Firering
Strategic Minerals plc / EPIC: FRG / Market: AIM / Sector:
Mining
5 June 2024
Firering
Strategic Minerals plc
("Firering" or "the Company")
Quicklime
Operational Update
Significant progress towards first production and independent
confirmation of tonnages and grades
Firering Strategic Minerals plc, an
emerging quicklime production and critical mineral exploration
company, is pleased to announce an operational update with regards
to its quicklime project in Zambia
("Limeco"), which is being fast-tracked towards
the commencement of commissioning in Q4 2024.
Highlights
Advancing work to commence phased commissioning and first of
eight kilns to come on stream in Q4 2024:
· Commenced modifications to existing plant, including changing
fuel source system for the kiln operation from Heavy Fuel Oil
("HFO") to coal gasification system.
· Engineers responsible for erecting and commissioning the two
coal gasifiers to arrive on site in July 2024.
· Advancing renovations to the crushing plant to enhance the
correct limestone size fraction for the kilns and the production of
aggregate from its waste stream.
· Limestone stockpile of approximately 150,000tn available to
support production.
Building a multi revenue stream operation from quicklime,
aggregate and ancillary products
· Advanced discussions with potential clients for the offtake of
quicklime; strong interest due to the recent increased copper
production activities in the Zambia Copperbelt.
· Sold aggregate produced to date with future offtake agreements
pending on the finalisation of the renovations to the crushing
plant in Q3 2024.
· Final stage of discussion with a third party interested in
leasing the HFO tanks for diesel storage.
Strengthening economics of estimated +30-year life of
mine:
· Independent consultant, Earthlab Exploration and Mining
Consulting (Pty) Ltd ("Earthlab") reproduced tonnages and grades
using the same range of cut-off grades used by Golder Associates
based on the 2018 geological model.
· Reconfirmed potential additional 95Mt Exploration Target -
licence application in place and license pending.
Yuval Cohen, Chief Executive of Firering, said:
"We are
delighted with the progress being made at Limeco, our near
production quicklime project with a historical pre-acquisition
spend of +$100m. Engineers from Protechglobal Consulting Services,
the firm behind the initial plant design on behalf of Glencore,
have commenced modifications to the lime plant. The general design
for the coal gasifier plant, set to replace the HFO installation,
was also approved with the first of the two gasifiers expected on
site in Q3 2024.
"We have been selling aggregate to industrial end-users since
October last year, enhancing our cash flow position. Additionally,
and in line with our strategy to diversify revenue streams, we have
advanced our quicklime offtake discussions as well as negotiations
regarding the leasing of HFO tanks. Furthermore, we are planning to
sell ash produced during the coal gasification to the local cement
industry until our own cement plant has been
erected.
"I
am also pleased to note that Earthlab successfully reproduced
tonnages and grades using the same range of cut-off grades used by
Golder based on the 2018 geological model and has affirmed a
possible extension to the mineral resource of some 95Mt along
strike to the southeast. Limeco has applied for an exploration
licence for this area, further securing its position as a long-term
supplier to various industries, including local and regional copper
producers.
"I
look forward to further updating the market as we focus on
commissioning the first kiln in the coming
months."
DETAILS
Limeco Assets
Limeco's assets comprise a lime
plant, crushing plant, limestone quarry, and ore and aggregate
stockpiles (Figure 1).
Figure 1: Location of Limeco's
assets (Source: Limeco, 2023).
Figure 2: Primary crusher with lime plant in
background (Source: Limeco, 2023).
Lime Plant Renovations
Limeco has engaged ProtechGlobal Consulting Services ("Protech"),
which originally designed the lime plant for Glencore, for the
modifications to the lime plant. Protech engineers have commenced
these modifications (Figure 3), including changing the fuel source
system required for the kiln operation from HFO to coal
gasification.
Figure 3: Protech inspecting the
kilns and stripping the burner ports to be modified for coal
gasification (Source: Limeco, 2024).
Coal required for the gasification
process will be sourced locally from Maamba Collieries, located
369km from Limeco. Engineers responsible for erecting and
commissioning the two coal gasifiers will arrive on site in July
2024. The high quality coal used in the
gasifier would ensure a tar free gasification process and ash
produced during the process will be removed. Limeco plans to sell
this ash to the local cement industry, creating an additional
revenue stream.
Quicklime Offtake
Agreements
Limeco is in advanced discussions
with potential clients for the offtake of its quicklime. Limeco has
received strong interest in its quicklime due to the recent
increased copper production activities in the Zambia Copperbelt,
which are further encouraged by the recent increases in the copper
price.
