After-Tax NPV of $1.1B and 31% IRR and Two New Satellites to be
Advanced
VANCOUVER, BC, Jan. 16,
2024 /PRNewswire/ -- Montage Gold Corp.
("Montage" or the "Company") (TSXV: MAU) (OTCPK: MAUTF) is pleased
to announce the results of the Updated Definitive Feasibility Study
(the "UFS" or the "Study") for the Koné Gold Project ("Koné Gold
Project", "Project", or "KGP") located in Côte d'Ivoire, which now
incorporates ore from the Gbongogo Main satellite deposit. The UFS
was prepared by Lycopodium Minerals Pty Ltd. in accordance with
Canadian Securities Administrators' National Instrument 43-101
Standards of Disclosure for Mineral Projects ("NI 43-101"). Please
note that all financial figures in this press release are in
United States dollars, unless
otherwise noted.
Highlights
- Significant Reserves and Production – A New Gold District in
Côte d'Ivoire
- 4.01Moz of Probable Mineral Reserves
- 3.57Moz of gold produced over a 16-year mine life
- Years 1-3: Avg. annual production of 349,000 oz at 1.15g/t
avg. head grade
- Years 1-8: Avg. annual production of 301,000 oz at 0.96g/t
avg. head grade
- Peak production of 378,000 oz in year 3
- Strong Financial Metrics – In an Increasing Cost
Environment
- $1,089M after-tax
NPV5% and 31% IRR at base case $1,850/oz gold price
- $1,456M after-tax
NPV5% and 39% IRR at spot $2,050/oz gold price
- Years 1-3: Avg. AISC1 of $899/oz
- LOM AISC1 of $998/oz
- Capital payback period of 2.6 years
- Optimizations Maintain Capital Efficiency – Further
Improvements Expected
- Pre-production capital requirement of $712M (vs $544M
from 2022 DFS)
- $126M reduction in sustaining
capital vs 2022 DFS
- Net increase in LOM total capital requirements of 5%
compared to 2022 DFS
- Several areas identified to optimize pre-production
capital
- Impact of Gbongogo Main Deposit
- Gbongogo Main represents 12% of Probable Reserves and
contributes $350M in pre-tax net cash
flow in first 3 years of operations
- Optimizes capital payback; demonstrates impact of satellite
deposits
- Planned haul road opens 38km corridor for priority
exploration
- KGP Construction Planned for Q4 2024
- Permitting process ongoing with all requisite approvals
expected in Q3 2024
- Project financing process underway
- Drilling to Continue in January on Next Satellite Deposit
Targets – Diouma North and Petit Yao
- Diouma North is located 2km south of Gbongogo Main and
<500m from planned haul road
- Recent Diouma North drilling included: 17.45m at 2.75g/t, 11m at 2.21g/t and 14m at 2.16g/t
- Petit Yao is located 3km from planned haul road
- Previous Petit Yao results included: 12m at 4.15g/t, 6m
at 10.82g/t, and 3m at 15.51g/t
Rick Clark, Montage CEO
commented,
"The completion of the UFS for the Koné Gold Project is the
culmination of a business plan of target identification,
exploration, economic analysis, and development assessment and
represents the hard work, dedication, and expertise since 2009 of
what is now the Montage team. I am extremely proud of what this
team has accomplished at the KGP since this opportunity was first
recognized by Hugh Stuart (President
of Montage) while investigating growth projects for Red Back Mining
in 2008-09.
"In the three years since Montage went public, we have
evolved from an exploration company with a 1.5Moz Inferred Mineral
Resource into a development company with Probable Mineral Reserves
of +4Moz and total Indicated Mineral Resources of nearly 5Moz. The
KGP is now positioned to become the largest gold mine in Côte
d'Ivoire with an expected average gold production of 349,000 oz per
year during the initial 3 years of operations at an AISC of less
than $1,000/oz, leading to a short
payback on capital of 2.6 years.
"The primary objective of the UFS was to optimize the
economics of the Koné Gold Project by incorporating higher grade
tonnes from Gbongogo Main. This change has materially de-risked the
financial parameters of the Project and demonstrates the
significant impact of discovering higher grade satellite deposits
within the broad 2,259 sq. km property package held 100% by
Montage. We will now focus on repeating this success as we advance
the next near-term satellite deposits within the KGP, notably
Diouma North and Petit Yao, both of which are in close proximity to
the planned haul road.
"The success we have achieved to date with the Koné Gold
Project highlights Côte d'Ivoire as a premier jurisdiction for gold
exploration and development. The combination of the geological
endowment of Côte d'Ivoire and the business focussed political will
of the Government of Côte d'Ivoire, represents a formula for mining
success. Côte d'Ivoire is a partner in every respect in the
development of its natural resources and the Koné Gold Project is a
perfect example of this. The construction of the KGP will be the
largest investment in a gold project in Côte d'Ivoire to date and
we look forward to working with the Government of Côte d'Ivoire to
realize success for all stakeholders."
A summary of operating and financial metrics from the UFS are
presented in Table 1 below along with a comparison to the 2022
DFS. A summary model with annual projections over the project life
has been included as Appendix 1 to this Release.
