The information contained within this announcement is deemed by the
Company to constitute inside information as stipulated under the
Market Abuse Regulations (EU) No. 596/2014
("MAR")
Kodal
Minerals Plc / Index: AIM / Epic: KOD / Sector: Mining
26 March 2024
Kodal Minerals
plc
("Kodal
Minerals", "Kodal" or the "Company")
Bougouni Lithium Project
Development Update
Kodal Minerals, the mineral
exploration and development company, is
pleased to provide an update on project development activities and
general progress at its Bougouni Lithium
Project in southern Mali ("Bougouni" or the
"Project"). As announced on 15 November 2023, Kodal has
received all funds related to the funding
transaction for US$117.75 million agreed between the Company
and Hainan Mining Co. Limited ("Hainan"), comprising a US$100
million investment from Hainan to acquire 51% of the Bougouni
project company, Kodal Mining UK Limited ("KMUK"), and a further
US$17.75 million received for the subscription for new ordinary
shares in Kodal Minerals plc at 0.5p per share.
Highlights:
· KMUK Management
team established and completed review of project development plan,
confirming US$65 million capital expenditure estimate for Bougouni
Lithium Project Stage 1 (using a dense media separation ("DMS")
approach).
· Long lead items of
DMS units and dual stream crushing modules ordered and work
commenced on build of items.
· Mining contract
finalised with a consortium consisting of Malian mining contractor
EGTF Mining SARL ("EGTF") and Auxin Mining Services Mali SARL
("Auxin"), with costs consistent with feasibility study.
· The Mali Minister
for Environment visited the Bougouni Lithium Project and endorsed
the Company's development programme and development of the DMS
processing site.
· All weather access
roads to the Ngoualana open pit and DMS processing site are
complete.
· Mining contractor
to mobilise to site in March to commence the earthwork and civil
engineering works.
· Updated ESIA for
Bougouni Project Phase 1 DMS approved by Mali's Department of the
Environment in February; negotiations with local community groups
on land compensation also progressing well.
·
Bougouni Project on track to commence
production in Q4 '24 following the achievement of key milestones in
Q1 '24.
· Bougouni Stage 1
(DMS) is fully financed with all permitting in place, including
environmental and social permits, with Kodal's Community
Development Plan also recently approved by Mali's Environment
Ministry.
Bernard Aylward, CEO of Kodal Minerals,
remarked: "The first quarter of 2024
has seen major progress as we push ahead with the development of
our flagship Bougouni Lithium Project. The integration of the
Hainan and Kodal groups within KMUK has been very pleasing; this
positive collaboration is very important to keep our development
momentum moving forward. The new management team has worked
together very effectively to review and improve the development
plan for Bougouni and, positively, confirmed the capital
expenditure estimate of US$65 million for Stage 1 of the project
development.
"This month we also signed contracts for the supply of the
crushing circuit and DMS modules from experienced suppliers in
China and expect these long lead items will be available on site in
time to maintain our expectation of first production in Q4
2024.
"With the main access road fully complete, the Mali Minister
for Environment, Professor Tiémoko Sangaré, visited the site late
last month. During the visit our project team presented the
features and plans for the Phase 1 DMS Operation at Bougouni, with
specific focus on the environment, the social aspects and the draft
of the Community Development Plan. I'm pleased to confirm that the
Minister has since followed up on his visit with a formal letter,
confirming his approval of the proposed plan for the Phase 1 DMS
project.
"Significantly, the team has finalised negotiations for the
award of a mining contract. The mining contractor will mobilise to
site in the coming weeks and will commence with site clearing works
in early April along with other key site establishment
activities.
"These are all major milestones for the Company and underpins
our target of moving into production at Bougouni before the end of
2024. We look forward to updating the market in the months ahead as
we advance this exciting West African Lithium
asset."
FURTHER
INFORMATION
Long Lead
Equipment
Hainan's Vice President for the
development phase, Jerry Gao, has spent a number of weeks this year
in China finalising competitive bids for the long lead process
equipment. Working with Steve Zaninovich, Kodal's Director of
Operations, the project team has now signed contracts for the
purchase of the two main long lead equipment packages: the crushing
circuit and the DMS processing equipment. Both packages are within
budget forecasts and the team remains on track to meet the overall
project budget of US$65 million for project stage 1.
Crushing
Modules
The dual crushing circuit modules
have been awarded to Beijing High Dynamic Technology Co., Ltd.
("BHD") in China. BHD will provide a turnkey design and supply
package for the dual crushing equipment modules, including all
ancillary equipment, in accordance with the detailed design concept
established with DRA Projects in South Africa. The contract price
is under budget and includes one year of strategic maintenance
spares. The delivery time ex-works is just 3 months, which is
around 2 months quicker than other bidders.
In the past 10 years, BHD has
supplied crushing equipment of similar and much larger capacity to
numerous projects in China and worldwide, including the DRC,
Namibia, Malaysia, Australia, the UK, the USA and South
Africa.
DMS Processing Plant
Equipment
The supply of DMS equipment has been
awarded to Haiwang Technology Group ("Haiwang") in Shandong
Province, China. Haiwang's scope of work includes the provision of
final detailed design services to provide a fully integrated DMS
processing plant, the supply of all processing equipment required
for the DMS operation, and the associated electrical,
instrumentation and process controls. The overall contract price is
within budget, and includes plant commissioning services, one year
of strategic maintenance spares and ongoing operational
support.