Crushing Plant
Renovations to the crushing plant
are on-going to enhance the production of -90mm +60mm limestone for
the kilns as well as the production of aggregate using the waste
stream (-60mm) from the crushing plant (Figure 4).
The double roll crusher will be
replaced by an impact crusher, which will arrive on site in June
2024. Aggregate produced to date has all been sold and future
offtake agreements are pending on the finalisation of the
renovations in Q3 2024.
Figure 4: Aerial view of renovations
at crushing plant (Source: Limeco, 2024)
HFO Storage Tanks
Due to the planned changeover from
HFO to coal gasification, the two large HFO storage tanks will no
longer be used for the production of quicklime. Each tank has a
storage capacity of 16,000t of fuel and Limeco is currently in
negotiations with a third party who is interested in leasing these
tanks for diesel storage. Once the lease contract is concluded,
Limeco will receive additional cashflow that will be used towards
the operations at its lime plant.
Mineral Resource
Golder estimated Mineral Resources
("MR") in its October 2017 report as shown in Table 1.
Class
|
Cut
off
|
Tonnes (Mt)
|
Variables
|
CaCO3
|
MgO
|
Al2O3
|
CaO
|
Fe2O3
|
LOI
|
SiO2
|
Measured Resources
|
92
|
18.1
|
95.78
|
1.13
|
0.23
|
53.69
|
0.13
|
42.49
|
0.76
|
Indicated Resources
|
92
|
45.5
|
95.28
|
1.79
|
0.35
|
53.37
|
0.2
|
41.89
|
1.05
|
Inferred Resources
|
92
|
10.1
|
94.53
|
2.97
|
0.65
|
52.95
|
0.47
|
41.13
|
1.6
|
Total Resources
|
92
|
73.7
|
95.3
|
1.79
|
0.36
|
53.39
|
0.22
|
41.93
|
1.05
|
Table 1: MR estimated by Golder
(2017).
Eight different limestone types (B1
to B8) were identified during geological logging (Figure
5).
Figure 5: Logging guide for the
limestone types identified at Limeco (Source: Limeco, Mopani,
2017).
Material types B1, B2 and B8 were
classified as ore and material types B3 to B7 as waste.
Future tests will focus on whether the B3 and B4 material
types can be reclassified as ore. All other rock types mined will
be crushed to produce aggregate.
In 2018, Golder updated the 2017
geological model and estimated total tonnages at cut-off grades
varying from 50% to 95% CaCO3 (Table 2). Earthlab
independently reproduced these tonnages using the same range of
cut-off grades (Table 3).
CaCO3 Cut-off (%)
|
Tonnage (t)
|
CaCO3 (%)
|
MgO
(%)
|
Al2O3
(%)
|
CaO
(%)
|
Fe2O3
(%)
|
LOI
(%)
|
SiO2
(%)
|
50
|
141,787,573
|
91.40
|
2.64
|
0.53
|
51.21
|
0.33
|
39.72
|
1.47
|
55
|
141,787,573
|
91.40
|
2.64
|
0.53
|
51.21
|
0.33
|
39.72
|
1.47
|
60
|
141,759,682
|
91.41
|
2.64
|
0.53
|
51.21
|
0.33
|
39.72
|
1.47
|
65
|
141,734,739
|
91.41
|
2.64
|
0.53
|
51.21
|
0.33
|
39.72
|
1.47
|
70
|
141,492,384
|
91.45
|
2.63
|
0.53
|
51.23
|
0.33
|
39.72
|
1.47
|
75
|
140,490,481
|
91.59
|
2.62
|
0.53
|
51.30
|
0.32
|
39.71
|
1.46
|
80
|
137,388,762
|
91.89
|
2.57
|
0.52
|
51.47
|
0.31
|
39.73
|
1.44
|
85
|
126,670,646
|
92.64
|
2.37
|
0.48
|
51.89
|
0.29
|
40.13
|
1.37
|
90
|
95,905,548
|
94.17
|
1.97
|
0.38
|
52.74
|
0.24
|
40.84
|
1.15
|
95
|
41,003,811
|
96.18
|
1.25
|
0.20
|
53.88
|
0.13
|
42.49
|
0.73
|
Table 2:Total tonnages produced by
Golder using the 2018 geological model.
