VANCOUVER, BC, Feb. 22, 2021 /PRNewswire/ - NexGen Energy
Ltd. ("NexGen" or the "Company") (TSX: NXE) (NYSE: NXE) is
pleased to announce the positive results of an independent
Feasibility Study ("FS" or the "Study"), Mineral Reserve and
Mineral Resource update of the basement-hosted Arrow Deposit,
located on the Company's 100% owned Rook I project ("Arrow" or the
"Project") in the Athabasca Basin
in Saskatchewan, Canada. The
FS was completed jointly by leading consultants including: Stantec
Consulting Limited ("Stantec"), Wood Canada Limited. ("Wood"), and
Roscoe Postle Associates Inc. ("RPA", now part of SLR Consulting
(Canada) Ltd), with other
technical inputs completed by sub-consultants.
Leigh Curyer, Chief Executive Officer, commented:
"The environmental and economic results from the Rook I
Feasibility Study place the Project as one of the leading global
resource projects with an elite ESG profile. Today's delivery of
the Feasibility Study is a significant milestone which transitions
NexGen into the next key stage of advancement. The results will be
included in the Environmental Assessment and Licensing processes
which incorporates engagement, consultation, monitoring and data
collection since 2013.
The NexGen team's commitment to elite standards is evident
throughout all aspects of the feasibility study, and the
organization as a whole. With a minimal physical and carbon
footprint, NexGen is uniquely positioned to become a world leader
in the production of clean energy fuel.
The global energy matrix is undertaking an enormous shift that
will rely heavily on nuclear energy to deliver the decarbonization
commitment for today's and future generations. It is proven
to be a safe, clean and most reliably efficient form of power
generation known to humankind. With all major countries
signalling significant infrastructure spending, and re-prioritizing
green energy policy as their major focus over this coming decade
and beyond, Rook I will be a material component in the delivery of
those global objectives.
I would like to take the opportunity to congratulate the entire
NexGen team, and thank the local communities where we operate, as
well as the Government of Saskatchewan and the Federal
Government Canada for their outstanding commitment and support for
execution of the Rook I Project's development to date."
Highlights
Table 1 – Summary of Arrow Deposit Feasibility Study (based
on US $50/lb
U3O8)
|
FS ($
CAD)
|
After-Tax NPV @
8%
|
$3.47
Billion
|
After-Tax Internal
Rate of Return (IRR)
|
52.4%
|
After-Tax
Payback
|
0.9
Year
|
Pre-Commitment Early
Works Capital
|
$158
Million
|
Project Execution
Capital
|
$1,142
Million
|
Total Pre-Production
Capital Costs
("CAPEX")
|
$1,300
Million
|
Average Annual
Production (Years 1-5)
|
28.8 M lbs
U3O8
|
Average Annual
After - Tax Net Cash Flow
(Years 1-5)
|
$1,038
Million
|
Average Annual
Production (Life of Mine)
|
21.7 M lbs
U3O8
|
Average Annual
After - Tax Net Cash Flow
(Life of Mine)
|
$763
Million
|
Nominal Mill
Capacity
|
1,300 tonnes per
day
|
Average Annual Mill
Feed Grade
|
2.37%
U3O8
|
Mine Life
|
10.7 Years
|
Average Annual
Operating Cost ("OPEX",
Life of Mine)
|
$ 7.58
(US $5.69)/lb
U3O8
|
|
|
1)
|
The economic
analysis was based on the timing of a final investment decision
("FID") and does not include the Pre-Commitment Early Works
Capital, which are costs NexGen intends on expending prior to the
FID. Pre-Commitment Early Works scope includes site
preparation and the supporting infrastructure (concrete batch
plant, Phase I camp accommodations and bulk fuel storage) required
to support full Project Execution Capital.
|
2)
|
FS based on CAD
$1.00 = US $0.75 and US $50/lb U3O8
price.
|
Webcast and Conference Call
NexGen will host a webcast and conference call today,
February 22, 2021 at 8:30AM Eastern Standard Time.
To join the call please dial (+1) 416 764 8659
(local/international) or (+1) 888 664 6392 (North America toll free) with passcode
89503308 and an operator will assist.
To join the webcast, please copy the following link to your
browser:
https://produceredition.webcasts.com/starthere.jsp?ei=1435461&tp_key=3a0aec72f1
where you will be directed to join the webcast.
