MONTREAL, Aug. 11,
2023 /CNW/ - Aya
Gold & Silver Inc. (TSX: AYA) (OTCQX: AYASF)
("Aya" or the "Corporation") is pleased to announce interim
financial and operational results for the second quarter ended
June 30, 2023. All amounts are in
thousands of US dollars unless otherwise stated.
Q2-2023 Highlights
Operational and Financial
- Strong operational performance:
-
- Silver production of 526,703 ounces ("oz") in Q2-2023, a 15%
increase from Q2-2022
- Recoveries averaged 87.3% in Q2-2023, compared to 87.9% in
Q2-2022
- Ore processed increased to 72,190 tonnes ("t") in Q2-2023
compared to 59,995t in Q2-2022
- Revenue of $9.6 million in
Q2-2023, a 12% increase from Q2-2022
- Cash cost of $10.98 per oz in
Q2-2023 compared to $10.95 per oz in
Q2-2022 (¹)
- Operating cash flow of $3.7
million in Q2-2023, a 234% increase compared to Q2-2022
- Robust financial position with $52
million of cash, cash equivalents and restricted cash
(²) compared to $42
million at December 31,
2022
- Settled dispute with previous CEO and related Net-Profit
Interest ("NPI") agreement, resulting in the dissolution of the
NPI
Exploration and Development:
- Completed 12,424 meters ("m") of drilling at Zgounder in
Q2-2023
- Conducted 4,634m of diamond drill
hole ("DDH") drilling on Zgounder Regional properties in
Q2-2023:
-
- Preliminary results returned anomalous zinc ("Zn") and copper
("Cu") values including silver ("Ag") intercepts
- Completed 18.7 kilometers ("km") of the 36km DDH program at
Boumadine in Q2-2023:
-
- Extended the strike 400m to
3.8km, which remains open in all directions
- Mapping identified a new at-surface northwest zone that extends
over 1.5km
- Acquired Tirzzit historical copper mine property, which is
67.7km², and rights for $4.7
million
Zgounder Expansion:
- Advanced Zgounder Mine expansion in Q2-2023:
-
- Overall project 45% complete and tracking on budget
- Underground development on track, with 65% of lateral and 42%
of vertical development completed
- Completed detailed engineering, ball mill and crushing
equipment on schedule
- Mobilised open-pit contractor, commenced in-pit stripping and
produced first ore
- Continued construction of the new tailings and water storage
facilities on schedule
(1)
|
The Corporation reports
non-GAAP measures, which include cash costs per silver ounce and
free cash flow, which are widely used in the mining industry as a
benchmark for performance, but do not have a standardized meaning
and the methods used by the Corporation to calculate such measures
may differ from methods used by other companies with similar
descriptions. See "Non-GAAP Measures" on page 15 of the
Corporation's Q2-2023 MD&A for a reconciliation of non-GAAP to
GAAP measures.
|
(2)
|
Non-GAAP Measures,
consisting of cash and cash equivalents of $49,568,497 and
restricted cash of $2,540,987.
|
Long-term Sustainability of Zgounder Operations:
- Continued construction of the 90km power line to connect
Zgounder to renewable grid power
- Provided over 3,040 hours of health & safety training
- Completed emergency response station and took delivery of mine
rescue vehicle and equipment
"Continuing our strong start to the year, Zgounder delivered
another exceptional quarter with strong financials and solid
execution. We benefited from above-capacity milling rates and
higher silver prices, which drove strong cash flow and silver
production of 526,703 ounces as well as lower cash costs," said
Benoit La Salle, President and CEO.
"We continue to execute on our Zgounder expansion, which is 45%
complete and on budget, and are well-positioned to achieve our
full-year production and cost guidance.
In July, we published our 2022 Sustainability Report
highlighting how we have accelerated integration of ESG and climate
change across Aya. We have aligned our operations with the
recommendations of the TCFD and tied executive compensation with
strategic objectives linked to key ESG performance indicators.
Our exploration success and resource growth continued in the
quarter with the strike extension to the south and the discovery of
a northwest zone at Boumadine. We also acquired the historical
Tirzzit copper mine, which adds seven prospective copper-silver
permits near Zgounder. In the near-term, we are adding drill rigs
at Zgounder and Boumadine and mobilizing at Tirzzit and expect to
further extend the Boumadine Main Trend, which will translate into
additional resources in Q1-2024."
