February 20, 2024
NEWS RELEASE
LUCARA ANNOUNCES YEAR END 2023
RESULTS; CONTINUED DEVELOPMENT OF THE UNDERGROUND
PROJECT
VANCOUVER, February 20, 2024 /CNW/
(LUC - TSX, LUC - BSE, LUC - Nasdaq Stockholm)
Lucara Diamond Corp. ("Lucara" or
the "Company") today reports its results for the year and quarter
ended December 31, 2023. All amounts are in U.S. dollars unless
otherwise noted.
FISCAL 2023 HIGHLIGHTS
· The
recovery of a 1,080 carat Type IIA white gem quality diamond in
August 2023, followed by a recovery of a 692 carat Type IIA diamond
later in the month. The fourth +1000 carat stone recovered from the
Karowe Mine.
· The
Karowe Mine recorded record plant throughput of 2.8 million tonnes
milled for the year.
· In
January 2024, the successful execution of an amended project
financing debt package of $220 million to amend the repayment
profile in line with the rebase schedule released in July 2023 for
the Karowe Underground Project ("UGP").
· On
February 18, 2024, the Company announced the signing of a new
definitive sales agreement ("NDSA") with HB Trading BV ("HB") in
respect of all qualifying diamonds produced in excess of 10.8
carats in size from the Karowe Mine.
· Total
revenue of $177.4 million for 2023, in line with revised
guidance.
· Cash
flow generated from operating activities of $63.4 million for
2023.
· 2023
operating cash cost of $28.75 per tonne of ore
processed(1).
· Investment of $101.3 million in the Karowe UGP in 2023.
Significant sinking progress was made in both the production and
the ventilation shafts during the second half of 2023.
William Lamb, President & CEO
commented: "2023 was a challenging year for Lucara. Although mining
activities in the open pit continued to show ongoing sustainable
improvements, including record production through the mill, the
development on the UGP experienced delays
in the early part of the year. Positive progress was made in the
sinking of both the production and the ventilation shafts resulting
in both shafts starting lateral development at the 670 level at the
end of the year. The Company has dedicated
significant effort and resources to focus on the UGP as this
project represents a very exciting and valuable future for
Lucara.
The diamond market in general
remains a volatile environment with market challenges coming from
multiple areas. Lucara remains well positioned to meet these market
challenges head on due to its unique high value production mix and
its ability to provide provenance for its diamonds through its
well-defined sales channels. Our sales strategy which focuses on gaining access to the upstream value chain
from polished diamonds is well aligned to the strategies of the
Government of the Republic of Botswana. The Company aims to
continue working toward long-term sustainable business practices to
provide value for all our stakeholders."
REVIEW FOR THE YEAR ENDED DECEMBER
31, 2023
· Operational highlights from the Karowe Mine for 2023
included:
o Ore and
waste mined of 2.7 million tonnes ("Mt") (2022: 3.3Mt) and 3.1
million tonnes (2022: 1.5Mt), respectively.
o 2.8
million tonnes (2022: 2.8Mt) of ore processed.
o A total of
395,134 carats recovered, including 18,509 carats from the
processing of historic recovery tailings, (2022: 335,769 carats) at
a recovered grade of 13.2 carats per hundred tonnes ("cpht") of
direct milled ore (2022: 12.1 cpht).
§ A total of
602 Specials (stones larger than 10.8 carats in size) were
recovered, with 22 diamonds greater than 100 carats including five
diamonds greater than 300 carats.
§ Recovered
Specials equated to 5.3% of the total recovered carats from ore
processed during 2023 (2022 - 7.2%).
o The Karowe
Mine has operated continuously for over three years without a lost
time injury.