Top 5 Feasibility Study Outcomes
- Enhanced Environmental Performance – Optimized
facilities layout reducing the project footprint by approximately
20% and lowering on-site personnel transportation and ore haulage.
Optimized shaft sizing, water useage through advanced water
recycling and plant engineering, all reflecting elite environmental
standards. With respect to the proposed shaft, mine workings
and Underground Tailings Management Facility ("UGTMF") locations,
geotechnical and hydrogeological testing validated highly competent
rock with no significant alteration, no major structures, and low
hydraulic conductivity.
- High Return on Capital with 0.9 Year Payback Period
and Life-of-Mine Production Flexibility – Incorporating a
consensus US$50 per lb uranium price
over the life of the mine, provides high economic returns. A
function of the Arrow Deposit geometry combined with the competent
ground conditions enables decoupled production areas in both the A2
and A3 zones, allowing strategic flexibility of mine sequencing and
production.
- CAPEX Accuracy – Nominal 4% increase over the
Pre-Feasibility Study ("PFS") or 1.6% - (incorporating
inflation rates of 2019: 1.95% and 2020: 0.62%) increase in CAPEX
from the PFS due to the following key areas: enhanced environmental
performance, refined mine design, change in shaft diameter, shaft
collar and freeze depths, optimized size of the power plant, paste
fill plant, requirement for an additional waste rock storage area,
and first principle calculations for indirect costs. The
production shaft was increased to 8.0
m in diameter (from 6.5 m in
diameter in PFS) to provide increased production flexibility,
optimization of the radiation and ventilation management, ensuring
the mine is elite from a safety perspective.
- OPEX Accuracy – Average OPEX reduced by 1% per tonne.
Reduction in mining, processing and G&A costs per tonne, with
an increase in paste fill cost per tonne based on paste fill binder
requirements. Cost per pound will be among the lowest in the
sector at US$5.69 per lb.
- Highest Level of Mineral Resource Confidence
– First time declaration of Measured Mineral Resources of
2,183 kt grading 4.35% U3O8, containing
209.6 M lbs
U3O8. Measured and Indicated
Mineral Resources total 3,754 kt grading 3.10%
U3O8, containing 256.7
M lbs U3O8 supporting initial 10.7
year mine life (11% increase).
Mineral Resources
The updated Mineral Resource Estimate has an effective date of
June 19, 2019 and builds upon the
Mineral Resource Estimate used in the PFS by incorporating holes
drilled in 2018 and 2019. The updated Mineral Resource Estimate is
principally comprised of Measured Mineral Resources – the highest
level of confidence determination within Mineral Resources – with
Measured Mineral Resources of 209.6 M
lbs of U3O8 contained in 2,183 kt grading
4.35% U3O8, Indicated Mineral Resources of
47.1 M lbs of
U3O8 contained in 1,572 kt grading 1.36%
U3O8, and Inferred Mineral Resources of
80.7 M lbs of
U3O8 contained in 4,399 kt grading 0.83%
U3O8, summarized below in Table 2. The drill
hole spacing defining the Measured and Indicated Mineral Resources
is supported by two leading and independent geostatistical drill
hole spacing studies.
Table 2 – Arrow Mineral Resource Estimate
FS Mineral
Resource
|
Structure
|
Tonnage
(k tonnes)
|
Grade
(U3O8%)
|
Contained
Metal
(U3O8 M lb)
|
Measured
|
A2 LG
|
920
|
0.79
|
16.0
|
A2 HG
|
441
|
16.65
|
161.9
|
A3 LG
|
821
|
1.75
|
31.7
|
Total:
|
2,183
|
4.35
|
209.6
|
Indicated
|
A2 LG
|
700
|
0.79
|
12.2
|
A2 HG
|
56
|
9.92
|
12.3
|
A3 LG
|
815
|
1.26
|
22.7
|
Total:
|
1,572
|
1.36
|
47.1
|
Measured and
Indicated
|
A2 LG
|
1,620
|
0.79
|
28.1
|
A2 HG
|
497
|
15.9
|
174.2
|
A3 LG
|
1,637
|
1.51
|
54.4
|
Total:
|
3,754
|
3.1
|
256.7
|
Inferred
|
A1 LG
|
1,557
|
0.69
|
23.7
|
A2 LG
|
863
|
0.61
|
11.5
|
A2 HG
|
3
|
10.95
|
0.6
|
A3 LG
|
1,207
|
1.12
|
29.8
|
A4 LG
|
769
|
0.89
|
15.0
|
Total:
|
4,399
|
0.83
|
80.7
|
Notes:
1.