Q2-2023 Operational and Financial Highlights
Key Performance
Metrics*
|
|
Q2-2023
|
Q2-2022
|
Variation
|
Operational
|
|
|
|
|
Ore Mined
(t)
|
|
103,231
|
62,221
|
66 %
|
Ore Processed
(t)
|
|
72,190
|
59,995
|
20 %
|
Average Grade (g/t
Ag)
|
|
265
|
273
|
(3 %)
|
Mill Recovery
(%)
|
|
87.3 %
|
87.9 %
|
(<1%)
|
Silver Ingots Produced
(oz)
|
|
202,559
|
219,762
|
(8 %)
|
Silver in Concentrate
Produced (oz)
|
|
324,144
|
239,299
|
35 %
|
Total Silver
Produced (oz)
|
|
526,703
|
459,061
|
15 %
|
Silver Ingots Sold
(oz)
|
|
164,707
|
196,556
|
(16 %)
|
Silver in Concentrate
Sold (oz)
|
|
287,816
|
242,524
|
19 %
|
Total Silver Sales
(oz)
|
|
452,523
|
439,080
|
3 %
|
Avg. Net Realized
Silver ($/oz)
|
|
21.26
|
19.53
|
9 %
|
Cash Costs per Silver
Ounce Sold (¹)
|
|
10.98
|
10.95
|
<1%
|
Financial
|
|
|
|
|
Revenue
|
|
9,621
|
8,574
|
12 %
|
Cost of
sales
|
|
6,876
|
5,811
|
18 %
|
Gross Margin
|
|
2,745
|
2,763
|
(1 %)
|
Operating
(loss)
|
|
(36)
|
506
|
(107 %)
|
Net Earnings
(loss)
|
|
(525)
|
725
|
(172 %)
|
Operating Cash
Flow
|
|
3,674
|
1,100
|
234 %
|
Cash and Restricted
Cash (2)
|
|
52,109
|
67,945
|
(23 %)
|
|
|
|
|
|
Shareholders
|
|
|
|
|
Earnings (Loss) per
Share – basic
|
|
(0.00)
|
0.01
|
NM
|
Earnings (Loss) per
Share – diluted
|
|
(0.00)
|
0.01
|
NM
|
(1,2) See
footnotes (1, 2) on first page
|
Second Quarter 2023 Financial & Operational Highlights
- Quarterly silver production of 526,703 oz, comprising 324,144
oz in silver concentrate and 202,559 oz in silver bars.
- Mill average feed grade of 265 grams per tonne ("g/t") Ag was
reported in Q2-2023 compared to 273 g/t Ag in Q2-2022, a decrease
of 3%.
- Milling operations reached 793 tonnes per day ("tpd"),
surpassing design capacity of 700 tpd.
- Average combined mill recovery of to 87.3% in Q2-2023 compared
to 87.9% in Q2-2022, a decrease of 0.6%.
- Plant availabilities reached 93.4% and 96.6% for the flotation
and cyanidation plants, respectively.
- Cash flow generated by operating activities of $3,674 in Q2-2023 compared to cash flow of
$1,100 in operating cash flow in
Q2-2022.
- Revenue from silver sales totaled $9,621 (Q2-2022 – $8,574) in Q2-2023, an increase of 12%
representing an average realized price of $21.26/oz. (Q2-2022 - $19.53/oz).
- Operations generated a gross margin of $2,745 in Q2-2023, a 1% decrease compared to
Q2-2022.
- Net loss for the quarter was $(525) (diluted EPS of $(0.00)) in Q2-2023, compared to net earnings of
$725 (diluted EPS of $0.01) in Q2-2022.
Q2-2023 Operations Review
In Q2-2023, Zgounder Mine operations focused on the ramp-up of
the underground mine, completing mobilization of the open pit
contractor and finalizing the open-pit definition drilling program.
The 1,950m underground level is now
fully operational, and access to the 1,925m level is in construction. Open-pit
stripping commenced in June, and ore production occurred in July. A
total of 103,231t of ore was mined and 72,190t was processed in Q2,
adding over 30kt of ore in inventory, in line with the 2024
commissioning plan.
The quarter saw completion of the new emergency response and
mine rescue station as well as on-site delivery of mine rescue
equipment and an emergency vehicle. Consequently, training for the
mine rescue and emergency response teams has been scheduled in the
second half of the year. Over 4,075 hours of training have been
dispensed year to date, a 150% increase compared to H1-2022 which
reflects the Corporation's commitment to enhancing the health and
safety culture at Zgounder.
Zgounder Development
Construction of the plant and surface infrastructure continued
to track on budget. At the end of Q2-2023, the mine expansion
project was 45% complete, compared to 32% at end of Q1-2023.
Construction of the processing plant was 40% complete, with
engineering near-complete and procurement well advanced. Earthworks
were completed in the quarter, and most concrete foundations were
poured. Delivery of several long-lead equipment items are expected
on site in Q3-2023, including the ball mill.
