Arcan Resources Ltd. (TSX VENTURE:ARN) ("Arcan" or the "Corporation") has
approved a $26.0 million capital expenditure budget for the first half of 2013
and estimates its full year 2013 budget at $52.0 million. The 2013 budget
includes drilling an estimated 13 gross (9.4 net) wells. Arcan also completed a
disposition of one and three-quarters sections of undeveloped land in 64-09W5
for proceeds of $10.0 million. The land sold was located in the southern-most
area of Arcan's Swan Hills acreage, did not have any associated production, and
was isolated from Arcan's existing core production and infrastructure. 


Arcan announces a capital budget program of $26.0 million for the first half of
2013, including an estimated $14.0 million towards drilling seven (4.4 net)
wells with the remainder being spent on infrastructure, recompletions, and
waterflood activities. Arcan currently estimates 2013 production to be
approximately 4,300 to 4,700 boe per day, an increase to the average production
rate for the second half of 2012, which Arcan estimates to be approximately
3,950 boe per day, net of dispositions. In line with its strategic direction,
Arcan plans to manage capital within its estimated cash flow stream for 2013. 


The land sale is consistent with Arcan's stated intention to dispose of non-core
assets through a number of targeted dispositions. Arcan remains focused on the
excellent opportunities in its core operating areas and the sale proceeds will
be applied directly against the debt on the balance sheet. Arcan is pleased with
this sale price, as only $0.5 million had been invested in these lands and
development had not yet begun. Arcan's strategy continues to be to maximize and
extract value in the forms of strategic sales or farm-outs, without sacrificing
the development inventory. Arcan expects to continue reviewing all aspects of
its assets, operations, and governance to strengthen its operational capability,
capital efficiencies, and to support its base of production. Along that line,
the first PetroBakken Energy Ltd. farm-out well at 06-28-68-09W5 was on-stream
November 29, 2012. After completing its production testing period, this well is
now producing into a pipeline directly into Arcan's production facilities. The
second well in this five to seven well program has already been drilled at
04-19-66-09W5 with completion expected in the first quarter of 2013. Arcan is
currently drilling the third well of this program at 05-01-67-09W5. Arcan has
also completed and commenced production on three of the four wells on its
10-05-68-08W5 pad. The fourth well is currently in the process of being
completed.


Arcan will focus on developing the large light oil resource in the Swan Hills
area. In addition to concluding the majority of the development in Deer Mountain
Unit #2, Arcan has transformed its Ethel area, which is comprised of 74 sections
of land, into a large development inventory of drill-ready locations. This asset
is now supported by an infrastructure corridor consisting of all weather roads,
pipelines, and facilities. As at June 30, 2012, Arcan's external independent
reserve auditors had recognized recoverable remaining reserves of 8.9 million
boe on a total proved plus probable reserve basis in Deer Mountain Unit #2, and
18.9 million boe on a total proved plus probable reserve basis in Ethel. The
investments over the last 18 months in the Ethel corridor provide the ground
work for Arcan to begin to capitalize on the value of the oil assets in Ethel.
In addition to the Ethel corridor development, Arcan is focused on development
of its farm-out lands in 2013, in order for Arcan to accelerate exploitation of
its land base as management feels that this would be an advantageous time to do
so given the current state of the capital markets.


Arcan will continue to shift to a program of sustainable growth, supported by a
strengthened balance sheet and focused cost reductions. Arcan continues to take
a measured approach to capital investment focused on capital efficiencies where
higher capital spending during the winter months is followed by a curtailment of
capital during times when access is only possible at an increased cost. Arcan
estimates that using a more measured approach to capital spending will allow for
wells to be drilled, completed, and tied-in at a cost of $4.5 million to $5.0
million. The 2013 drilling program will focus on high graded locations
throughout Arcan's land base with the balance of the capital program targeting
production constraints and the expansion of the waterflood process. To secure
the capital program and cash flow Arcan is hedged at 2,000 barrels per day for
all of 2013 and 2014 at approximately $100.00 and $93.00 West Texas
Intermediate, respectively. 


Arcan will continue its efforts to control committed capital and the pace of its
development. This is expected to ensure that the Corporation can continue
financially sustainable growth and efficient deployment of capital. The changing
capital market environment is driving Arcan to make operational adjustments as
well. The recently announced farm-outs to PetroBakken Energy Ltd. provide for
capital-efficient development on areas stretching across Arcan's land base that
would not otherwise have been developed in the near term. Arcan will continue to
implement changes that provide for a stable financial base, maximize shareholder
value and provide secure growth per share as Arcan transitions to a more
efficient oil producer positioned for long term success. Holding a large
multi-year light oil development inventory, Arcan's management continues to look
strategically at all of Arcan's assets and will consider all opportunities for
development and acceleration as they arise. 


Arcan recently launched its new website at www.arcanres.com. The website has
been redesigned and features improved functionality to enhance the quality of
the Corporation's disclosure. The new website contains standard disclosure
materials, including information explaining the waterflood secondary recovery
technique, news releases, financial documents and presentations, as well as
supplemental information for the benefit of the investment community.
Information is expected to be added shortly to include a new corporate
presentation and a question and answer document that addresses some of the
questions that Arcan's management frequently receive.


About Arcan Resources Ltd.

Arcan Resources Ltd. is an Alberta, Canada corporation that is engaged in the
production, development, exploration and acquisition of petroleum and natural
gas located in Canada's Western Sedimentary Basin. 