Table 1 – UFS Summary
Metrics
Metrics
|
Units
|
UFS
|
2022 DFS
|
Pit Optimization Gold
Price
|
$/oz
|
$1,550
|
$1,250
|
Financial Model Base
Case Gold Price
|
$/oz
|
$1,850
|
$1,600
|
Life of Mine
|
years
|
16.0
|
14.8
|
Total Material
Processed
|
Mt
|
174.3
|
161.1
|
Contained Gold
(Probable Reserves)
|
Moz
|
4.01
|
3.42
|
Strip Ratio
|
w:o
|
1.18:1
|
0.90:1
|
Average Annual Mining
Rate
|
Mtpa
|
42.4
|
35.0
|
Mill
Throughput
|
Mtpa
|
11.0
|
11.0
|
Average Head Grade,
first 3 years
|
Au g/t
|
1.15
|
0.93
|
Average Head Grade,
first 8 Years
|
Au g/t
|
0.96
|
0.81
|
Average Head Grade,
LOM
|
Au g/t
|
0.72
|
0.66
|
Processing Recovery,
first 3 Years
|
%
|
89.6 %
|
91.1 %
|
Processing Recovery,
first 8 Years
|
%
|
90.0 %
|
90.3 %
|
Processing Recovery,
LOM
|
%
|
89.0 %
|
89.3 %
|
Total Gold Production,
LOM
|
Moz
|
3.57
|
3.06
|
Average Gold
Production, first 3 years
|
koz/yr
|
349
|
285
|
Average Gold
Production, first 8 years
|
koz/yr
|
301
|
255
|
Average Gold
Production, LOM
|
koz/yr
|
223
|
207
|
Mining Cost Per Tonne
Mined, LOM
|
$/t, mined
|
$3.22
|
$2.73
|
Mining Cost Per Tonne
Processed, LOM
|
$/t,
processed
|
$6.68
|
$5.20
|
Processing Cost, LOM
(incl. rehandle)
|
$/t,
processed
|
$8.94
|
$8.04
|
G&A, LOM
|
$/t,
processed
|
$0.98
|
$0.93
|
Royalties,
LOM
|
$/t,
processed
|
$2.84
|
$1.97
|
Total Operating Costs,
LOM
|
$/t,
processed
|
$19.83
|
$15.89
|
Average AISC, first 3
years
|
$/oz
|
$899
|
$824
|
Average AISC,
LOM
|
$/oz
|
$998
|
$933
|
Initial Capital
Expenditure
|
$M
|
$712
|
$544
|
Sustaining Capital
(incl. Closure)
|
$M
|
$165
|
$292
|
Total LOM Capital
(incl. Closure)
|
$M
|
$877
|
$836
|
NPV5%,
pre-tax (100%)
|
$M
|
$1,437
|
$992
|
Pre-tax IRR
|
%
|
34.6 %
|
39.6 %
|
NPV5%,
after-tax (100%)
|
$M
|
$1,089
|
$746
|
After-tax
IRR
|
%
|
31.0 %
|
34.8 %
|
Payback
Period
|
years
|
2.6
|
2.7
|
Details
Koné Gold Project Overview
The Koné Gold Project is located approximately 470km
north-west of Abidjan, the
commercial capital of Côte d'Ivoire. The Project comprises six
exploration permits (PR262, PR748, PR842, PR879b, PR919 and PR920)
covering 1,801 sq. km and two applications covering a further 456
sq. km, for a combined total of 2,259 sq. km.
The communities of Fadiadougou and Batogo lie 5km east and west
respectively of the Koné resource area and the village of Gbongogo
is located 4km north-west of the Gbongogo Main resource. The
village of Dolourogoukaha will be impacted by the development pf
the Gbongogo Main pit and will be resettled outside the affected
area. Beyond this, the Project area is largely devoid of habitation
with subsistence farming and cashew plantations being the dominant
land use.
The nearest major centre is Séguéla, 80km to the south. The
Project area is accessible year-round with an asphalt highway
within 300m of the proposed plant
location.
Figure 1: Location of Koné Gold Project
Drilling to Start in January at Next Satellite Deposit
Targets
Exploration during Q4 2023 focussed on continued assessment of
the numerous targets within the KGP covered by the program in H1
2023 and several new areas of artisanal mining activity.
A key priority area is Diouma-Gbongogo-Korotou shear zone
(Figure 2), a 15km strike length of soil anomalism, artisanal
mining and 9 targets drilled to some degree, with the Gbongogo Main
pit and planned haul road located at the south end.
In addition, Montage will be re-starting exploration at the
Petit Yao target which sits 7km east of Koné and just 3km southeast
of the planned haul road.
Figure 2: Diouma-Gbongogo-Korotou Shear Zone and District
Target Areas
The Diouma North prospect is located 2km south of Gbongogo Main,
and less than 500m from the planned
haul road. As follow-up to reconnaissance and RC drilling in early
2023, Montage completed three diamond core holes, with highlight
intercepts including: 14m at 2.16g/t
from 58m (GBDDH062); and 17.45m at 2.74g/t from 79m and 11m at
2.21g/t from 127m (GBDDH064). Diamond
drilling at Diouma will re-commence by the end of January with an
initial core programme which, if successful, will be followed up
with an RC programme with the aim of defining an initial resource
by mid-2024. Results presented in Table 2 below represent
intercepts that have intersected the targeted mineralized area. A
complete set of previously unreleased results is included in
Appendix 2 of this press release.
Table 2: Highlight Drill Results from
Diouma North
Hole
|
From
|
To
|
Length
|
Au
|
|
(m)
|
(m)
|
(m)
|
g/t
|
GBRC065*
|
24
|
47
|
23
|
1.43
|
53
|
75
|
22
|
1.55
|
GBRC067*
|
51
|
59
|
8
|
7.39
|
GBRC070*
|
12
|
24
|
12
|
2.61
|
GBRC071*
|
79
|
94
|
15
|
3.84
|
GBRC073
|
7
|
21
|
14
|
1.73
|
GBDDH062
|
58
|
72
|
14
|
2.16
|
GBDDH064
|
78.85
|
96.30
|
17.45
|
2.74
|
127
|
138
|
11
|
2.21
|
* previously released
intercepts.
|
The Petit Yao target sits approximately 7km east of the Koné
deposit and 3km southeast of the planned haul road. It was first
identified in late 2019 by Montage geologists recognizing
prospective volcanic rocks in an area previously assumed to be
un-prospective. Drilling completed at Petit Yao includes
3,392m of RC and 681m of shallow aircore, with highlight
intercepts shown in Table 3 below.
Table 3: Highlight Drill Results from
Petit Yao
Hole
|
From
|
To
|
Length
|
Au
|
|
(m)
|
(m)
|
(m)
|
g/t
|
MRCAC128*
|
0
|
12
|
12
|
4.15
|
MRPYRC030A*
|
37
|
43
|
6
|
10.82
|
MRPYRC039*
|
28
|
31
|
3
|
15.51
|
MRPYRC049*
|
35
|
39
|
4
|
8.31
|
* previously released
intercepts.
|
In H1 2022, an IP survey was completed over Petit Yao, which
clarified a strong northwest trend to the underlying geology and
has resulted in a re-interpretation which now extends over a strike
of approximately 900m. This new
interpretation will be drill tested in Q1 2024.
Mineral Resources and Reserves Estimates
Recoverable Mineral Resources were estimated for the Koné and
Gbongogo Main deposits by Matrix Resource Consultants Pty Ltd.
using Multiple Indicator Kriging ("MIK").
Koné Deposit
The Mineral Resource Estimate ("MRE") for the Koné deposit has
been re-stated based on an optimal pit shell generated using cost
inputs in line with the UFS and a gold price of $1,800/oz with an effective date of 19 December 2023.
Table 4 shows the Indicated and Inferred Mineral Resource
estimates at a range of cut-off grades.