Underground development continued to advance strongly in the
quarter. Over 6,500m of lateral and
ramp accesses have now been completed, representing 65% of the
total lateral infrastructure. Most levels between 1,925m and 2,100m
are now connected to the underground ramp. The main ventilation
shaft has been completed, and installation of primary fans is
planned for Q3-2023. To date, 253m of
vertical raises have been completed, 42% of the total development.
In June, the open pit contractor was mobilized, and open pit
operations commenced. Overall, open pit and underground mine
development are 47% advanced.
At quarter-end, construction of the tailing storage facility was
progressing well and was 55% complete. The two water storage basins
were 74% complete with only the lining installation remaining, in
time before the rainy season. Other infrastructure, such as the
camp, roads, workshops, and warehouses, were 55% completed.
Finally, the power line and electrical substations progressed to
27% completion.
At the end of Q2-2023, $132
million had been committed across all capital cost
categories, and $54 million had been
incurred. The Aya project team remains confident of completing the
project within the original budget of $159
million including contingency.
The table below presents construction progress by main project
area:
Area
|
Progress
|
Process
Plant
|
40 %
|
Underground and
Open-Pit Mines
|
47 %
|
Tailings
|
55 %
|
Water
Management
|
74 %
|
Electrical
Infrastructure
|
27 %
|
On-site
Infrastructure
|
55 %
|
Q2-2023 Exploration
Zgounder
In Q2-2023, drilling at Zgounder focused on delineating
near-mine targets both laterally and at depth. A total of
12,424m of DDH and reverse
circulation ("RC") drilling was conducted on Zgounder in Q2-2023
(exploration and definition drilling) including T28 and YAK
underground drilling. At quarter-end, two underground rigs were
active on the property and the 26,000m underground DDH program was 17% complete.
Given that the development of the 1,950m level is complete and the 1,925m level is near-complete, the exploration
program is expected to be expanded in H2-2023.
Notably, surface RC drill hole ZG-RC-23-2260-70 intersected
1,611 g/t Ag over 27m including 4,771
g/t Ag over 5.0m, confirming ongoing
high-grade mineralization in the open-pit area. Furthermore, hole
ZG-23-02 returned 1,753 g/t Ag over 6.5m, defining high-grade mineralization from
surface in the east outside of the resource envelope.
Zgounder Regional
At the end of June 2023, a total
of 8,582m had been drilled on the
Zgounder Far West, Tala and Izza areas of the Zgounder Regional
permits. Preliminary results released at the end of May returned
anomalous Zn, Cu and Ag values that will be drill tested in
parallel to new zones. Hole ZGW-22-06 in the Zgounder Far West
intercepted 1.22% Zn over 85.5m
including 1.91% Zn over 5.0m. In the
Tala area, hole AM-22-001 intercepted 0.93% Cu over 6.0m including 1.27% Cu over 3.0m.
Boumadine
Five drill rigs were active on the Boumadine property throughout
the second quarter with a total of 31,395m drilled in H1-2023. The 2023 drill
program, which was 85% complete at quarter-end, was completed in
July. The aim of the infill and exploration drilling was to explore
and extend the strike along the main trend in the Central and South
Zones. In early July, results from Q2-2023 drilling were released,
confirming the extension of the main trend mineralization by
400m to 3.8km in strike to the south
with BOU-DD23-125, BOU-DD23-136 and BOU-DD23-142 intersecting
high-grade mineralization in the form of massive sulphide
veins.
In parallel, results from surface detailed mapping were received
in Q2-2023 which identified a new at-surface northwest zone at
Boumadine. The surface samples returned values up to 460 g/t
AgEq along a 1.5km structure of N030 orientation,
demonstrating the potential outside of the Boumadine Main Trend
(see Figure 7). The mapping revealed two major sets of faulting
events: a N030 faulting event that cross-cut Boumadine Main Trend
(N340) and may be responsible for the Au-Zn enrichment of the
mineralization; and a N070 fault event cutting both N340 and N070
structures which seem responsible for the Ag-Pb enrichment. A total
of 127 surface grab samples were also taken, with 36 still pending
results.
The quarter saw a first site visit by RSC Consulting Limited,
which has been mandated to conduct a NI 43-101-compliant mineral
resource estimate of Boumadine. Furthermore, an on-site sample
preparation laboratory was commissioned on the project site, which
will greatly improve sample turnaround times.
The technical information relating to Zgounder, Zgounder
Regional and Boumadine properties was reviewed and approved by
David Lalonde, B. Sc, Head of
Exploration, designated as a Qualified Person under National
Instrument 43-101.
Acquisition of Tirzzit
On June 28, 2023, the Corporation
acquired Tirzzit, a collection of seven permits located 25 km from
the Zgounder Silver Mine in the Kingdom of Morocco.