|
CIM Definition
Standards were followed for Mineral Resources, Mineral Resources
are reported inclusive of Mineral Reserves.
|
2.
|
Mineral Resources are
reported at a cut-off grade of 0.25% U3O8
based on a long-term price of US$50 per lb
U3O8 and estimated costs.
|
3.
|
A minimum mining
width of 1.0 m was used
|
4.
|
The effective date of
Mineral Resources is June 19th, 2019
|
5.
|
Numbers may not add
due to rounding.
|
6.
|
Mineral Resources
that are not Mineral Reserves do not have demonstrated
economics.
|
RPA is not aware of any environmental, permitting, legal, title,
taxation, socio-economic, marketing, political, or other relevant
factors that could materially affect the Mineral Resource
Estimate.
Mineral Reserves
The FS defines Probable Mineral Reserves of 239.6 M lbs of
U3O8 contained in 4,575 kt
grading 2.37% U3O8 from the Measured
and Indicated Mineral Resources, summarized in Table 3. The
Probable Mineral Reserves include diluting materials and allowances
for losses which may occur when material is mined. A majority
of the Mineral Reserves are based on Measured Mineral Resources,
and 100% of the Mineral Reserves allocated to the Probable category
based on the Project's current development stage.
Table 3 - Arrow Probable Mineral Reserves
Probable Mineral
Reserves
|
Structure
|
Tonnage
(k
tonnes)
|
Grade
(U3O8%)
|
Contained
Metal
(U3O8 M lb)
|
A2
|
2,594
|
3.32%
|
190.0
|
A3
|
1,982
|
1.13%
|
49.5
|
Total
|
4,575
|
2.37%
|
239.6
|
Notes:
1.
|
CIM definitions were
followed for Mineral Reserves.
|
2.
|
Mineral Reserves are
reported with an effective date of January 21, 2021.
|
3.
|
Mineral Reserves
include transverse and longitudinal stopes, ore development,
marginal ore, special waste and a nominal amount of waste required
for mill ramp-up and grade control.
|
4.
|
Stopes were estimated
at a cut-off grade of 0.30%
U3O8.
|
5.
|
Marginal ore is
material between 0.26% U3O8 and 0.30%
U3O8 that must be extracted to access mining
areas.
|
6.
|
Special waste in
material between 0.03% and 0.26% U3O8 that
must be extracted to access mining areas. 0.03%
U3O8 is the limit for what is considered
benign waste and material that must be treated and stockpiled in an
engineered facility.
|
7.
|
Mineral Reserves are
estimated using a long-term metal price of US$50 per pound
U3O8, and a 0.75 US$/C$ exchange rate (C$1.00
= US$0.75). The cost to ship the yellow cake product to a
refinery is considered to be included in the metal
price.
|
8.
|
A minimum mining
width of 3.0 m was applied for all long hole stopes.
|
9.
|
Mineral Reserves are
estimated using a combined underground mining recovery of 95.5% and
total dilution (planned and unplanned) of 33.8%.
|
10.
|
The density varies
according to the U3O8 grade in the block
model. Waste density is 2.464
t/m3.
|
11.
|
Numbers may not add
due to rounding.
|
Stantec is not aware of any environmental, permitting, legal,
title, taxation, socio-economic, marketing, political, or other
relevant factors that could materially affect the Mineral
Reserve Estimate.
Mine Plan and Production
Profile
A detailed mine plan based on conventional long-hole stope
mining was engineered using Mineral Reserves only.
Geotechnical studies during the FS re-emphasized the conventional
long-hole stoping mining method, including the use of longitudinal
and transverse stopes, 30 m level
spacing, and the nominal stope strike length of 12 metres to 24
metres. This represents an excellent stope stability range for
underground mining in the highly competent conditions. The FS
production profile is underpinned by long-hole stopes in the
transverse orientation through A2 High Grade mineralization. The
ability to mine transverse long-hole stopes through the A2 High
Grade will support significant scheduling flexibility, enabling
NexGen to uniquely correlate supply quickly and inexpensively to
market conditions.
Furthermore, given the competency and conditions of the
underground environment, all waste streams from the process plant
are planned to be stored underground in the Underground Tailings
Management Facility ("UGTMF") while process water streams will be
treated on surface in the optimized effluent treatment plant.
