TSXV:ARTG
VANCOUVER, BC, Aug. 15,
2023 /CNW/ - Artemis Gold Inc. (TSXV: ARTG) ("Artemis
Gold" or the "Company") reports financial results for the three and
six months ended June 30, 2023 ("Q2
2023") and provides an update on construction progress at the
Blackwater Mine in central British
Columbia. The project remains fully funded, on track for
first gold pour in H2 2024 and there is no change to the initial
capital expenditure guidance at this time.
Q2 2023 Financial
Results
Artemis Gold's Q2 2023 financial results – including the
consolidated interim financial statements and Management's
Discussion and Analysis ("MD&A") – have been filed and are
available for review on SEDAR+ (www.sedarplus.ca) and on the
Company's website (www.artemisgoldinc.com).
Construction Update
Overall construction at the Blackwater mine was 27% complete as
of June 30, 2023. Project development
continues to advance on schedule, targeting first gold pour in H2
2024. Earthworks continued in priority infrastructure areas, with
approximately 400 hectares logged and cleared and 85% of access
roads needed for construction now operable.
Construction of additional accommodation dormitories is in
progress, which will raise the total camp capacity from 420 to over
550 beds.
Construction of the tailings storage facility main wall is on
track to commence as planned.
Total major works man-hours worked to June 30, 2023, stood in excess of 160,000 hours
with a zero LTIFR1 and an AIFR2 of
129.37.
Plant Site
Process plant construction progressed well on several work
fronts including the mill building, ball mill, carbon in leach
(CIL) tanks, and the primary, secondary, and tertiary crushers, as
well as the reclaim tunnel earthworks. The mill building structural
steel has been delivered and assembly is expected to commence in Q3
2023, with completion anticipated by the end of 2023.
Heavy Equipment
The construction fleet has been commissioned and is operational.
Larger haul trucks are planned to arrive in Q3 2023 to expand and
support the existing fleet as earthworks ramp up over the
summer.
Initial deliveries of the mining fleet, including the first
240-ton CAT 793 haul trucks, are also expected to arrive in Q3
2023.
Engineering and
Procurement
At the end of June 2023, the
Sedgman EPC contract works passed 40% complete overall with
engineering and design over 85% complete. Procurement is over 90%
complete, with fabrication and shipping of critical items well
advanced including key equipment such as the primary, secondary and
tertiary crushers, the ball mill heads and components, inter-tank
screens and cyclone cluster. Electrical machinery control centre
fabrication is well advanced and on schedule.
Laboratory and oxygen plant tenders have been completed, and
contracts have been awarded for production drilling and explosive
supplies. The civil, mechanical and piping materials and equipment
for the water management pond, tailings storage facility as well as
the diversion system infrastructure has been ordered as
planned.
Personnel
At the end of June 2023 there were
approximately 350 staff and contractors on site at Blackwater Mine.
Of these, approximately 25% are female and over 30% identify as
Indigenous. Over 50% of the development team is from the local
region and over 80% are B.C. residents.
Artemis Gold Chairman and CEO Steven
Dean commented, "We remain focused on a disciplined approach
to development of the Blackwater mine. We have formed strong
partnerships with our local communities and First Nations, and with
Phase 1 fully funded and 27% complete, we remain on track to pour
first gold in H2 2024. Blackwater will be one of B.C.'s largest
gold mines and a significant contributor to the local, provincial,
and federal economies."
Subsequent to June 30, 2023
Artemis Gold took proactive measures during July 2023 to temporarily reduce the number of
non-essential staff and contractors as a result of an uncontrolled
wildfire reaching the immediate vicinity of the mine site.
Following the wildfire, all mine site infrastructure remains
intact, including the construction camp, process plant area,
construction fleet and contractors' fleets, and damage to property
was minimal as previously reported. Site construction activities
resumed in early August. Current staff and contractor numbers are
over 400 at Blackwater Mine, with all scheduled work fronts
active.
There is no change to the targeted gold pour in H2 2024. The
Company continues to assess the impact of the wildfire on the
Company's estimates of initial capital. Any cost impact depends on
various factors, including contractual remedies and insurance
recoveries available to the Company and its contractors.
At this time, the Company is not making any change to its
initial capital expenditure guidance and the project remains fully
funded.
The initial capital to complete to first gold pour is estimated
to range between C$730 million and
C$750 million, of which the Company
had incurred approximately C$186
million as at the end of June
2023. The Company's cash and cash equivalents at the end of
June 2023 totalled approximately
C$63 million. At the same date, the
Company had funding committed from its streamer in the amount of
US$136 million (approximately
C$180 million) undrawn as at
June 30, 2023, committed project loan
facilities in the amount of C$385
million (including up to C$25
million of capitalized interest), along with a C$40 million standby cost overrun facility. The
Company also has 26.3 million warrants outstanding which are
exercisable at C$1.08 per warrant
before August 27, 2024 for
anticipated proceeds of C$28
million.