Table 4 – Koné Mineral Resource
Estimate
Cut-off
Grade
|
Indicated
|
Inferred
|
Au g/t
|
Mt
|
Au g/t
|
Au Moz
|
Mt
|
Au g/t
|
Au Moz
|
0.1
|
286
|
0.50
|
4.60
|
37
|
0.3
|
0.36
|
0.2
|
229
|
0.59
|
4.34
|
25
|
0.5
|
0.40
|
0.3
|
170
|
0.70
|
3.83
|
16
|
0.6
|
0.31
|
0.4
|
130
|
0.81
|
3.39
|
10
|
0.7
|
0.23
|
0.5
|
100
|
0.92
|
2.96
|
7.0
|
0.8
|
0.18
|
0.6
|
78
|
1.03
|
2.58
|
5.0
|
0.9
|
0.14
|
0.7
|
61
|
1.14
|
2.24
|
3.0
|
1.1
|
0.11
|
0.8
|
47
|
1.25
|
1.89
|
2.0
|
1.2
|
0.08
|
Notes:
- The MRE is reported on a 100% basis and is constrained
within an optimal pit shell generated at a gold price of
US$1,800/ounce.
- The identified Mineral Resources are classified according to
the "CIM" definitions of Indicated Mineral Resources and Inferred
Mineral Resources.
- The MRE was prepared by Mr. Jonathon Abbott of Matrix Resource Consultants
of Perth, Australia who is a
Qualified Person as defined by NI 43-101.
- The estimate at 0.2g/t represents the base case or preferred
scenario for Koné.
- Mineral Resources are reported inclusive of Mineral
Reserves.
- Mineral Resources that are not Mineral Reserves do not have
demonstrated economic viability.
- Figures are rounded to reflect the precision of the
estimates.
Gbongogo Main Deposit
The Mineral Resource Estimate ("MRE") for the Gbongogo Main
deposit is constrained within an optimal pit shell generated using
cost inputs in line with the UFS and at a gold price of
$1,800/oz with an effective date of
19 December 2023.
Table 5 shows the Indicated and Inferred Mineral Resource
estimates at a range of cut-off grades.
Table 5 – Gbongogo Main Indicated
Mineral Resource Estimate
Cut-off
Grade
|
Indicated
|
Au g/t
|
Mt
|
Au g/t
|
Au Moz
|
0.2
|
15
|
1.16
|
0.56
|
0.3
|
14
|
1.26
|
0.57
|
0.4
|
12
|
1.37
|
0.53
|
0.5
|
11
|
1.48
|
0.52
|
0.6
|
9.9
|
1.59
|
0.51
|
0.7
|
8.8
|
1.71
|
0.48
|
0.8
|
7.8
|
1.83
|
0.46
|
0.9
|
6.9
|
1.96
|
0.43
|
1.0
|
6.1
|
2.09
|
0.41
|
Notes:
- The MRE is reported on a 100% basis and is constrained
within an optimal pit shell generated at a gold price of
US$1,800/ounce.
- The identified Mineral Resources are classified according to
the "CIM" definitions of Indicated Mineral Resources and Inferred
Mineral Resources.
- The MRE was prepared by Mr. Jonathon Abbott of Matrix Resource Consultants
of Perth, Australia who is a
Qualified Person as defined by NI 43-101.
- The estimate at 0.5g/t represents the base case or preferred
scenario for Gbongogo Main.
- Mineral Resources are reported inclusive of Mineral
Reserves.
- Mineral Resources that are not Mineral Reserves do not have
demonstrated economic viability.
- Figures are rounded to reflect the precision of the
estimates.
Combined Resources
Table 6 shows the combined resources based on the preferred cut
off grades for each deposit.
Table 6 – Combined Resources
Cut-off
Grade
|
Indicated
|
Inferred
|
Au g/t
|
Mt
|
Au g/t
|
Au Moz
|
Mt
|
Au g/t
|
Au Moz
|
Koné 0.20
g/t
|
229
|
0.59
|
4.34
|
25
|
0.5
|
0.40
|
Gbongogo Main 0.50
g/t
|
11
|
1.48
|
0.52
|
-
|
-
|
-
|
Total
|
240
|
0.63
|
4.87
|
25
|
0.5
|
0.40
|
Notes:
- Figures are rounded to reflect the precision of the estimates
and include rounding errors.
The Mineral Reserve estimate was prepared by Carci Mining
Consultants Ltd., dated as of January 15,
2024 and is presented below in Table 7.
Table 7 – Mineral Reserve
Estimate
Pit
|
Classification
|
Oxide
|
Transition
|
Fresh
|
Total
|
Mt
|
Au
g/t
|
Au
Moz
|
Mt
|
Au
g/t
|
Au
Moz
|
Mt
|
Au
g/t
|
Au
Moz
|
Mt
|
Au
g/t
|
Au
Moz
|
Koné South
|
Probable
|
9.6
|
0.58
|
0.18
|
7.0
|
0.60
|
0.13
|
145.3
|
0.67
|
3.18
|
161.9
|
0.67
|
3.49
|
Koné North
|
Probable
|
0.9
|
0.47
|
0.01
|
0.4
|
0.44
|
0.01
|
0.4
|
0.51
|
0.01
|
1.9
|
0.47
|
0.03
|
Gbongogo
Main
|
Probable
|
0.7
|
1.36
|
0.03
|
0.5
|
1.09
|
0.02
|
9.4
|
1.46
|
0.44
|
10.7
|
1.43
|
0.49
|
Total
|
Probable
|
11.3
|
0.63
|
0.23
|
7.9
|
0.63
|
0.16
|
155.1
|
0.73
|
3.62
|
174.3
|
0.72
|
4.01
|
Notes:
- The Mineral Reserves are classified according to the "CIM"
definitions.
- All Mineral Reserves were classified as Probable based on the
Indicated Mineral Resource.
- The Mineral Reserve cut off grade range from 0.19 g/t to
0.49g/t based on a $1,550/oz gold
price.
- The Mineral Reserve statement was prepared by Joeline
McGrath of Carci Mining Consultants Ltd, who is a Qualified Person
as defined by NI 43-101.
- The figures in this table are rounded to reflect the precision
of the estimates and may include rounding errors.
Updated Definitive Feasibility Study Overview
The UFS is based on three open-pit gold deposits feeding a
central gold processing facility (Figure 3). The Project will
produce an average of 223,000 ounces of gold per year over the life
of the mine. The initial life of the Project is 16.0 years. There
is upside potential through regional exploration and identification
of satellite pits similar to Gbongogo Main that could be mined and
trucked to a central processing facility.
Initial capital to fund construction and commissioning is
estimated at $712.1 million with
total capital estimated at $877.5
million over the LOM including closure costs. All-in
sustaining costs1 are estimated at $899 per ounce during the first three years of
the Project, well below the current industry average, and
$998 per ounce over the life of the
Project. Processing costs of $8.35/t
position the Project to be able to take advantage of mining
satellite pits identified through ongoing exploration.
The financial analysis performed from the results of this UFS
demonstrates the economic viability of the Koné Gold Project using
the base case gold price assumption of $1,850 per ounce. This results in an after-tax
net present value cashflow at a 5% discount rate (NPV5%)
of $1,089 million and an after-tax
IRR of 31.0% (both on a 100% basis) with a 2.6 year payback.
