YASTEST
ENDEAVOUR REPORTS THAT WET COMMISSIONING IS UNDERWAY AT ITS HOUNDÉ
PROJECT
Construction ahead of schedule with
gold pour expected in first half of Q4-2017 & on-budget
View News Release in PDF
Format
Abidjan,
September 25, 2017 - Endeavour Mining Corporation
(TSX:EDV)(OTCQX:EDVMF) ("Endeavour") ("the Company") is pleased to
announce that excellent progress continues to be made at its Houndé
Gold Project in Burkina Faso, as wet commissioning has commenced
and the first ore has been introduced to the process plant milling
circuit in preparation for production. Construction is progressing
ahead of schedule, with over 97% of the total project complete and
on-budget, with the first gold pour expected ahead of schedule in
the first half of the fourth quarter.
Jeremy Langford,
COO, stated: "We are very proud of the
progress made in the recent months in spite of the challenges
presented by exceptionally heavy rainfall this past wet-season.
Construction remains on budget and ahead of schedule as we rapidly
approach the first gold pour without a lost time injury. Moreover,
we believe that we have significantly de-risked its start-up with
three months' worth of ore feed already stockpiled on the ROM and
the transition of the experienced Agbaou processing team to
Houndé.
This confidence
has allowed us to continue to aggressively advance Endeavour's high
quality project pipeline with a portion of the Hounde construction
team already transitioning to the Ity CIL project and the launch of
the Kalana updated feasibility study."
Key milestones achieved to date
include:
- 6.3 million man-hours have been worked without a
lost time injury.
- The dry plant has been fully commissioned and wet
plant commissioning has commenced with first ore introduced to the
system via the SAG and Ball Milling circuit.
- Open pit mining activities at the Main Vindaloo
open pit commenced in late December 2016 with over 8Mt moved
to-date. A total of 515kt at 2.8 g/t containing 46koz has already
been mined and stockpiled on the ROM pad, representing nearly
3-months of feed. Mining to-date suggests positive grade
reconciliation against the resource model.
- The general manager of Endeavour's Agbaou mine
and the majority of its processing team, which successfully
ramped-up the mill in 2014, have been transferred to Houndé to
de-risk its start-up as the plants are of similar design.
- The construction of the fuel farm, the 90kv
overhead power line and the 26MW backup power station have been
completed, with power having being drawn down from the national
grid.
- The construction of the grade control and sample
preparation laboratories has been completed and is
operational.
- The construction of the 300-person permanent
accommodation village and resettlement has been completed.
- The construction of the water harvest dam decant
tower is complete, with water already being pumped to the water
storage dam. Current dam volume is approximately
2,000,000m3, with the
water harvesting still feeding the water storage dam.
- The airstrip is 50% complete and expected to be
operational in November.
- The TSF Cell 1 construction is complete and
operational and TSF Cell 2 construction and ROM pad extension are
underway (Cell 2 was not scheduled until year 2 of operations,
however was brought forward).
- Following a two year period of no exploration
drilling, activities resumed in 2017 with a $5 million program to
focus on delineating high-grade targets. During H1-2017 a total of
6,400 meters diamond drilling, 2,700 meters of reverse circulation
drilling and 48,300 meters of air-core drilling were conducted,
resulting in positive initial results on high-grade targets such as
Kari Pump and Sia/Sianikoui.
Activities in H2-2017 will concentrate on the most promising
exploration targets identified during the initial campaign with
results expected to be published in Q4-2017.
ABOUT THE HOUNDÉ
PROJECT
Once in production, Endeavour's
90%-owned Houndé Project will become the Company's flagship
low-cost mine, ranking amongst West Africa's top tier cash
generating mines, with an average annual production of 190,000
ounces at an All-In Sustaining Cost ("AISC") of US$709/oz over an
initial 10-year mine life based on reserves. In its first four
years, the average annual production is expected to be 235,000
ounces at an AISC of US$610/oz.[1]
The project is an open pit mine
with a 3.0Mtpa gravity circuit / Carbon-In-Leach plant. The initial
capital cost is estimated at $328 million, inclusive of $46 million
for the owner-mining fleet. Construction began in April 2016 and is
progressing on-budget and ahead of schedule with the first gold
pour expected during the first half of the fourth quarter of
2017.
QUALIFIED
PERSONS
Jeremy Langford, Endeavour's Chief
Operating Officer - Fellow of the Australasian Institute of Mining
and Metallurgy - FAusIMM, is a Qualified Person under NI 43-101,
and has reviewed and approved the technical information in this
news release.
ABOUT ENDEAVOUR
MINING
Endeavour Mining
is a TSX-listed intermediate gold producer, focused on developing a
portfolio of high quality mines in the prolific West-African
region, where it has established a solid operational and
construction track record.