About Artemis Gold
Artemis Gold is a well-financed, growth-oriented gold
development company with a strong financial capacity aimed at
creating shareholder value through the identification, acquisition,
and development of gold properties in mining-friendly
jurisdictions. The company's current focus is construction of the
Blackwater Mine project in central British Columbia approximately 160km southwest
of Prince George and 450km
northeast of Vancouver. The
project is one of the largest capital investments in the
Bulkley-Nechako, Fraser-Fort George
and Cariboo regions of B.C. in the last decade. The first pour of
gold and silver from Blackwater Mine is expected H2 2024 and the
mine is expected to be in production for a minimum of 22 years.
Artemis Gold trades on the TSX-V under the symbol ARTG. For more
information visit www.artemisgoldinc.com.
Qualified Person
Jeremy Langford, FAUSIMM, a
Qualified Person as defined by National Instrument 43-101, has
reviewed and approved the scientific and technical information in
this press release.
On behalf of the Board of
Directors
Steven Dean
Chairman and Chief Executive Officer
+1 604 558 1107
Neither the TSX Venture Exchange nor its Regulation Services
Provider (as that term is defined in the policies of the TSX
Venture Exchange) accepts responsibility for the adequacy or
accuracy of this release.
Cautionary Note Regarding
Forward-looking Information
This press release contains certain forward-looking
statements and forward-looking information as defined under
applicable Canadian and U.S. securities laws. Statements contained
in this press release that are not historical facts are
forward-looking statements that involve known and unknown risks and
uncertainties. Any statements that refer to expectations,
projections or other characterizations of future events or
circumstances contain forward-looking statements. In certain cases,
forward-looking statements and information can be identified using
forward-looking terminology such as "may", "will", "expect",
"intend", "estimate", "anticipate", "believe", "continue", "plans",
"potential" or similar terminology. Forward-looking statements and
information are made as of the date of this press release, and
include, but are not limited to, statements regarding the potential
of the Blackwater mine project; the jobs to be created in
connection with the project; the contribution of the project to the
economy; opinions of the Province of British Columbia regarding the project and the
region; agreements and relationships with Indigenous partners; the
future of mining in British
Columbia; the plans of the Company with respect to the
project, including construction, site preparation, clearing,
consultation with indigenous groups, and other plans and
expectations of the Company with respect to the project.
These forward-looking statements represent management's
current beliefs, expectations, estimates and projections regarding
future events and operating performance, which are based on
information currently available to management, management's
historical experience, perception of trends and current business
conditions, expected future developments and other factors which
management considers appropriate. Such forward-looking statements
involve numerous risks and uncertainties, and actual results may
vary. Important risks and other factors that may cause actual
results to vary include, without limitation: risks related to the
ability of the Company to accomplish its plans and objectives with
respect to the development of the project within the expected
timing or at all, the timing and receipt of certain required
approvals, changes in commodity prices, changes in interest and
currency exchange rates, risks inherent in exploration estimates
and results, risks inherent in exploration and development
activities, changes in development or mining plans due to changes
in logistical, technical or other factors, unanticipated
operational difficulties (including failure of plant, equipment or
processes to operate in accordance with specifications, cost
escalation, unavailability of materials, equipment or third party
contractors, delays in the receipt of government approvals,
industrial disturbances, job action, and unanticipated events
related to heath, safety and environmental matters), changes in
governmental regulation of mining operations, political risk,
social unrest, changes in general economic conditions or conditions
in the financial markets, and other risks related to the ability of
the Company to proceed with its plans for the project and other
risks set out in the Company's most recent MD&A, which is
available on the Company's website at
www.artemisgoldinc.com and on SEDAR at
www.sedar.com.
In making the forward-looking statements in this press
release, the Company has applied several material assumptions,
including without limitation, the assumptions that: (1) market
fundamentals will result in sustained mineral demand and prices;
(2) any necessary approvals and consents in connection with the
development of the project will be obtained; (3) financing for the
development, construction and continued operation of the project
will continue to be available on terms suitable to the Company; (4)
sustained commodity prices will continue to make the project
economically viable; and (5) there will not be any unfavourable
changes to the economic, political, permitting and legal climate in
which the Company operates. Although the Company has attempted to
identify important factors that could affect the Company and may
cause actual actions, events, or results to differ materially from
those described in forward-looking statements, there may be other
factors that cause the actual results or performance by the Company
to differ materially from those expressed in, or implied by, any
forward-looking statements. Accordingly, no assurances can be given
that any of the events anticipated by the forward-looking
statements will transpire or occur, or if any of them do so, what
impact they will have on the results of operations or financial
condition of the Company. Investors should therefore not place
undue reliance on forward-looking statements. The Company is under
no obligation, and expressly disclaims any obligation, to update,
alter or otherwise revise any forward-looking statement, whether
written or oral, that may be made from time to time, whether
because of new information, future events or otherwise, except as
may be required under applicable securities laws.
____________________________
|
1
|
LTIFR or Lost Time
Injury Frequency Rate refers to the number of lost time injuries
occurring per million man-hours worked, divided by total man-hours
worked.
|
2
|
AIFR or All Injury
Frequency Rate refers to the total number of recordable incidents
occurring per million man-hours worked, divided by total man-hours
worked.
|
SOURCE Artemis Gold Inc.