CaCO3 Cut-off (%)
|
Tonnage (t)
|
CaCO3 (%)
|
MgO
(%)
|
Al2O3
(%)
|
CaO
(%)
|
Fe2O3
(%)
|
LOI
(%)
|
SiO2
(%)
|
50
|
141,751,554
|
91.40
|
2.64
|
0.53
|
51.21
|
0.33
|
41.89
|
1.50
|
55
|
141,751,554
|
91.40
|
2.64
|
0.53
|
51.21
|
0.33
|
41.89
|
1.50
|
60
|
141,723,663
|
91.41
|
2.64
|
0.53
|
51.21
|
0.33
|
41.89
|
1.50
|
65
|
141,698,720
|
91.41
|
2.64
|
0.53
|
51.21
|
0.33
|
41.89
|
1.50
|
70
|
141,456,278
|
91.45
|
2.63
|
0.53
|
51.23
|
0.33
|
41.89
|
1.50
|
75
|
140,453,551
|
91.59
|
2.62
|
0.53
|
51.30
|
0.32
|
41.89
|
1.49
|
80
|
137,352,124
|
91.89
|
2.57
|
0.52
|
51.47
|
0.31
|
41.90
|
1.47
|
85
|
126,632,940
|
92.64
|
2.37
|
0.48
|
51.89
|
0.29
|
41.95
|
1.39
|
90
|
95,886,315
|
94.17
|
1.97
|
0.38
|
52.74
|
0.24
|
42.11
|
1.17
|
95
|
40,987,598
|
96.18
|
1.25
|
0.20
|
53.88
|
0.13
|
42.60
|
0.73
|
Table 3: Total tonnages produced by
Earthlab using the 2018 geological model.
Earthlab, independent consultant,
commented: "Earthlab reviewed the existing 2017 and 2018
geological models, underlying data, and the 2017 Mineral Resources
report prepared by Golder Associates. Using the 2018 geological
model, Earthlab was able to reproduce total tonnages and grades
reported by Golder by applying the same range of cut-off grades. We
agree with Golder that further work should, inter alia, focus on
testing the B3 and B4 material's suitability for use in the
production of quicklime, which would have a positive impact on the
Mineral Resource."
Competent Person
In accordance with the AIM Rules -
Note for Mining and Oil & Gas Companies, the information
contained in this announcement has been reviewed by Mr. Deon du
Plessis. Mr du Plessis is a qualified professional Geologist
(Pr.Sci.Nat. - 400050/05) and Fellow of the Geological Society of
South Africa (FGSSA - 963338). Mr du Plessis has over 22
years of relevant experience within the geology and mining
sectors.
THIS ANNOUNCEMENT CONTAINS INSIDE INFORMATION AS STIPULATED
UNDER THE UK VERSION OF THE MARKET ABUSE REGULATION NO 596/2014
WHICH IS PART OF ENGLISH LAW BY VIRTUE OF THE EUROPEAN (WITHDRAWAL)
ACT 2018, AS AMENDED. ON PUBLICATION OF THIS ANNOUNCEMENT VIA
A REGULATORY INFORMATION SERVICE, THIS INFORMATION IS CONSIDERED TO
BE IN THE PUBLIC DOMAIN.
*** ENDS
***
For further information visit
www.fireringplc.com or contact:
Firering Strategic Minerals
Yuval Cohen
|
E:
info@firering-holdings.com
|
SPARK Advisory Partners Limited (Nominated
Adviser)
Neil Baldwin / James Keeshan / Adam
Dawes
|
T: +44 20 3368 3550
|
Optiva Securities Limited (Joint Broker)
Christian Dennis / Daniel
Ingram
|
T: +44 20 3137 1903
|
Shard Capital Partners LLP (Joint Broker)
Damon Heath / Erik
Woolgar
|
T: +44 20 7186 9950
|
St
Brides Partners Limited (Financial PR)
Isabel de Salis / Susie Geliher /
Isabelle Morris
|
E: firering@stbridespartners.co.uk
|
About Firering
Firering Strategic Minerals plc is
an AIM-quoted mining company focused on exploring and developing a
portfolio of mines producing strategic minerals in Côte d'Ivoire,
specifically lithium and tantalum, to support the global transition
to net zero emissions. It operates the Atex Lithium-Tantalum
Project in northern Côte d'Ivoire, which is prospective for both
lithium and tantalum. Firering's main focus to date has been
to advance development at Atex with a view to establishing a maiden
lithium resource and then progressing a Lithium project through to
DFS. Firering is also assessing pilot scale production of
ethically sourced tantalum and niobium to generate early revenues
and support further exploration work. Should pilot production
be successful, a large-scale tantalum production facility may be
developed, which will be supported by a debt facility of FCFA
5,057,000,000 (approximately €7,500,000) which is available
to execute as required to fund the entire scale-up plan to develop
a portfolio of ethically sourced mineral projects in the Côte
d'Ivoire, supplying EV batteries, high tech electronics and other
fast-growing end markets.
On 28 May 2024 Firering announced
that it had agreed to acquire a 20.5% shareholding in Limeco,
together with an option to acquire up to a further 24.5%
shareholding.