The FS mine plan, using a 0.30% U3O8
cut-off grade, includes Probable Mineral Reserves consisting of
239.6 M lbs of
U3O8 contained in 4,575 kt grading 2.37%
U3O8 that will be extracted by underground
mining in an initial 10.7 year mine life. The mine production
schedule envisions an average life of mine rate of 1,207 tonnes per
day during steady state production.
The underground workings will be accessed by two (2) shafts,
with the production shaft supporting personnel movements,
materials, ore, waste and fresh air. The production shaft was
increased to 8.0 m in diameter (from
6.5 m in diameter in PFS) to optimize
radiation and ventilation management, ensuring the mine is elite
from a safety perspective. Additionally, the production shaft
will have divided compartments, ensuring that fresh air and
personnel entering the mine, remain isolated from ore being skipped
to surface. The exhaust shaft was optimized and ultimately
decreased to 5.5 m in diameter (from
6.5 m in diameter in the PFS) and
will be used for exhaust air and emergency secondary egress. Mining
extraction has been optimized and estimated to be 95.5% of
mineralized tonnes for both ore development and stopes. Planned
dilution was included in the generation of the stope shapes, and
additional backfill dilution (at zero grade) was included where
appropriate. Overall rock dilution is estimated to be 33.8%, which
includes backfill dilution applied on secondary stopes only. Figure
1 below presents a cross section displaying the underground mining
infrastructure and the Measured and Indicated Mineral
Resources. Figure 2 below presents the annual mining schedule
based on set assumptions.
![Figure 1 – Cross Section View of FS Mine Design (Looking Northeast) (CNW Group/NexGen Energy Ltd.) Figure 1 – Cross Section View of FS Mine Design (Looking Northeast) (CNW Group/NexGen Energy Ltd.)](https://mma.prnewswire.com/media/1441512/NexGen_Energy_Ltd__NexGen_Announces_Elite_Environmental_and_Econ.jpg)
![Figure 2 – Arrow Deposit Production Profile (CNW Group/NexGen Energy Ltd.) Figure 2 – Arrow Deposit Production Profile (CNW Group/NexGen Energy Ltd.)](https://mma.prnewswire.com/media/1441513/NexGen_Energy_Ltd__NexGen_Announces_Elite_Environmental_and_Econ.jpg)
Shaft pilot holes (GAR-18-013, and GAR-18-015) were drilled
vertically within the diameter of the respective planned shafts to
assess the geotechnical and hydrogeological characteristics for
prospective exhaust and production shaft locations. Supported by
the information from GAR-18-015 the location was selected for the
production shaft and likewise for GAR-18-013 for the exhaust shaft.
Both holes proved to be favourable for all aspects of shaft
development. Below the planned temporary freeze depth the
shaft holes intersected competent rock with no uranium
mineralization, no significant alteration, no major structures, and
low hydraulic conductivity. These components validate the competent
ground conditions of the proposed shaft locations. Figures 3 and 4
below are core photos from the production and exhaust shaft pilot
holes.
Processing and Underground Tailings Management
Facility
Extensive testwork and engineering has determined that proven
technology in a conventional uranium processing flowsheet is most
effective for the production of U3O8 from the
Arrow Deposit. A key environmental differentiator for the Project
regarding processing is the environmental standard of the disposal
of all tailings in a purpose-built Underground Tailings Management
facility ("UGTMF").
The main components of the processing plant are:
- Ore Sorting
- Grinding
- Leaching
- Liquid-Solid Separation via Counter Current Decantation and
Clarification
- Solvent Extraction
- Gypsum Precipitation and Washing
- Yellowcake Precipitation and Washing
- Yellowcake Drying, Calcining and Packaging
- Tailings Preparation and Paste Tailings Plant
Metallurgical testing resulted in supporting and refining
process design parameters. The FS process recovery of 97.6%
confirming the predictable nature of the processing flow sheet.
The FS also confirmed that all processed waste streams can be
stored in the UGTMF and no surface tailings facility is
required. The UGTMF is a reflection of NexGen's
industry-leading environmental design approach, contributing to the
significant reduction of the Project's surface footprint, and
representing an opportunity to implement best practice of
progressive closure of tailings facilities during the operational
phase of the mine. The FS drill program validated the
geotechnical conditions and favourable conditions for the
UGTMF. The Study also optimized the geotechnical design, size
and sequencing of the UGTMF included in the FS mine plan. The UGTMF
is an example of NexGen's commitment to advancing the Project with
innovative approaches to deliver optimal environmental, social and
economic performance.
