Premier African Minerals Limited / Ticker: PREM
/ Index: AIM / Sector: Mining
For immediate
release
8 May
2024
Premier African Minerals
Limited
Zulu Lithium Plant
Update
Premier African Minerals Limited
("Premier" or the
"Company") is pleased to
provide an update on progress at operations at Zulu Lithium and
Tantalum ("Zulu").
As previously announced in April,
all efforts have been focussed on the Zulu floatation circuit which
is now running in continuous state and is producing saleable
spodumene concentrate. The process to complete rectification and
optimisation of the floatation circuit remains ongoing and Premier
expects continuous and significant improvement in both floatation
grade and tonnage to follow.
George Roach, CEO, commented, "Thanks to the support the Company receives from ENPROTEC, the
supplier of the float plant components and innovation and
dedication from our team at Zulu, we are now able to run the
floatation circuit continuously and produce saleable spodumene
concentrate.
There is much to be encouraged by,
notably, the use of an activator in the spodumene floatation plant
that has seen recoveries in internal laboratory work approaching
90% and the indications that the ore body in situ grade is higher
than was estimated in our Resource model. The overall plant is
currently running at a feed rate to spodumene floatation that is
approximately 50% of original floatation design capacity and will
need a further conditioning tank and minor pump upgrades to operate
at the full design capacity. This is over and above the recently
completed flow changes. The required pumps are already at site and
the additional civils for the conditioning tank should complete in
May 2024.
Target production for the coming
week is expected to start at 50 tonnes spodumene concentrate per
day with increasing production. Target full projected capacity
remains at 4,000 tonne per month. Grade is consistently improving
with continuous running and latest internal chemical analysis of
spodumene concentrate produced by the floatation circuit indicates
grades have now improved to between 4.5% and 6.3%
Li2O."
The
Zulu Plant
For the reasons previously reported,
Premier replaced the original plant contractor in March 2024.
Whilst the floatation circuit is now running in a constant and
stable state, it will take time to fully remedy the original design
deficiencies in the overall plant and move from what in many
instances are interim fixes to the final operating plant. Some of
these issues are set out below:
Ore Sorters
Neither the XRT or the Ultraviolet
sorters are adequately performing the functions for which they were
sold and delivered to the Company. It is only the diligent and very
careful efforts of a team from the Zulu Geology Department that
both carefully oversees mining and ROM pad inspections to avoid
waste reporting to the plant and thus allows the plant to operate
contaminant free. This interim solution is working well and is
adequate for now, but does not represent a long-term solution. The
equipment supplier has been called upon to deal with this. Premier
will seek to enforce its rights and is investigating
alternatives.
Milling and sizing
The original mill and screen system
was inadequate and unable to provide ore adequately milled and
screened. This set back Zulu by a year. The new ball mill and
sizing equipment has resulted in an interim stable operation but
only after a complete redesign of the mill discharge and hydrosizer
circuit to operate at a consistent optimised feed rate. Additional
upgrades will be installed in this circuit in the near future to
bring this to industry standard.
Magnetic separation and Tantalum
recovery
The plant was supplied with a
magnetic separator and a circuit intended to remove both a
paramagnetic and a magnetic fraction for bagging. The magnetic
separator supplied is low intensity (LIMS) and cannot remove a
paramagnetic fraction that would include tantalum. The magnetic
separator circuit is further unable to efficiently remove iron
generated from the milling process to an acceptable degree and will
need to be upgraded in the near future.
Floatation Circuit
The components of the floatation
circuit were originally specified by the original plant contractor
on the basis that they would be integrated, installed and
commissioned by them. That ENPROTEC has committed to rectify design
constraints and commission this part of the plant is a major factor
in the successful operational status now achieved.
Ore body and plant grades
With development of the open pit,
the Company has now been able to validate the actual pegmatite that
is being mined. In-pit evaluation is undertaken through the
sampling of the pegmatite from blast hole drilling and channel
samples cut across the bench. This allows for better reconciliation
to the 5m x 5m x 5m Assay Block Model grades. On the bench level
currently being developed and mined, the Indicated Resource grade
from the assay block model was 1.01% Li2O while the average grade of the ore
hauled to the ROM pad is currently 1.13% Li2O, an approximate 10%
increase.
At the same time, with material
blended from selective mining in the EPO area,
Li2O grades
recorded in the ore feed to the floatation circuit are in the range
of 1,1% Li2O to
1,8% Li2O, and the
dry solids being fed to the spodumene float plant contain between
12% and 25% spodumene.
Spodumene Concentrate
The term SC6 is used as a price
determination point, being the price paid for spodumene concentrate
in which the Li2O
grade is 6%. Approximately 74% of the concentrate would then be
made up of spodumene. Spodumene concentrate in any grade more than
4% Li2O is saleable
with an adjustment to the price paid relative to the actual amount
of spodumene contained in that bag. It should be noted that prices
are quoted for spodumene concentrates at lower grades and these
prices are in the public domain.
It is worth noting that the market
for lepidolite is improving and Premier believes that it is likely
that our Mica/lepidolite will sell in the near future.
Financial model
The Company will engage an
independent consultancy to assess overall cost implications related
to the present mining operation. Previously, the Company has
indicated a mine gate production cost at $800 per ton. This may
benefit from reduced mining costs linked to ore sourced from within
the EPO.
