Project Update
04 Luglio 2024 - 8:00AM
UK Regulatory
Project Update
Kenmare Resources plc
(“Kenmare” or “the Company”)
4 July 2024
Project Update
Kenmare Resources plc (LSE:KMR, ISE:KMR), one of
the leading global producers of titanium minerals and zircon, which
operates the Moma Titanium Minerals Mine (the "Mine" or "Moma") in
northern Mozambique, is pleased to provide a project update for the
Wet Concentrator Plant (“WCP”) A upgrade and transition to the
Nataka ore zone.
Statement from Michael Carvill, Managing
Director:
“The Board has approved the final part of
the Definitive Feasibility Study for the WCP A upgrade and
transition to the Nataka ore zone, relating to the infrastructure.
The total capital costs for the project remain in line with
previous estimates. On-going detailed engineering and scheduling
work has resulted in lower expected capital expenditure in
2024.
Works are advancing well for the upgrade,
with the fabrication of the two new dredges and the upfront
desliming circuit making encouraging progress. Nataka represents
over 70% of Moma’s Mineral Resources and unlocking this ore zone
secures production for decades to come, whilst maintaining
Kenmare’s first quartile position on the industry revenue to cost
curve.”
Overview
Nataka is the largest ore zone in Kenmare’s
portfolio, containing 6.4 billion tonnes of Moma’s 9.0 billion
tonnes of Mineral Resources. WCP A is the largest of Kenmare’s
three mining plants, representing approximately 50% of total mining
capacity. WCP A will begin its transition from its current mine
path in Namalope, where it has mined for 17 years, to Nataka in
late 2025. This is the only move of this kind that is required in
WCP A’s economic life, which is expected to extend beyond the
existing mine plan that runs to 2045.
Kenmare’s Board approved the initial three parts
of WCP A’s Definitive Feasibility Study (“DFS”) in 2023, while the
DFS relating to infrastructure was completed in Q2 2024. The
Infrastructure DFS addresses four key elements:
-
Electricity supply – including a new 110kV overhead powerline from
the Mineral Separation Plant (“MSP”) to the Nataka substation
-
Pumping and piping – allowing for transportation of slimes from WCP
A to the primary densification paddock and ultimately the Tailings
Storage Facility (“TSF”), as well as distributing water
-
Heavy Mineral Concentrate (“HMC”) handling – including a new
terrace for stacking and storage of HMC. HMC will be pumped from
WCP A to the infrastructure terrace by pipeline and in the early
years of operation, transported to the MSP by road
-
Other infrastructure – including the new Nataka electricity
substation, maintenance workshops for heavy mobile equipment, and
offices
Capital costs
The total capital cost for the upgrade and
transition of WCP A is expected to be in line with previous
estimates and totals $341 million. This includes $106 million in
respect of WCP A infrastructure (including both base capital
expenditure of $88 million and $18 million of the overall project
contingency). Kenmare plans to fund the WCP A upgrade and
transition from cash flow and existing debt facilities.
The breakdown of the total capital costs remains
similar to Kenmare’s previous guidance, including contingency of
$52 million. The breakdown is as follows:
Component |
Cost estimate in July 2024 |
Cost estimate in December 2023 |
New dredges |
65 |
65 |
Other WCP A upgrades (e.g. upfront desliming circuit) |
100 |
100 |
TSF |
36 |
36 |
Nataka infrastructure |
88 |
98 |
Contingency |
521 |
42 |
Total |
341 |
341 |
- A portion of contingency has been
committed.
Kenmare began incurring capital expenditure for
the WCP A upgrade and transition in 2023, beginning with orders for
key long lead time items, such as the two new higher capacity
dredges. The capital expenditure incurred to date has been lower
than expected and further detailed engineering and scheduling work
has deferred $38 million of expected capital expenditure from 2024
into subsequent years, in line with the expected mine plan.
Kenmare continues to expect to begin the
transition of WCP A to the Nataka ore zone in late 2025.
Capital expenditure schedule
($m) |
2023 |
2024 |
2025 |
2026 |
2027 |
2028 |
Total |
July 2024 |
11 |
141 |
128 |
40 |
4 |
17 |
341 |
December 2023 |
11 |
179 |
121 |
20 |
10 |
- |
341 |
Project status update
The WCP A upgrade and transition project
consists of three key components, in addition to the infrastructure
included in the WCP A Infrastructure DFS, and their current status
is as follows:
- New more powerful
dredges – the fabrication of two new higher capacity
dredges is progressing with Kenmare’s contractor in the
Netherlands
- Upfront desliming
circuit to more effectively manage slimes at
Nataka – the fabrication of pontoons and surge bin (parts of the
desliming circuit) is underway and the earth works for the starter
pond are also in progress
- Introduction of a
TSF to replace the current paddock system – the detailed
design of the TSF is progressing well and on schedule for
completion in Q3 2024. Construction is expected to begin in Q4
2024
Other capital projects
Work continues on both the DFS for the WCP B
upgrade, which is expected to increase WCP B’s capacity by over
40%; and the Pre-Feasibility Study for the Congolone ore zone,
which is a potential future growth opportunity for the Company.
Kenmare expects to provide an update on both studies with the
Company’s Interim Results, which will be announced on 14 August
2024.
The Company will announce its Q2 and H1 2024 Production Update
on 17 July 2024.
For further information, please contact:
Kenmare Resources plc
Jeremy Dibb / Katharine Sutton / Michael Starke
Investor Relations
ir@kenmareresources.com
Tel: +353 1 671 0411
Mob: + 353 87 943 0367 / + 353 87 663 0875
Murray (PR advisor)
Paul O’Kane
pokane@murraygroup.ie
Tel: +353 1 498 0300
Mob: +353 86 609 0221
About Kenmare Resources
Kenmare Resources plc is one of the world's
largest producers of mineral sands products. Listed on the London
Stock Exchange and the Euronext Dublin, Kenmare operates the Moma
Titanium Minerals Mine in Mozambique. Moma's production accounts
for approximately 7% of global titanium feedstocks and the Company
supplies to customers operating in more than 15 countries. Kenmare
produces raw materials that are ultimately consumed in everyday
quality-of-life items such as paints, plastics and ceramic
tiles.
All monetary amounts refer to United States dollars unless
otherwise indicated.
Forward Looking Statements
This announcement contains some forward-looking
statements that represent Kenmare's expectations for its business,
based on current expectations about future events, which by their
nature involve risks and uncertainties. Kenmare believes that its
expectations and assumptions with respect to these forward-looking
statements are reasonable. However, because they involve risk and
uncertainty, which are in some cases beyond Kenmare's control,
actual results or performance may differ materially from those
expressed or implied by such forward-looking information.
Grafico Azioni Kenmare Resources (LSE:KMR)
Storico
Da Dic 2024 a Gen 2025
Grafico Azioni Kenmare Resources (LSE:KMR)
Storico
Da Gen 2024 a Gen 2025