Legal Advisories

Barrels of oil equivalent ("boe") may be misleading, particularly if used in
isolation. A boe conversion ratio of six thousand cubic feet ("Mcf") of natural
gas to one barrel ("bbl") of oil is based on an energy equivalency conversion
primarily applicable at the burner tip and does not represent a value
equivalency at the wellhead. In addition, given that the value ratio based on
the current price of oil as compared to natural gas is significantly different
from the energy equivalent of six to one, utilizing a boe conversion ratio of 6
Mcf : 1 bbl would be misleading as an indication of value. 


All reserves information contained within this press release comes from our
independent reserves report prepared by GLJ Petroleum Consultants Ltd. with an
effective date of June 30, 2012. The estimates of reserves for individual
properties may not reflect the same confidence level as estimates of reserves
for all properties, due to the effects of aggregation.


Forward-Looking Information and Statements

This press release contains certain forward-looking information and statements
within the meaning of applicable securities laws. The use of any of the words
"estimates", ''expects'', ''will'', ''plans'' and similar expressions are
intended to identify forward-looking information or statements. In particular,
but without limiting the foregoing, this press release contains forward-looking
information and statements pertaining to, among other things, the following:
anticipated average production for the second half of 2012; anticipated average
production for 2013; anticipated timing of the fracture and completion of
Arcan's recent wells; the expected use of proceeds from the disposition of the
Swan Hills land; the 2013 capital expenditure program including drilling and
expectations; anticipated operating costs for 2013; Arcan's expectations
respecting its growth, activities and the deployment of capital throughout the
remainder of 2012 and 2013; Arcan's strategic direction; Arcan's development and
ability to implement and execute its 2013 business plans and strategic
direction; Arcan's review of all aspects of assets, operations and governance;
Arcan's consideration of development opportunities; the launch and contents of
the Corporation's website; future growth including development, exploration,
acquisition, construction and operational activities and related expenditures. 


The forward-looking information and statements contained in this press release,
including but not limited to the estimates of 2012 and 2013 annual production,
reflect several material factors and expectations and assumptions of Arcan
including, without limitation: that Arcan will continue to conduct its
operations in a manner consistent with past operations; the lack of any adverse
weather conditions; the lack of significant changes in capital markets or
commodity prices; the accuracy of current horizontal production data, historical
well production and waterflood results; the general continuance of current or,
where applicable, assumed industry conditions; continuity of reservoir
conditions across Arcan's Swan Hills land base and its Ethel oil pool;
availability of debt and/or equity sources to fund Arcan's capital and operating
requirements as needed; the continuance of existing and, in certain
circumstances, proposed tax and royalty regimes; the accuracy of the estimates
of Arcan's reserve volumes; and certain commodity price and other cost
assumptions and estimates. 


Arcan believes the material factors, expectations and assumptions reflected in
the forward-looking information and statements are reasonable at this time but
no assurance can be given that these factors, expectations and assumptions will
prove to be correct. The forward-looking information and statements included in
this press release are not guarantees of future performance and should not be
unduly relied upon. Such information and statements involve known and unknown
risks, uncertainties and other factors that may cause actual results or events
to differ materially from those anticipated in such forward-looking information
or statements including, without limitation: for reasons currently
unanticipated, Arcan's production rates may not reach the levels currently
expected; the application and modification of horizontal, multi-stage fracture
technologies may not have the impact currently anticipated by Arcan; the future
drilling locations identified by Arcan may prove to be unsuitable or unavailable
and drilling on the locations identified may not occur; water injection at
additional sites in the Deer Mountain Unit #2 or in the Ethel field may not have
the impact on production currently anticipated by Arcan; Arcan's capital
spending and operational plans for 2013 may not be completed in the timelines
anticipated, in the manner anticipated or at all and the execution of such plans
may be negatively affected further; changes in tax or environmental laws or
royalty rates; increased debt levels or debt service requirements; inaccurate
estimation of Arcan's oil and gas reserves volumes; limited, unfavourable or no
access to debt or equity capital markets; increased costs and expenses; the
impact of competitors; changes in commodity prices; reliance on industry
partners; and certain other risks detailed from time to time in Arcan's public
disclosure documents including, without limitation, those risks identified in
this press release, and in Arcan's annual information form for the year ended
December 31, 2011, copies of which are available on Arcan's SEDAR profile at
www.sedar.com.


The forward-looking information and statements contained in this press release
speak only as of the date of this press release and Arcan does not assume any
obligation to publicly update or revise them to reflect new events or
circumstances, except as may be required pursuant to applicable laws.


FOR FURTHER INFORMATION PLEASE CONTACT: 
Arcan Resources Ltd.
Terry McCoy
Chief Executive Officer
(403) 262-0321
tmccoy@arcanres.com


Arcan Resources Ltd.
Douglas Penner
President
(403) 262-0321
dpenner@arcanres.com


Arcan Resources Ltd.
Suite 2200, 500 - 4th Avenue S.W.
Calgary, AB T2P 2V6

Grafico Azioni (TSXV:ARN)
Storico
Da Apr 2024 a Mag 2024 Clicca qui per i Grafici di
Grafico Azioni (TSXV:ARN)
Storico
Da Mag 2023 a Mag 2024 Clicca qui per i Grafici di