FS testwork demonstrated paste fill strength meets or exceeds
all requirements set in the FS design for a potential
Paste-Backfill to be used for underground stope stability. The
testing refined the design parameters for the Paste Tailings Plant.
The Paste-Backfill testing was done at the Saskatchewan Research
Council's Saskatoon facilities in
2019.
Capital Costs
A capital cost estimate (Class 3 - AACE International
classification guidelines) was produced for the FS. The total
pre-production CAPEX for the contemplated underground mine, process
plant and supporting infrastructure at Arrow are estimated at CAD
$1.30 Billion. Wood and Stantec
estimated the capital costs based on a three-dimensional model, a
mechanical equipment list, material takeoffs, vendor budget
quotations on major and secondary equipment, and inputs from
leading expert service providers who have significant experience in
construction projects and cost estimation both in the Athabasca Basin and globally.
Total Pre-production construction is envisioned to occur in two
stages, i) Pre-Commitment Early Works, and ii) Project
Execution.
The Pre-Commitment Early Works stage is scheduled to be
completed in six (6) months with the objective of de-risking early
earthworks, drilling the temporary freeze holes for shaft sinking
and establishing supporting infrastructure required to maximize
efficiencies for the Project Execution stage. Supporting
infrastructure includes the construction of a concrete batch plant,
Phase I camp accommodations and bulk fuel storage. The
Project Execution stage is scheduled to be completed in three and a
half (3.5) years and will include the balance of the Project scope
incorporating ramp-up and commissioning.
The construction phases will be supported by a labour force
consisting of skilled labour, trades people, professionals and
administration. The Study determined the total personnel hours
required for pre-production construction is 3,824,000
hours. The CAPEX is summarized below in Table 4.
Table 4 – Summary of Capital Cost Estimates
Capital Cost
Description
|
Capital Cost
Estimates
($ CAD
Millions)
|
Pre-Commitment
Early Works
|
158
|
Project
Execution Capital
|
|
UG Mining
|
240
|
Processing
|
216
|
Site
Development
|
28
|
On-Site / Off-Site
Infrastructure
|
119
|
Indirect
Costs
|
327
|
Owners
Costs
|
98
|
Contingency – Project
Execution
|
115
|
Total Project
Execution Capital
|
1,142
|
Total
Pre-Production Capital
|
1,300
|
Notes:
1.
|
Numbers may not add
due to rounding.
|
2.
|
Pre-Commitment Early
Works capital includes contingency.
|
Sustaining Capital and Decommissioning Costs
The Sustaining Capital through the life-of-mine, including
Decommissioning Costs, is estimated to be $432 M. As with all underground mines the
main expenditures are for underground mine development and
additional and replacement mobile equipment. The Sustaining
Capital costs are summarized in Table 5.
Table 5 – Summary of Sustaining Capital and Decommissioning
Cost Estimates
Sustaining Cost
Description
|
Sustaining
Cost Estimates
($ CAD
Millions)
|
UG Mining
Equipment
|
62
|
UG Mine
Development
|
108
|
UG
Infrastructure
|
78
|
UGTMF
|
40
|
Surface
Infrastructure
|
28
|
Process
Plant
|
15
|
Indirect
Costs
|
32
|
Total Sustaining
Capital Costs
|
362
|
Decommissioning
Costs
|
70
|
Total Capital
Costs
|
432
|
Notes:
3.
|
Numbers may not add
due to rounding.
|
4.
|
Decommissioning costs
are net of salvage values.
|
Operating Costs
The OPEX estimate is based on a shaft-accessed underground mine
with a conventional longitudinal and transverse long-hole stope
mining method, a conventional processing facility, and a UGTMF.
While in operation the FS defines a peak required workforce of
approximately 470 persons – 290 would be on-site at any one time;
the expertise required ranges from skilled labour, equipment
operators, mining professionals, technical professional, management
and administrative. NexGen's community-first approach ensures all
opportunities are prioritized within the local region. The OPEX is
summarized below in Tables 6.