The Company is highly confident that there are additional
opportunities to further strengthen the Project through the
continued drilling and testing of satellite targets and optimizing
efficiencies on select capital costs.
The study was prepared for Montage by Lycopodium Minerals Pty
Ltd. Other discipline specific consultants were:
Mineral Resource
Estimate:
|
Matrix Resource
Consultants Pty Ltd.
|
Metallurgical
Testwork:
|
SGS
Lakefield
|
Metallurgical
oversight:
|
MPH Minerals
Consultancy Ltd.
|
Tailings and Water
Storage:
|
Knight Piésold Pty
Ltd.
|
Hydrogeology:
|
Australasian
Groundwater & Environmental Consultants
|
Environment:
|
Mineesia
Ltd.
|
Mineral Reserve
Estimate & Mining:
|
Carci Mining
Consultants Ltd
|
Key Differences in Project Scope Compared to
2022 DFS
As part of the recent feasibility review and process, several
areas of the Project were re-evaluated:
- The mine plan now incorporates the mining of the Koné
South and Gbongogo Main pits simultaneously at the start of
operations to maximise grade and economics during the payback
period.
- The power will now be supplied via a grid connection. This
change was made due to the lack of reliable LNG supplies in
the country and the high cost of importing LNG.
Figure 3: Koné Gold Project Site Layout
Mining
Mining operations will be carried out by a contractor on a unit
cost per tonne basis utilising a mining fleet comprised of 90t
rigid body haul trucks with suitably sized loading units at a rate
of 39Mtpa at Koné and 15Mtpa at Gbongogo Main, respectively. The
grade of the processed material in the first eight years is
enhanced by using an elevated cut off grade to the plant and
stockpiling the lower grade material for later processing.
Pit optimizations were completed based on slope angle
recommendations from SRK Consulting:
- for Koné South 48° for oxide, 68° for transition and 68° for
fresh rock; the overall slope angle inclusive of ramps and berms is
approximately 55°.
- for Gbongogo Main 32° for oxide, 40° for transition, and from
43° to 55° for fresh rock, which is reduced in areas of
unfavourable bedding to 35°; the overall slope angle inclusive of
ramps and berms is approximately 43°.
The optimizations were run using estimates of processing cost
and recovery data for each domain. Mining costs were broken into
base and incremental mining costs, derived from competitive bids
received from West African mining contractors.
A gold price of $1,550/oz was used
for the optimisation along with the following royalty assumptions:
i) a sliding scale royalty payable to the government of Côte
d'Ivoire, 4.0% at $1,550/oz Au; ii) a
2% property royalty; and iii) a 0.5% community development fund
royalty.
Pit designs (Figure 4 and Figure 5) were completed for the Koné
and Gbongogo Main deposits which will be exploited through three
pits, a smaller Northern pit which reaches a depth of 70m, a larger Southern pit which extends to a
depth of 495m, and the Gbongogo Main
pit which extends to a depth of 220m.
The overall strip ratio of the Project is 1.18:1; the Koné
South, Koné North and Gbongogo Main pits have strip ratios of 1:01,
1.19 and 3.77, respectively.
Figure 4 – UFS Koné South Pit Design
Figure 5 – UFS Gbongogo Main Pit Design
Figure 6 shows the mine schedule and Figure 7 shows the
processing schedule with the higher-grade feed material being
processed during the first eight years of the mine life. Stockpiled
lower grade material will be processed after the completion of
mining operations.
Figure 6 – Mining Schedule
Figure 7 – Processing Schedule
Figure 8 shows forecasted gold production and processing
recoveries. The Koné South pit will be used for the deposition of
tailings generated during the last 7 years of processing.
Figure 8 – Annual Gold Production and Recoveries
Metallurgy
A comprehensive testwork program was carried out by SGS
Lakefield on 68 comminution and 146 leach optimization and
variability samples representing a range of material and rock types
at the Koné and Gbongogo Main deposits.
The testwork program demonstrated that the mineralization is
amenable to direct tank carbon in pulp cyanide leaching with good
gold recoveries, low reagent consumptions and medium-low resistance
to grinding, providing favourable processing economics and a simple
flowsheet.
Table 8 shows the forecast gold recoveries and reagent
consumptions at the average LOM grades. Forecast gold recoveries
were estimated based on variable residue grades related to feed
grade, a solution loss of 0.005mg/l gold and carbon fines loss of
0.15%.
Cyanide consumption is low to very low and lime consumption is
low for the dominant fresh material (90%), but higher for the less
dominant transition (4%) and oxide (6%) zones.
Table 9 shows the comminution results. The fresh mineralization
is soft in terms of resistance to ball milling and crushing with
medium abrasivity. A full suite of High-Pressure Grinding Rolls
(HPGR) testing has been completed on a Koné Fresh ore sample and
Static Pressure Testing two Koné Footwall Fresh ore samples. The
(HPGR) investigation included: batch testing and a locked-cycle
test, the Bond ball mill grindability test on both the HPGR feed
and HPGR product and the SPT test. The HPGR test results have been
supplemented by Semi Autogenous Grinding (SAG) mill test data in
the design of the HPGR.
Table 8 – Metallurgical Testwork
Summary
Samples
Tested
|
Domain
|
LOM Plant
Feed
|
Average LOM
Grade
|
Forecast
Recovery
|
Cyanide
Consumption
|
Lime
Consumption
|
(Mt)
|
(Au g/t)
|
( %)
|
(kg/t)
|
(kg/t)
|
53
|
Koné South
Fresh
|
129.5
|
0.69
|
89.1
|
0.22
|
0.47
|
12
|
Koné North
Fresh
|
0.4
|
0.51
|
77.1
|
0.23
|
0.45
|
8
|
Gbongogo Main
Fresh
|
9.4
|
1.46
|
86.1
|
0.42
|
0.55
|
13
|
Koné South FW
Fresh
|
15.8
|
0.58
|
87.7
|
0.23
|
0.45
|
17
|
Koné South
Transition
|
7.0
|
0.60
|
91.3
|
0.18
|
0.99
|
5
|
Koné North
Transition
|
0.4
|
0.44
|
88.0
|
0.35
|
0.75
|
4
|
Gbongogo Main
Transition
|
0.5
|
1.09
|
91.2
|
0,21
|
1.06
|
21
|
Koné South
Oxide
|
9.6
|
0.59
|
93.9
|
0.18
|
2.50
|
9
|
Koné North
Oxide
|
0.9
|
0.47
|
93.2
|
0.13
|
2.79
|
4
|
Gbongogo Main
Oxide
|
0.7
|
1.36
|
92.8
|
0.29
|
2.6
|
130
|
All Domains
|
174.3
|
0.72
|
89.0
|
0.24
|
0.62
|
Table 9 – Comminution
Testwork for Fresh Rock
Test
|
Samples
Tested
|
Units
|
Average
|
SGS Lakefield
Classification
|
Bond Ball Mill Work
Index
|
68
|
kWh/t
|
10.7
|
Soft
|
SAG Milling
Index
|
68
|
A x b
|
59.6
|
Moderate
|
HPGR (HPi)
|
2
|
kWh/t
|
13.2
|
Medium
|
Crusher Work
Index
|
14
|
kWh/t
|
15.8
|
Medium
|
Abrasion
Index
|
18
|
g
|
0.4
|
Medium
|
Process Plant
The process plant design is based on a simple and robust
metallurgical flowsheet designed for optimal precious metal
recovery. The key design criteria for the plant are:
- Nominal throughput of 11.0 Mtpa with a grind size of 80%
passing (P80) 75 µm.