Endeavour is
ideally positioned as the major pure West-African multi-operation
gold mining company, operating 5 mines across Côte d'Ivoire (Agbaou
and Ity), Burkina Faso (Karma), Mali (Tabakoto), and Ghana (Nzema).
In 2017, it expects to produce between 500koz and 530koz at an AISC
of US$855 to US$900/oz, following the full-year deconsolidation of
the discontinued Nzema mine. Endeavour is currently building its
Houndé project in Burkina Faso, which is expected to commence
production in Q4-2017 and to become its flagship low-cost mine with
an average annual production of 190koz at an AISC of US$709/oz over
an initial 10-year mine life, based on reserves. The development of
the Houndé and Ity CIL projects are expected to lift Endeavour's
group production to +900kozpa and decrease its average AISC to
circa $800/oz by 2019, while exploration aims to extend all mine
lives to +10 years.
CONTACT
INFORMATION
Martino De Ciccio
VP VP - Strategy & Investor Relations
+ 44 203 011 2706
mdeciccio@endeavourmining.com |
DFH Public Affairs in
Toronto
John Vincic, Senior Advisor
(416) 206-0118 x.224
jvincic@dfhpublicaffairs.com
Brunswick Group LLP in London
Carole Cable, Partner
+44 7974 982 458
ccable@brunswickgroup.com |
Corporate Office:
5 Young St, Kensington, London W8 5EH, UK
This news release contains
"forward-looking statements" including but not limited to,
statements with respect to Endeavour's plans and operating
performance, the estimation of mineral reserves and resources, the
timing and amount of estimated future production, costs of future
production, future capital expenditures, and the success of
exploration activities. Generally, these forward-looking statements
can be identified by the use of forward-looking terminology such as
"expects", "expected", "budgeted", "forecasts", and "anticipates".
Forward-looking statements, while based on management's best
estimates and assumptions, are subject to risks and uncertainties
that may cause actual results to be materially different from those
expressed or implied by such forward-looking statements, including
but not limited to: risks related to the successful integration of
acquisitions; risks related to international operations; risks
related to general economic conditions and credit availability,
actual results of current exploration activities, unanticipated
reclamation expenses; changes in project parameters as plans
continue to be refined; fluctuations in prices of metals including
gold; fluctuations in foreign currency exchange rates, increases in
market prices of mining consumables, possible variations in ore
reserves, grade or recovery rates; failure of plant, equipment or
processes to operate as anticipated; accidents, labour disputes,
title disputes, claims and limitations on insurance coverage and
other risks of the mining industry; delays in the completion of
development or construction activities, changes in national and
local government regulation of mining operations, tax rules and
regulations, and political and economic developments in countries
in which Endeavour operates. Although Endeavour has attempted to
identify important factors that could cause actual results to
differ materially from those contained in forward-looking
statements, there may be other factors that cause results not to be
as anticipated, estimated or intended. There can be no assurance
that such statements will prove to be accurate, as actual results
and future events could differ materially from those anticipated in
such statements. Accordingly, readers should not place undue
reliance on forward-looking statements. Please refer to Endeavour's
most recent Annual Information Form filed under its profile at
www.sedar.com for further information respecting the risks
affecting Endeavour and its business. AISC, all-in sustaining costs
at the mine level, cash costs, operating EBITDA, all-in sustaining
margin, free cash flow, net free cash flow, free cash flow per
share, net debt, and adjusted earnings are non-GAAP financial
performance measures with no standard meaning under IFRS, further
discussed in the section Non-GAAP Measures in the most recently
filed Management Discussion and Analysis.
APPENDIX
Image 1: Aerial View
Image 2 : Ball Mill
Image 3 : Thickener
Image 4 : Mining at the
Vindaloo Main Deposit
Image 5:
Ore to the Stockpile
[1]As announced
in Endeavour's April 11, 2016, news release entitled "Endeavour
starts construction of its Houndé Project, its next low-cost gold
mine" available on the Company's website and on Sedar.
Mining at the Vindaloo Main
Deposit
Aerial View
Thickener
Ore to the Stockpile
View News Release in PDF Format
Ball Mill
This
announcement is distributed by Nasdaq Corporate Solutions on behalf
of Nasdaq Corporate Solutions clients.
The issuer of this announcement warrants that they are solely
responsible for the content, accuracy and originality of the
information contained therein.
Source: Endeavour Mining Corporation via
Globenewswire
Grafico Azioni Vanguard Extended Durati... (AMEX:EDV)
Storico
Da Dic 2024 a Gen 2025
Grafico Azioni Vanguard Extended Durati... (AMEX:EDV)
Storico
Da Gen 2024 a Gen 2025