About ENPROTEC
ENPROTEC is a Multi-disciplinary
Engineering Applications Group that Offers End-to-end Solutions to
the Mining & Mineral Processing Industry. ENPROTEC aim to
extract ore optimally and derive tangible value for its clients
from their operations while eliminating environmental risks.
ENPROTEC is a global partner in the mineral processing industry,
offering a diverse range of solutions and technologies.
ENPROTEC is committed to working
together with Premier on the Zulu plant to mitigate the current
flotation plant constraints to produce a high grade saleable SC6
concentrate at the required design throughput.
Competent Persons Statement
Bruce Cumming, a consulting
geologist to Premier, has reviewed and approved this release to the
extent that reference is made to the geology and mineralogy of the
Zulu pegmatites. Mr. Cumming is a SACNASP and GSSA registered
geoscientist with 48 years' experience in exploration and project
management, in multicommodity projects throughout
Africa.
Market Abuse Regulations
The information contained within this
announcement is deemed by the Company to constitute inside
information as stipulated under the Market Abuse Regulations (EU)
No. 596/2014 as it forms part of UK Domestic Law by virtue of the
European Union (Withdrawal) Act 2018 ("UK MAR").
The person who arranged the release
of this announcement on behalf of the Company was George
Roach.
A copy of this announcement is
available at the Company's website, www.premierafricanminerals.com
Enquiries:
George Roach
|
Premier African Minerals Limited
|
Tel: +27 (0) 100 201 281
|
Michael Cornish / Roland Cornish
|
Beaumont Cornish Limited
(Nominated Adviser)
|
Tel: +44 (0) 20 7628 3396
|
Douglas Crippen
|
CMC
Markets UK Plc
|
Tel: +44 (0) 20 3003 8632
|
Toby Gibbs/Rachel Goldstein
|
Shore Capital Stockbrokers Limited
|
Tel: +44 (0) 20 7408 4090
|
Nominated
Adviser Statement
Beaumont Cornish Limited ("Beaumont Cornish"), which is authorised
and regulated in the United Kingdom by the Financial Conduct
Authority, is acting as nominated adviser to the Company in
connection with this announcement and will not regard any other
person as its client and will not be responsible to anyone else for
providing the protections afforded to the clients of Beaumont
Cornish or for providing advice in relation to such proposals.
Beaumont Cornish has not authorised the contents of, or any part
of, this document and no liability whatsoever is accepted by
Beaumont Cornish for the accuracy of any information, or opinions
contained in this document or for the omission of any information.
Beaumont Cornish as nominated adviser to the Company owes certain
responsibilities to the London Stock Exchange which are not owed to
the Company, the Directors, Shareholders, or any other
person.
Forward
Looking Statements
Certain statements in this announcement are or
may be deemed to be forward looking statements. Forward looking
statements are identified by their use of terms and phrases such as
''believe'' ''could'' "should" ''envisage'' ''estimate'' ''intend''
''may'' ''plan'' ''will'' or the negative of those variations or
comparable expressions including references to assumptions. These
forward-looking statements are not based on historical facts but
rather on the Directors' current expectations and assumptions
regarding the Company's future growth results of operations
performance future capital and other expenditures (including the
amount. Nature and sources of funding thereof) competitive
advantages business prospects and opportunities. Such forward
looking statements reflect the Directors' current beliefs and
assumptions and are based on information currently available to the
Directors. A number of factors could cause actual results to differ
materially from the results discussed in the forward-looking
statements including risks associated with vulnerability to general
economic and business conditions competition environmental and
other regulatory changes actions by governmental authorities the
availability of capital markets reliance on key personnel uninsured
and underinsured losses and other factors many of which are beyond
the control of the Company. Although any forward-looking statements
contained in this announcement are based upon what the Directors
believe to be reasonable assumptions. The Company cannot assure
investors that actual results will be consistent with such forward
looking statements.
Glossary
|
"Li2O"
|
Lithium Oxide (Lithia) - an inorganic lithium
compound used to assess lithium minerals.
|
"m"
|
Meter.
|
"ROM"
|
Run-of-mine.
|
"SC6"
|
spodumene concentrate.
|
|
"Assay Block Model"
|
Block modelling refers to a subset of 3D
models. Normally, the blocks or cells are measured x by y by z, in
metres. In a block model, geological zones are divided into blocks
and the tonnage and grade of contained mineral is estimated for
each block. The shape of blocks (either cubes or rectangular
cuboids) and the estimation methods vary according to the specific
requirements of a project.
|
|
"XRT"
|
X-ray sorting technique where specific mineral
bearing rock can be separated from specific mineral-poor rock and
other impurities. This upgrades in metal terms the material feed to
the plant and lowers the tonnage of rock requiring processing which
results in improved economics for mineral processing
operations.
|
|
Notes to
Editors:
Premier African Minerals Limited (AIM: PREM) is
a multi-commodity mining and natural resource development company
focused on Southern Africa with its RHA Tungsten and Zulu Lithium
projects in Zimbabwe.
The Company has a diverse portfolio of
projects, which include tungsten, rare earth elements, lithium and
tantalum in Zimbabwe and lithium and gold in Mozambique,
encompassing brownfield projects with near-term production
potential to grass-roots exploration. The Company has accepted a
share offer by Vortex Limited ("Vortex") for the exchange of Premier's
entire 4.8% interest in Circum Minerals Limited ("Circum"), the owners of the Danakil
Potash Project in Ethiopia, for a 13.1% interest in the enlarged
share capital of Vortex. Vortex has an interest of 36.7% in
Circum.
Ends