- Process plant availability of 91.3% supported by the selection
of standby equipment in critical areas.
- The treatment plant design incorporates the following unit
process operations:
- Primary and closed-circuit secondary crushing using a
gyratory crusher and two cone crushers to produce a crushed product
size P80 of approximately 31mm.
- A crushed feed stockpile with a nominal live capacity of
22,000 wet tonnes, providing buffer
storage of crushed ore with continuous reclaim feeders for the
HPGR-ball mill comminution circuit.
- Two parallel HPGRs in closed circuit with wet sizing
screens, with undersize slurry reporting to the milling circuit via
the cyclone feed hopper. Two parallel trains of ball mills in
closed circuit with hydrocyclones to produce a grind size of
P8075 µm.
- Pre-leach thickening to increase the slurry density feeding
the leach and carbon in pulp ("CIP") circuit to minimise tankage
and reduce overall reagent consumption.
- Leach circuit incorporating 14 leach tanks, arranged in two
parallel trains of 7 each in series, to provide 36 hours leach
residence time, and equipped with external oxygen contactors.
- A Kemix Pumpcell CIP circuit consisting of eight tanks for
recovery of gold onto carbon, to minimize carbon inventory, gold in
circuit and operating costs. The CIP and elution circuit design is
based on daily carbon harvesting.
- 20 tonne elution circuit, electrowinning and gold smelting
to recover gold from the loaded carbon to produce a gold/silver
doré.
- Tailings thickening to recover and recycle process water
from the CIP tailings.
- Tailings pumping to the Tailings Storage Facility
("TSF").
Project Infrastructure
Haul Road from Gbongogo Main to Koné
The Gbongogo haul road is 38.1 km in length and transverses
a sparsely populated area between the two sites and has been
designed to avoid villages, defined forest areas and minimise
interactions with existing public roads. The road incorporates a
pedestrian corridor leading to underpasses along the alignment.
Access to the road will be restricted by construction of safety
berms along the entire length of the road. Traffic control will be
provided at all intersections with the public roads.
The haul road alignment has been designed to limit the number of
water courses impacted by the road with culverts provided at all
main water intersections and a bridge to be constructed at the
crossing of the Marahoué River.
Water
Water will be sourced from the nearby Marahoué river, from
pit dewatering and a supplementary borefield.
The river abstraction facility will be constructed adjacent to
the Marahoué River bridge approximately 26 km north of the water
storage facility ("WSF"). The extraction facility will comprise a
sump to allow for harvesting of water by a pump mounted on a bridge
support column. Pumping will only take place in the wet season,
normally from June to December, provided minimum flows are met.
Hydrological assessment of the river catchment indicates that the
river will have sufficient excess flow during this period and will
not affect downstream users.
Harvested river water and pit de-watering will be pumped to an
off-stream WSF. Surface runoff from the Koné mining area, ROM pad
and stockpiles will gravity flow to the WSF. The WSF will have a
capacity of approximately 7.2 million m3 and will enable
accumulation of water during the wet season and a gradual drawdown
in the dry season. In addition, water will be recycled from the
tailings storage facility to the process water pond. Surface runoff
from the Gbongogo mining area, will be collected in two sediment
ponds and overflow to the Marahoué river following sediment
settling.
Tailings
The TSF will comprise of a single cell confined by a cross
valley embankment which will be raised annually until the mining in
Koné South pit is completed early in year 9.
The TSF basin will be lined with HDPE within the normal
operating pond areas and a compacted soil liner elsewhere to reduce
seepage. In addition, a system of underdrainage, embankment
drainage and sub-liner drainage will be constructed to reduce
seepage and aid consolidation of the tailings. Tailings will be
deposited subaerially with the supernatant pond located away from
the embankment. Water will be recovered from the supernatant pond
by a suction pump with floating intake located in a channel
excavated adjacent to an access causeway.
Following the completion of the mining early in year 9, tailings
will be deposited into the Koné South pit via four spigots located
around the perimeter of the pit. Water will be extracted from the
decant pond using floating intake lines to position the pumps above
the pond elevation. The pond volume will be at its highest at the
first year as the TSF pond will be pumped to the pit to let the TSF
commence the closure process.
The TSF will be closed and rehabilitated after deposition is
transferred to the pit. Closure spillways will be formed to prevent
water accumulating on the facilities and a waste rock cover will be
placed over the tailings prior to topsoiling and revegetation.
Power
The UFS evaluated hybrid power supply options from
proposals received from West African power providers. However,
local supplies of LNG cannot be guaranteed and so power will now be
supplied from the National Grid via a new 225kV transmission
line.
The Koné Gold Project process plant is estimated to have a
maximum demand of 44.8 MW and an average annual demand of 37 MW,
with an expected energy consumption of 303GWhr/yr.
The capital cost estimate for grid connection is estimated to be
$26M (before contingency). The
operating cost is estimated at $0.1149/kWhr.
Environmental
Under the Mining Code, all applicants for an exploitation
licence must submit an Environmental and Social Impact Assessment
("ESIA") to the Agence Nationale de L'Environment ("ANDE"), the
authority in charge of supervising, validating and controlling
environmental impact studies. Montage submitted the ESIA in
December 2023. There are currently no
objections to the development of the Project.
Mining of the Koné North Pit will affect less than 10% of the
Toudian Forest Reserve and discussions with the Ministry of Water
and Forests have commenced to obtain authorization. The impact of
the project on the forest reserve has been assessed during the
ESIA. The UFS includes provision for the backfilling and
re-habilitation of all but 14ha during operations. This will be
complemented by a forest management plan in collaboration with
relevant government agencies to ensure the upgrade and protection
of the forest reserve.
Permitting
The development of the Project will be subject to the following
permitting process:
- Approval of the ESIA by ANDE.
- Receipt of environmental approval of its design and
environmental management program.
- Application for and receipt of a Mining Permit (valid for 10
years and then renewable).
- Negotiation of a Mining Convention.