Table 6 – Unit Operating Cost Estimates
OPEX
|
$ CAD/t
Milled
|
$ CAD/lb
U3O8
|
Mining
|
151.09
|
2.96
|
Mineral
Processing
|
141.41
|
2.77
|
Tailings and
Paste
|
31.46
|
0.62
|
General and
Administration
|
62.84
|
1.23
|
Total Operating
Costs
|
386.80
|
7.58
|
Note:
|
Numbers may not add
due to rounding.
|
Economic Results
The Study was based on a uranium price estimate of US$50/lb U3O8 per pound,
net of yellow cake transportation fees and a fixed USD:CAD
conversion rate of 0.75.
The economic analysis was based on the timing of a final
investment decision ("FID") and does not include the Pre-Commitment
Early Works Capital, which are costs NexGen intends on expending
prior to the FID. The economic analysis is based on a Project
Execution Capital Cost estimate of $1,142
M and a construction schedule of 3.5 years, excluding the
Pre-Commitment Early Works scope (capital costs of $158 M and 6-month construction schedule).
The Feasibility Study returned an after-tax NPV8% of
$3.47 billion and an IRR of
52.4%. NPV and IRR are summarized in the following table
using Base Case and other flat uranium price estimates. The
economic model was subjected to a sensitivity analysis to determine
the effects of changing metals prices, grade, metal recovery,
exchange rate, OPEX, CAPEX, labour and reagent costs. The NPV is
most sensitive to metals prices, grade, metal recovery, and
exchange rate.
Table 7 – NPV and IRR Sensitivity to Uranium Price
Uranium Price ($
USD/lb U3O8)
|
After-Tax
NPV8
|
After-Tax
IRR
|
$65/lb
U3O8
|
CAD $4.87
Billion
|
62.8%
|
$60/lb
U3O8
|
CAD $4.40
Billion
|
59.5%
|
$55/lb
U3O8
|
CAD $3.93
Billion
|
56.1%
|
$50/lb
U3O8 (Base Case)
|
CAD
$3.47 Billion
|
52.4%
|
$45/lb
U3O8
|
CAD $3.00
Billion
|
48.4%
|
$40/lb
U3O8
|
CAD $2.53
Billion
|
44.0%
|
About NexGen
NexGen is a British Columbia
corporation with a focus on developing the Rook I Project located
in the south western Athabasca
Basin, Saskatchewan, Canada into
production. NexGen has a highly experienced team of uranium
industry professionals with a successful track record in the
discovery of uranium deposits and in developing projects through
discovery to production. NexGen also owns a portfolio of
highly prospective uranium properties in the south western
Athabasca Basin, Saskatchewan, Canada.
Technical Disclosure
The technical information in this news release with respect to
the FS has been reviewed and approved by Mark Hatton, P.Eng. of Stantec, Paul O'Hara, P.Eng. of Wood, and Mark B. Mathisen, C.P.G. of RPA, each of whom is
an independent "qualified person" under National Instrument 43-101
– Standards of Disclosure for Mineral Projects
("NI-43-101").
All technical information in this news release has been reviewed
and approved by Anthony (Tony)
George, P.Eng, NexGen's Chief Project Officer, who is a
qualified person under National Instrument 43-101.
A technical report in respect of the FS will be filed on SEDAR
(www.sedar.com) and EDGAR (www.sec.gov/edgar.shtml)
shortly.
Cautionary Note to U.S. Investors
This news release includes Mineral Reserves and Mineral
Resources classification terms that comply with reporting standards
in Canada and the Mineral Reserves
and the Mineral Resources estimates are made in accordance with NI
43-101. NI 43-101 is a rule developed by the Canadian Securities
Administrators that establishes standards for all public disclosure
an issuer makes of scientific and technical information concerning
mineral projects. These standards differ from the requirements of
the Securities and Exchange Commission ("SEC") set the SEC's
rules that are applicable to domestic United States reporting companies.
Consequently, Mineral Reserves and Mineral Resources
information included in this news release is not comparable to
similar information that would generally be disclosed by domestic
U.S. reporting companies subject to the reporting and disclosure
requirements of the SEC Accordingly, information concerning
mineral deposits set forth herein may not be comparable with
information made public by companies that report in accordance with
U.S. standards.
