continue consolidation of the surrounding district. Although
Solaris believes that the expectations reflected in such
forward-looking statements and/or information are reasonable,
readers are cautioned that actual results may vary from the
forward-looking statements. The Company has based these
forward-looking statements and information on the Company’s current
expectations and assumptions about future events including
assumptions regarding the completion of the EIA and PFS, 2024 and
2025 baseline programs and funding, that all conditions required to
draw down the remaining US$40 million of offtake financing will be
obtained, that such remaining US$40 million of offtake financing
will close, that all conditions required to close the Company’s
strategic financing will be obtained including (i) receipt of the
requisite approval of the TSX, (ii) receipt of regulatory approval
under the Investment Canada Act, and (iii) receipt of regulatory
approval from the relevant authorities in the People’s Republic of
China, and that closing of the strategic financing will occur.
These statements also involve known and unknown risks,
uncertainties and other factors that may cause actual results or
events to differ materially from those anticipated in such
forward-looking statements, including the risks, uncertainties and
other factors identified in the Solaris Management’s Discussion and
Analysis, for the year ended December 31, 2023 available at
www.sedarplus.ca. Furthermore, the forward-looking statements
contained in this news release are made as at the date of this news
release and Solaris does not undertake any obligation to publicly
update or revise any of these forward-looking statements except as
may be required by applicable securities laws.
Grafico Azioni Solaris Resources (TSX:SLS)
Storico
Da Feb 2025 a Mar 2025
Grafico Azioni Solaris Resources (TSX:SLS)
Storico
Da Mar 2024 a Mar 2025