ANDE hosted a public enquiry in late December 2023 and expect environmental validation
of the project to be completed in Q1 2024. In parallel with this
process, Montage is preparing the Mining Permit application and
initiating discussions in respect of the Mining Convention, all
with assistance from local advisors. Based on current expectations,
Montage believes it will receive final permits and approvals in Q3
of 2024.
Capital Costs Summary
Capital cost estimates are summarized in Table 10 and Table 11.
The initial project capital cost is estimated at $712.1M, including a contingency allowance of
$65.3M.
Table 10 – Pre-Production Capital
Cost Estimate Summary (Q4'23, +15/-10%)
Main Area
|
Koné
|
Gbongogo
|
Total
|
($M)
|
($M)
|
($M)
|
Resettlement
|
$7.4
|
$2.0
|
$9.4
|
Camp
|
$6.4
|
-
|
$6.4
|
Pre-Production
Mining
|
$45.2
|
$11.9
|
$57.1
|
Gbongogo Haul
Road
|
-
|
$27.4
|
$27.4
|
Gbongogo Surface
Water
|
-
|
$3.3
|
$3.3
|
Grid
Connection
|
$26.1
|
-
|
$26.1
|
Process
Plant
|
$338.4
|
-
|
$338.4
|
Infrastructure
|
$26.5
|
-
|
$26.5
|
Tailings and Water
Storage
|
$55.0
|
-
|
$55.0
|
EPCM
|
$46.4
|
-
|
$46.4
|
Owners Costs
|
$49.3
|
$1.4
|
$50.7
|
Subtotal
|
$600.8
|
$46.0
|
$646.8
|
Contingency
|
$61.3
|
$4.0
|
$65.3
|
Grand Total
|
$662.1
|
$50.0
|
$712.1
|
Compared to the 2022 DFS and excluding capital costs associated
with Gbongogo Main, the Koné pre-production capital cost has
increased by $118.3M (including
contingency). The significant increases are in the following
areas:
|
$28M
|
|
$24M
|
|
$19M
|
|
$7M
|
|
$7M
|
|
$4M
|
|
$3M
|
|
$24M
|
The Gbongogo Main infrastructure costs add a further
$50.0M.
The duration of the detailed design and construction phase of
the Project has been estimated to be 31 months commencing with the
construction of the Marahoué bridge, road and pump station and the
WSF. The plant is estimated to take 27 months to construct. Mining
will commence 12 months prior to start of processing.
The total LOM capital cost is estimated at $877.4M, including sustaining capital and closure
costs of $165.3M, as shown in Table
11.
Table 11 – Sustaining Capital Cost
Estimate Summary (Q4'23, +15/-10%)
Main Area
|
Value ($M)
|
Camp
|
$4.4
|
Tailings Storage
Facility
|
$65.0
|
Process
Plant
|
$34.4
|
Closure
|
$61.6
|
Grand Total
|
$165.3
|
Sustaining capital estimates have decreased by $126.4M compared to the 2022 DFS, primarily due
to the change in power supply from LNG to a grid connection.
Taken as a whole, these changes have resulted in a $65/oz increase in LOM AISC¹ versus the 2022
DFS.
Operating Costs Summary
Contract open pit mining costs were derived from a tender
process involving several West African mining contractors who were
provided a detailed mining plan for the Koné and Gbongogo Main
deposits. The average open pit operating cost ($/t mined) is shown
in Table 12. A diesel price of $1.00/l was used.
Table 12 – Mining
Costs (Q4'23)
|
Ore
|
Waste
|
Total
|
($/t)
|
($/t)
|
($/t)
|
Average
|
$3.49
|
$2.86
|
$3.22
|
Process operating costs have been developed for each major
domain. Operating costs were developed using the plant parameters
specified in the process design criteria. Table 13 presents the
operating cost summary by material type. In addition to the
processing costs, rehandle costs equate to $0.59/t processed when averaged over the LOM.
Table 13 – Process Operating Cost per
Material Type (Q4'23, +15/-15%)
|
Annual Fixed
Processing Costs
|
Variable Processing
Costs ($/t)
|
Total
|
($M/y)
|
Oxide
|
Transition
|
Fresh
|
Fixed + Variable
($/t)
|
Average
|
$19.3
|
$5.42
|
$5.65
|
$6.71
|
$8.35
|
Total fixed mine level general and administration ("G&A")
costs are estimated at $12.1M
annually, which are in addition to the $19.3M in annual fixed processing costs shown in
Table 13.
Table 14 shows the LOM total cash cost¹ and all-in sustaining
costs¹ calculated both on a $/payable ounce and $/tonne processed
basis. Pre-production capitalized mining costs are excluded from
these calculations.
Table 14 – Cash Cost and Unit Cost
Summary (using $1,850/oz gold
price)
Description
|
LOM Total
|
LOM Avg.
|
LOM Avg.
|
($M)
|
($/payable
oz)
|
($/t
processed)
|
Operating
Cost
|
|
|
|
Mining
|
$1,164
|
$326
|
$6.68
|
Road Haulage
|
$68
|
$19
|
$0.39
|
Processing
|
$1,456
|
$408
|
$8.35
|
Rehandle
|
$103
|
$29
|
$0.59
|
G&A
|
$171
|
$48
|
$0.98
|
Royalties
|
$495
|
$139
|
$2.84
|
Total Cash
Cost¹
|
$3,457
|
$969
|
$19.83
|
Sustaining
Capital
|
$104
|
$29
|
$0.60
|
All-in Sustaining
Costs¹
|
$3,561
|
$998
|
$20.42
|
Financial Analysis
An economic analysis has been carried out for the Project using
a cash flow model. The model has been constructed using annual cash
flows taking into account annual processed tonnages and grades
for the CIP feed, process recoveries, metal prices, operating costs
and refining charges, royalties and capital expenditures (both
initial and sustaining). A payable factor of 99.90% has been
assumed for purposes of gold sales.
The financial analysis used a base price of $1,850 per ounce. The financial assessment of the
Project is carried out on a "100% equity" basis and the debt and
equity sources of capital funds are ignored. No provision has been
made for the effects of inflation. Côte d'Ivoire tax regulations
are applied to assess the tax liabilities (corporate tax rate of
25%), duties and other levies. Discounting and IRR calculations has
been applied from the first year of operations using a 5% discount
rate and pre-production capital is deducted on an undiscounted
basis. A detailed annual summary cash flow model is provided in
Appendix 1 of this release.
Sensitivity Analysis
Table 15 shows the Project sensitivity of the NPV, IRR, Cash
Cost and AISC with gold price.