Forward-Looking Information
The information contained herein contains "forward-looking
statements" within the meaning of applicable United States securities laws and regulations
and "forward-looking information" within the meaning of applicable
Canadian securities legislation. "Forward-looking information"
includes, but is not limited to, statements with respect to mineral
reserve and mineral resource estimates, the 2021 Arrow Deposit,
Rook I Project and estimates of uranium production, grade and
long-term average uranium prices, anticipated effects of completed
drill results on the Rook I Project, planned work programs,
completion of further site investigations and engineering work to
support basic engineering of the project and expected outcomes.
Generally, but not always, forward-looking information and
statements can be identified by the use of words such as "plans",
"expects", "is expected", "budget", "scheduled", "estimates",
"forecasts", "intends", "anticipates", or "believes" or the
negative connotation thereof or variations of such words and
phrases or state that certain actions, events or results "may",
"could", "would", "might" or "will be taken", "occur" or "be
achieved" or the negative connotation thereof. Statements
relating to "mineral resources" are deemed to be forward-looking
information, as they involve the implied assessment that, based on
certain estimates and assumptions, the mineral resources described
can be profitably produced in the future.
Forward-looking information and statements are based on the
then current expectations, beliefs, assumptions, estimates and
forecasts about NexGen's business and the industry and markets in
which it operates. Forward-looking information and statements are
made based upon numerous assumptions, including among others, that
the mineral reserve and resources estimates and the key assumptions
and parameters on which such estimates are based are as set out in
this news release and the technical report for the property , the
results of planned exploration activities are as anticipated, the
price and market supply of uranium, the cost of planned exploration
activities, that financing will be available if and when needed and
on reasonable terms, that third party contractors, equipment,
supplies and governmental and other approvals required to conduct
NexGen's planned exploration activities will be available on
reasonable terms and in a timely manner and that general business
and economic conditions will not change in a material adverse
manner. Although the assumptions made by the Company in providing
forward looking information or making forward looking statements
are considered reasonable by management at the time, there can be
no assurance that such assumptions will prove to be accurate in the
future.
Forward-looking information and statements also involve known
and unknown risks and uncertainties and other factors, which may
cause actual results, performances and achievements of NexGen to
differ materially from any projections of results, performances and
achievements of NexGen expressed or implied by such forward-looking
information or statements, including, among others, the existence
of negative operating cash flow and dependence on third party
financing, uncertainty of the availability of additional financing,
the risk that pending assay results will not confirm previously
announced preliminary results, conclusions of economic valuations,
the risk that actual results of exploration activities will be
different than anticipated, the cost of labour, equipment or
materials will increase more than expected, that the future price
of uranium will decline or otherwise not rise to an economic level,
the appeal of alternate sources of energy to uranium-produced
energy, that the Canadian dollar will strengthen against the U.S.
dollar, that mineral resources and reserves are not as estimated,
that actual costs or actual results of reclamation activities are
greater than expected, that changes in project parameters and plans
continue to be refined and may result in increased costs, of
unexpected variations in mineral resources and reserves, grade or
recovery rates or other risks generally associated with mining,
unanticipated delays in obtaining governmental, regulatory or First
Nations approvals, risks related to First Nations title and
consultation, reliance upon key management and other personnel,
deficiencies in the Company's title to its properties, uninsurable
risks, failure to manage conflicts of interest, failure to obtain
or maintain required permits and licences, risks related to changes
in laws, regulations, policy and public perception, as well as
those factors or other risks as more fully described in NexGen's
Annual Information Form dated March 11,
2020 filed with the securities commissions of all of the
provinces of Canada except
Quebec and in NexGen's 40-F filed
with the United States Securities and Exchange Commission, which
are available on SEDAR at www.sedar.com and Edgar at
www.sec.gov.
Although the Company has attempted to identify important
factors that could cause actual results to differ materially from
those contained in the forward-looking information or statements or
implied by forward-looking information or statements, there may be
other factors that cause results not to be as anticipated,
estimated or intended. Readers are cautioned not to
place undue reliance on forward-looking information or statements
due to the inherent uncertainty thereof.
There can be no assurance that forward-looking information
and statements will prove to be accurate, as actual results and
future events could differ materially from those anticipated,
estimated or intended. Accordingly, readers should not place undue
reliance on forward-looking statements or information. The Company
undertakes no obligation to update or reissue forward-looking
information as a result of new information or events except as
required by applicable securities laws.
View original content to download
multimedia:http://www.prnewswire.com/news-releases/nexgen-announces-elite-environmental-and-economic-results-from-the-rook-i-feasibility-study-301232246.html
SOURCE NexGen Energy Ltd.