Importantly, Haiwang have provided a
superior performance guarantee for the DMS plant based on exceeding
the Company's throughput target and achieving concentrate grade
above the Company's 5.5% target for the production of 125,000 -
130,000 tonnes per annum of spodumene. The Haiwang DMS plant
throughput guarantee is based on achieving 4,848 tonnes per day of
ore feed over a continuous seven-day period. This translates to an
annualised throughput rate of 1.2 million tonnes per annum (after
allowances for routine maintenance and downtime), which provides
the Company with major potential production upside.
The delivery time ex-works is just 3
months, which means that all equipment will be on site within 6
months (allowing for shipping time). This is around 2 months
quicker than other bidders and provides sufficient time for the
Company to complete civil construction works on site in advance of
receiving the Haiwang package, to underpin our goal of becoming a
producer before the end of 2024.
Haiwang is a leading provider of
classifying equipment with a focus on cyclone separation, a key
factor in DMS processing. In the past 10 years, Haiwang has
supplied DMS equipment of similar capacity to numerous DMS projects
worldwide, including China, Namibia and Zimbabwe.
Mining Contract
Award
The project team has finalised
negotiations and awarded the Mining Contract for Bougouni. The
successful group is a consortium between Auxin Mining Services Mali
SARL ("Auxin") and Enterprise Générale Traoré et Fréres SARL
("EGTF"), together "the Mining Contractor". The annualised
mining cost is within the Company's mine operating cost estimate of
US$3.65 per tonne mined, as outlined in the Company's announcement
of 29 September 2022.
Auxin Mining Services Mali SARL is a
subsidiary of Beijing Auxin Chemical Technology Ltd, which is in
turn, a subsidiary controlled by China North Industries Corporation
(NORINCO). Auxin is active in West Africa in the areas of
explosives manufacture and distribution, and contract mining
services. Auxin have existing contract mining operations at
projects in Namibia, Nigeria and Zimbabwe.
EGTF is a fully owned Malian company
and is well established in the fields of earthworks, civils and
contract mining in West Africa. EGTF has worked with numerous
mining companies in West Africa, including Randgold/Barrick (Morila
and Loulo) and AngloGold Ashanti (Siguri).
The cooperation of EGTF and Auxin
will provide the following advantages to the Bougouni
mine:
· Auxin will enhance
the technical proficiency of drilling, blasting and explosives
handling, which EGTF has less direct experience with;
· EGTF will provide
excavate, load and haul services associated with the mining
operation;
· Leverage of the
established presence of EGTF, their local labour pool, and their
social responsibility expertise having worked in many remote areas
in Mali over many years;
· Facilitation of
technical and cultural communication between the Company and the
Mining Contractor overall, with Chinese and French speaking parties
on both sides; and
· As part of the
Norinco Group, Auxin has access to capital that will enable the
mobilisation of new equipment to replace used equipment over the
course of the life of mine.
Environmental and
Social
As part of the Phase 1 DMS
environmental approval update process, the Company submitted an
update of the ESIA (environmental and social impact assessment)
report in early October 2023 to the Mali Environmental Department;
Direction National de
l'Assainissement et du Controle des Pollutions et des
Nuisance ("DNACPN").
Following negotiation with the
DNACPN, this official submission was requested in the form of a
"Notice d'Impacts Environmental
et Social" ("NEIS"). The NEIS updated the ESIA to highlight
the minor adjustments required for the Phase 1 DMS Project,
separate from the original ESIA submission, which focussed on the
flotation pathway that will now be developed as a Phase 2
expansion, and is currently expected to commence development within
2 years' time.
Part of the submission approval
process included a visit to site from representatives of the
DNACPN, accompanied by the Minister of Environment. The site
meeting was very successful and following that site meeting the
department endorsed the NEIS, issuing a formal letter last month
advising of its approval of the NEIS for the implementation of the
DMS project.
Construction
Preparations
The main access road is fully
functional and the payment of compensation to all traditional
landowners is complete. This provides full access to the Ngoualana
mine site for the project team to commence construction
activities.
EGTF will undertake the site
preparation earthworks commencing in early April. In preparation
for establishing the project team on site, modular site offices
have been purchased, including support services required to sustain
the project team at Bougouni.
Forward
Plan
We look forward to updating
shareholders in the coming months as construction commences in
earnest, as we strive to maintain our completion schedule milestone
of being in production before the end of the year.
With the signing of the mining
contractor and the long lead equipment purchases secured with
speedy delivery times, we remain confident in achieving our
production timeline.
Investor
presentation
The management of Kodal will hold an
online presentation on Thursday, 28 March 2024 at 12:30pm GMT. The
presentation will be hosted on the Investor Meet Company platform.
Those interested in joining the online presentation can do so using
the following link:
https://www.investormeetcompany.com/kodal-minerals-plc/register-investor
**ENDS**
For further information, please
visit www.kodalminerals.com or contact the following:
Kodal Minerals plc
Bernard Aylward, CEO
|
Tel: +61 418 943 345
|
Allenby Capital Limited, Nominated
Adviser
Jeremy Porter/Vivek Bhardwaj/Nick
Harriss
|
Tel: 020 3328 5656
|
SP Angel Corporate Finance LLP,
Financial Adviser & Joint Broker
John Mackay/Adam Cowl
|
Tel: 020 3470 0470
|
Canaccord Genuity Limited, Joint
Broker
James Asensio/Ana
Ercegovic
|
Tel: 0207 523 4680
|
Buchanan, Financial PR
Bobby Morse/Oonagh Reidy
|
Tel: +44 (0)20 7466 5000
kodal@buchanancomms.co.uk
|