Table 15 – Project Sensitivity
|
Gold Price
($/oz)
|
Metric
|
Units
|
$1,650
|
$1,750
|
$1,850*
|
$1,950
|
$2,050
|
NPV5%
|
$M
|
721
|
905
|
1,089
|
1,273
|
1,456
|
IRR
|
%
|
22.6 %
|
26.9 %
|
31.0 %
|
35.2 %
|
39.3 %
|
Total Cash
Cost1
|
$/payable oz
|
954
|
962
|
969
|
977
|
984
|
AISC1
|
$/payable oz
|
983
|
991
|
998
|
1,006
|
1,013
|
Payback
|
years
|
3.2
|
2.8
|
2.6
|
2.3
|
2.2
|
* Three-year trailing average
Opportunities
Potential opportunities to improve the economics of
the Koné Gold Project have been identified:
- The wider Koné Gold Project of 2,259 sq.km hosts over 100km
strike extent of regional scale mineralised structures which are
underexplored. These areas have the potential through further
exploration to add satellite deposits to the current mine
life.
- Continue discussions with contractors to look to achieve
capital cost reductions.
- Continue to engage with stakeholders to maintain ease of
Project implementation.
Koné Gold UFS Live Webcast
A conference call and webcast will be held on Friday, January 19, 2024, starting at
11:00am Eastern Time to discuss the
Updated Feasibility Study on the Koné Gold Project. To
participate in the conference call, use the following dial-in
numbers and conference ID, or join the webcast using the link
below:
International: +1 (416) 764-8659
North American Toll-Free: +1 (888) 664-6392
Conference ID: 39004138
Webcast URL: https://app.webinar.net/91Av7DERlpD
Notes:
- Cash costs per payable ounce of gold and per tonne
processed, AISC per payable ounce of gold sold and per tonne
processed are non-GAAP financial measures. Please see "Cautionary
Note Regarding Non-GAAP Measures". AISC per payable ounce includes
all mining costs, processing costs, mine level G&A, royalties,
and sustaining capital and is adjusted to reflect movements in
stockpiles. Cash costs per payable ounce includes all mining costs,
processing costs, mine level G&A, and royalties and is adjusted
to reflect movements in stockpiles.
ABOUT MONTAGE GOLD CORP.
Montage is a Canadian-based precious metals exploration and
development company focused on opportunities in Côte d'Ivoire. The
Company's flagship property is the Koné Gold Project, located in
northwest Côte d'Ivoire, which currently hosts a Probable Mineral
Reserve of 174.3 Mt grading 0.72g/t for 4.01M ounces of gold. The Company released the
results of a UFS on the Koné Gold Project on January 16, 2024, outlining a 16-year gold
project producing 3.57M ounces of
gold at AISC of $998 per ounce over
the life of mine, with average annual production of 223koz, and
peak annual production of 378koz. Montage has a management team and
Board with significant experience in discovering and developing
gold deposits in Africa.
The Koné and Gbongogo Main Mineral Resource Estimates were
carried out by Mr. Jonathon Abbott
of Matrix Resource Consultants of Perth, Western
Australia, who is considered to be independent of Montage
Gold. Mr. Abbott is a member in good standing of the Australian
Institute of Geoscientists and has sufficient experience which is
relevant to the commodity, style of mineralization under
consideration and activity which he is undertaking to qualify as a
Qualified Person under NI 43–101.
The Mineral Reserve Estimate was carried out by Ms. Joeline McGrath of Carci Mining Consultants
Ltd., who is considered to be independent of Montage Gold. Ms.
McGrath is a member in good standing of the Australian Institute of
Mining and Metallurgy and has sufficient experience which is
relevant to the work which she is undertaking to qualify as a
Qualified Person under NI 43–101.
QUALIFIED PERSONS STATEMENT
The technical contents of this release have been approved by the
following Qualified Persons pursuant to National Instrument
43-101:
- Sandy Hunter: Lycopodium
Minerals Pty Ltd.
- Jonathon Abbott: Consulting
Geologist, Matrix Resource Consultants
- Mike Hallewell: Consultant, MPH
Minerals Consultancy Ltd.
- Pieter Labuschagne: Consultant,
Australasian Groundwater & Environmental Consultants
- Carl Nicholas: Consultant,
Mineesia Ltd.
- Joeline McGrath: Consultant,
Carci Mining Consultants Ltd
- Tim Rowles: Consultant, Knight
Piésold Pty Ltd.
TECHNICAL DISCLOSURE
Data verification programs have included review of QA/QC data,
re-sampling and sample analysis programs, and database
verification. Validation checks were performed on data, and
comprise checks on surveys, collar co-ordinates and assay data.
Sufficient verification checks were undertaken on the database to
provide confidence that the database is virtually error free and
appropriate to support Mineral Resource and Reserve estimation.
A technical report for the Koné Gold Project will be prepared in
accordance with National Instrument 43-101 and will be filed on
SEDAR at www.sedar.com and on the Company's website at
www.montagegoldcorp.com within 45 days of this press release.
Readers are encouraged to read the technical report in its
entirety, including all qualifications, assumptions and exclusions
that relate to the details summarized in this press release. The
technical report is intended to be read as a whole, and sections
should not be read or relied upon out of context.
Neither the TSX Venture Exchange nor its Regulation Services
Provider (as that term is defined in the policies of the TSX
Venture Exchange) accepts responsibility for the adequacy or
accuracy of this release.
TECHNICAL DISCLOSURE – SAMPLING AND ASSAYING
The technical contents of this press release relating to
exploration results have been approved by Hugh Stuart, BSc, MSc, a Qualified Person
pursuant to NI 43-101. Mr. Stuart is the President of the Company,
a Chartered Geologist and a Fellow of the Geological Society of
London.
Samples used for the results described have been prepared and
analysed by fire assay using a 50-gram charge at the Bureau Veritas
facility in Abidjan, Côte d'Ivoire
or the SGS facility in Yamoussoukro, Côte d'Ivoire. Shallow RC
reconnaissance results are based on 3 metre composite samples.
Field duplicate samples are taken, and blanks and standards are
added to every batch submitted. QA/QC has been approved in line
with industry standards and interpretations reviewed the Qualified
Person.
FORWARD LOOKING STATEMENTS
This press release contains certain forward-looking information
and forward-looking statements within the meaning of Canadian
securities legislation (collectively, "Forward-looking
Statements"). All statements, other than statements of historical
fact, constitute Forward-looking Statements. Words such as "will",
"intends", "proposed" and "expects" or similar expressions are
intended to identify Forward-looking Statements. Forward looking
Statements in this press release include statements related to the
Company's mineral reserve and resource estimates; the timing and
amount of future production from the Koné Gold Project;
expectations with respect to the IRR, NPV, payback and costs of the
Koné Gold Project; anticipated mining and processing methods of the
Koné Gold Project; anticipated mine life of the Koné Gold Project;
expected recoveries and grades of the Koné Gold Project; and timing
for permits and concessions. Forward-looking Statements involve
various risks and uncertainties and are based on certain factors
and assumptions. There can be no assurance that such statements
will prove to be accurate, and actual results and future events
could differ materially from those anticipated in such statements.