The Corporation issued 622,728 of its shares at C$8.36 (having a value of $3.9M) and paid $800,000 in cash for a total consideration of
$4.7 million. The assets acquired
include the following:
- Seven permits, comprising five exploration permits and two
mining licenses, one of which hosts a high-grade historical copper
mine.
- A property totaling 67.7 square km.
The transaction remains subject to administrative procedures in
the Kingdom of Morocco.
Q2-2023 Conference Call
The Corporation will hold a conference call today at
10 am EDT to discuss its Q2-2023
financial and operational results. The webcast can be accessed as
follows:
- Via webcast: https://app.webinar.net/PblE8kG8eLX
- Via URL entry: https://emportal.ink/3NONQbo
To join the call without operator assistance, register and enter
your phone number to receive an instant automated call back.
- Via telephone: Local and international: (+1) 416-764-8650
N. American Toll Free:
888-664-6383
You can also dial direct to be entered to the
call by an operator. To ensure your participation, please call
approximately five minutes prior to the scheduled start of the
call.
The conference call and webcast will be available for replay by
dialing (+1) 416-764-8677 or toll-free on 1-888-390-0541, entry
code 370442 #. The conference call replay will expire on
August 18, 2023.
The presentation slides will also be posted on Aya's
website.
About Aya Gold & Silver
Inc.
Aya Gold & Silver Inc. is a
rapidly growing, Canada-based
silver producer with operations in the Kingdom of Morocco.
The only TSX-listed pure silver mining company, Aya operates the
high-grade Zgounder Silver Mine and is exploring its properties
along the prospective South-Atlas Fault, several of which have
hosted past-producing mines and historical resources. Aya's
Moroccan mining assets are complemented by its Tijirit Gold Project
in Mauritania, which is being
advanced to feasibility.
Aya's management team is focused on maximising shareholder value
by anchoring sustainability at the heart of its operations,
governance, and financial growth plans.
For additional information, please visit Aya's website at
www.ayagoldsilver.com.
Forward-Looking Statements
This press release contains certain statements that constitute
forward-looking information within the meaning of applicable
securities laws ("forward-looking statements"), which reflects
management's expectations regarding Aya's future growth and
business prospects (including the timing and development of new
deposits and the success of exploration activities) and other
opportunities. Wherever possible, words such as "will", "expect",
"maintain", "achieve", "expand", "ramp-up", "plan", "as-planned",
"tracking", "guidance", "potential", "deliver", "committed",
"continue", "growth", "advance", "expected", "increase", and
similar expressions or statements that certain actions, events or
results "may", "could", "would", "might", "will", or are "likely"
to be taken, occur or be achieved, have been used to identify such
forward-looking information. Specific forward-looking statements in
this press release include, but are not limited to, statements and
information with respect to the exploration and development
potential of Zgounder and the conversion of Inferred Mineral
Resources into Measured and Indicated Mineral Resources, future
opportunities for enhancing development at Zgounder, executing on
the planned expansion at the Zgounder mine, and timing for the
release of the Company's disclosure in connection with the
foregoing. Although the forward-looking information contained in
this press release reflect management's current beliefs based upon
information currently available to management and based upon what
management believes to be reasonable assumptions, Aya cannot be
certain that actual results will be consistent with such
forward-looking information. Such forward-looking statements are
based upon assumptions, opinions and analysis made by management in
light of its experience, current conditions, and its expectations
of future developments that management believe to be reasonable and
relevant but that may prove to be incorrect. These assumptions
include, among other things, the closing and timing of financing,
the ability to obtain any requisite governmental approvals, the
accuracy of Mineral Reserve and Mineral Resource Estimates
(including, but not limited to, ore tonnage and ore grade
estimates), silver price, exchange rates, fuel and energy costs,
future economic conditions, anticipated future estimates of free
cash flow, and courses of action. Aya cautions you not to place
undue reliance upon any such forward-looking statements. The risks
and uncertainties that may affect forward-looking statements
include, among others: the inherent risks involved in exploration
and development of mineral properties, including government
approvals and permitting, changes in economic conditions, changes
in the worldwide price of silver and other key inputs, changes in
mine plans (including, but not limited to, throughput and
recoveries being affected by metallurgical characteristics) and
other factors, such as project execution delays, many of which are
beyond the control of Aya, as well as other risks and uncertainties
which are more fully described in Aya's 2022 Annual Information
Form dated March 31, 2023, and in
other filings of Aya with securities and regulatory authorities
which are available on SEDAR at www.sedar.com. Aya does not
undertake any obligation to update forward-looking statements
should assumptions related to these plans, estimates, projections,
beliefs and opinions change. Nothing in this document should be
construed as either an offer to sell or a solicitation to buy or
sell Aya securities. All references to Aya include its subsidiaries
unless the context requires otherwise.
SOURCE Aya Gold & Silver
Inc