Important factors that could cause actual results to differ
materially from the Company's expectations include uncertainties
inherent in the preparation of mineral reserve and resource
estimates and definitive feasibility studies such as the MRE and
the UFS, including but not limited to, assumptions underlying the
production estimates not being realized, incorrect cost
assumptions, unexpected variations in quantity of mineralized
material, grade or recovery rates, unexpected changes to
geotechnical or hydrogeological considerations, unexpected failures
of plant, equipment or processes, unexpected changes to
availability of power or the power rates, failure to maintain
permits and licenses, higher than expected interest or tax rates,
adverse changes in project parameters, unanticipated delays and
costs of consulting and accommodating rights of local communities,
environmental risks inherent in the Côte d'Ivoire, title risks,
including failure to renew concessions, unanticipated commodity
price and exchange rate fluctuations, risks relating to COVID-19,
delays in or failure to receive access agreements or amended
permits, the impact and progression of the COVID-19 pandemic and
other risk factors set forth in the Company's final prospectus
under the heading "Risk Factors". The Company undertakes no
obligation to update or revise any Forward-looking Statements,
whether as a result of new information, future events or otherwise,
except as may be required by law. New factors emerge from time to
time, and it is not possible for Montage to predict all of them, or
assess the impact of each such factor or the extent to which any
factor, or combination of factors, may cause results to differ
materially from those contained in any Forward-looking Statement.
Any Forward-looking Statements contained in this press release are
expressly qualified in their entirety by this cautionary
statement.
NON-GAAP MEASURES
This press release includes certain terms or performance
measures commonly used in the mining industry that are not defined
under International Financial Reporting Standards ("IFRS"),
including cash costs and AISC per payable ounce of gold sold and
per tonne processed. Non-GAAP measures do not have any standardized
meaning prescribed under IFRS and, therefore, they may not be
comparable to similar measures employed by other companies. The
Company discloses "cash costs" and "all-in sustaining costs"
because it understands that certain investors use this information
to determine the Company's ability to generate earnings and cash
flows for use in investing and other activities. The Company
believes that conventional measures of performance prepared in
accordance with IFRS, do not fully illustrate the ability of mines
to generate cash flows. The measures, as determined under IFRS, are
not necessarily indicative of operating profit or cash flows from
operating activities. The measures cash costs and all-in sustaining
costs are considered to be key indicators of a project's ability to
generate operating earnings and cash flows. Non-GAAP financial
measures should not be considered in isolation as a substitute for
measures of performance prepared in accordance with IFRS and are
not necessarily indicative of operating costs, operating profit or
cash flows presented under IFRS. Readers should also refer to our
management's discussion and analysis, available under our corporate
profile at www.sedar.com for a more detailed discussion of how we
calculate such measures.
Appendix 1 – Summary Production and
Financial Model
Appendix 2 – Listing of Intercept
Detail for Diouma North
Hole ID
|
Drill Type
|
Collar Location
(UTM Zone 29N)
|
Orientation
|
Depth
|
From
|
To
|
Length
|
Uncut
Au
|
Grade Cut to
20g/t
|
mE
|
mN
|
mRL
|
Dip
|
Azim
|
|
(m)
|
(m)
|
(m)
|
(g/t)
|
(g/t)
|
GBRC073
|
RC
|
769,712
|
991,540
|
339
|
-55
|
100
|
52
|
7
|
21
|
14
|
1.73
|
1.73
|
GBRC074
|
RC
|
769,516
|
991,429
|
343
|
-55
|
100
|
108
|
No significant
intercept
|
GBRC075
|
RC
|
769,574
|
991,419
|
343
|
-55
|
100
|
114
|
No significant
intercept
|
GBRC076
|
RC
|
794,703
|
1,017,177
|
399
|
-55
|
125
|
126
|
96
|
106
|
10
|
0.79
|
0.79
|
121
|
124
|
3
|
3.26
|
3.26
|
GBRC082
|
RC
|
769,615
|
991,882
|
338
|
-55
|
90
|
114
|
14
|
27
|
13
|
0.89
|
0.89
|
GBRC087
|
RC
|
769,578
|
991,440
|
344
|
-55
|
100
|
162
|
3
|
8
|
5
|
0.89
|
0.89
|
GBRC090
|
RC
|
769,657
|
991,607
|
339
|
-55
|
100
|
80
|
50
|
57
|
7
|
0.74
|
0.74
|
GBRC091
|
RC
|
769,598
|
991,618
|
341
|
-55
|
100
|
162
|
81
|
89
|
8
|
1.34
|
1.34
|
100
|
106
|
6
|
0.93
|
0.93
|
GBRC092
|
RC
|
769,624
|
991,653
|
340
|
-55
|
100
|
150
|
45
|
48
|
3
|
1.08
|
1.08
|
75
|
78
|
3
|
1.70
|
1.70
|
GBRC093
|
RC
|
769,670
|
991,648
|
338
|
-55
|
100
|
100
|
40
|
46
|
6
|
2.28
|
2.28
|
GBRC094
|
RC
|
769,678
|
991,694
|
339
|
-55
|
100
|
110
|
14
|
20
|
6
|
0.79
|
0.79
|
GBRC095
|
RC
|
769,633
|
991,700
|
340
|
-55
|
100
|
150
|
No significant
intercept
|
GBRC096
|
RC
|
769,573
|
991,677
|
341
|
-55
|
100
|
100
|
No significant
intercept
|
GBRC099
|
RC
|
769,544
|
991,466
|
344
|
-55
|
100
|
162
|
No significant
intercept
|
GBRC100
|
RC
|
769,610
|
991,410
|
344
|
-55
|
100
|
120
|
8
|
14
|
6
|
1.59
|
1.59
|
GBDDH062
|
Core
|
769,642
|
991,552
|
343
|
-55
|
100
|
104.7
|
58.00
|
72.00
|
14.00
|
2.16
|
2.16
|
77.00
|
82.00
|
5.00
|
0.85
|
0.85
|
85.00
|
88.10
|
3.10
|
1.99
|
1.99
|
GBDDH063
|
Core
|
769,630
|
991,576
|
342
|
-55
|
100
|
143.7
|
88.00
|
91.50
|
3.50
|
3.23
|
3.23
|
GBDDH064
|
Core
|
769,690
|
991,578
|
341
|
-55
|
200
|
176.7
|
43.00
|
46.00
|
3.00
|
3.84
|
3.84
|
78.85
|
96.30
|
17.45
|
2.74
|
2.16
|
127.00
|
138.00
|
11.00
|
2.21
|
2.21
|
View original content to download
multimedia:https://www.prnewswire.com/news-releases/montage-announces-updated-feasibility-study-at-kone-gold-project-302035508.html
SOURCE Montage Gold Corp