· Financial highlights for 2023
included:
o Revenues
of $177.4 million (2022: $212.9 million) achieved despite a weaker
rough diamond market. Fourth quarter pricing stabilized in smaller
goods and increases of 5% were observed compared to the third
quarter of 2023, albeit approximately 19% below prices observed in
the fourth quarter of 2022. Revenue reflects the weighting of
Lucara's revenue towards larger goods where pricing was observed to
be more stable. The performance further reflects the increased
volume of material processed from the North and Centre lobes in the
first half of the year. During 2023, 26% of the carats processed
were recovered from the Centre Lobe, 3% from the North Lobe and 71%
were recovered from South Lobe ore (2022: 100% South Lobe ore). In
comparison to the revenue earned in 2022, current year revenues
reflected a more diverse product mix with a return to Centre and
North Lobe processing during the year.
o Operating
margins of 56% were achieved (2022: 63%). A strong operating margin
continues to be achieved through cost reduction initiatives
assisted by a strong U.S. dollar.
o Adjusted
EBITDA(1) was $54.4 million (2022: $86.7 million), with
the decrease attributable to the change in revenue.
o Net loss
was $20.2 million (2022: net income of $40.4 million), resulting in
a loss per share of $0.04 (2022: earnings of $0.09). The change to
a net loss is due to the decrease in revenue, an impairment of
intangible assets, and a significant non-cash deferred tax expense
as the investment in the underground expansion project
continues.
o The
Company identified an impairment indicator for the Company's Clara
sales platform and completed an impairment test based on the fair
value less cost of disposal expected to be
derived from the platform. An impairment was recognized on the
intangible asset by $11.2 million in Q4 2023.
o Cash flow
from operating activities was $63.4 million (2022: $96.2
million).
· During
2023, the Company invested $101.3 million into the Karowe UGP,
including capitalized borrowing costs:
o Shaft
sinking, lateral development and grouting programs were the focus
in both the ventilation and production shafts in Q4 2023. At the
end of 2023, the production and ventilation shafts were both at 348
metres below collar or 666 metres above sea level ("masl") and the
process of establishing the first shaft stations and lateral
connection between the two shafts (670 level) had
commenced.
o
During Q4 2023, the ventilation shaft sank 76
metres, the 718 slinging cubby was completed, the 670-level station
catwalk was established and the lateral station development
commenced. Total lateral development in Q4 2023 was 97 metres.
During the quarter, development equipment, including a Kubota, a
Sandvik DD321 boom jumbo drill and a Caterpillar R1300G 7-tonne
load, haul, dump unit were mobilized at the 670-level for lateral
development mining. Sinking and lateral development was in the
Thlabala mudstones in dry conditions.
o Production
shaft activities included sinking a total of 114 metres and
establishing the 670-level station catwalk and initiating lateral
development. A total of 30 metres of lateral development was
completed.
o Commissioning of the temporary bulk air coolers at each shaft
was completed and construction of the permanent bulk air coolers at
the production shaft continued.
o Detailed
engineering and fabrication of the permanent men and materials
winder commenced during the quarter, representing the last major
component for the permanent winders.
· Cash
position and liquidity at December 31, 2023:
o Cash and
cash equivalents of $13.3 million.
o Working
capital deficit (current assets less current liabilities) of $16.6
million.
o Cost
overrun facility ("COF") of $18.6 million.
o $90.0
million drawn on the $170.0 million Project Loan ("Project Loan")
for the Karowe UGP.
o $35.0
million drawn on the $50.0 million working capital facility
("WCF").
· On
January 9, 2024, the Company announced that it had signed amended
documentation in relation to the senior secured project financing
debt package of $220.0 million (the "Facilities") executed in July
2021 (the "Rebase Amendments"). The project facility portion had
been increased from $170.0 million to $190.0 million, while the
working capital facility had been decreased from $50.0 million to
$30.0 million. While the total quantum of the Facilities has not
changed, the repayment profile has been extended in line with the
rebase schedule released on July 17, 2023, and the maturity of the
WCF has been extended to June 30, 2031.
· During
2023, the Company announced the appointment of William Lamb as
Chief Executive Officer, effective August 17, 2023, and Glenn
Kondo, as Chief Financial Officer, effective January 1, 2024. Eira
Thomas and Zara Boldt departed during 2023.
DIAMOND MARKET
The long-term outlook for natural
diamond prices remains positive, anchored on improving fundamentals
around supply and demand as many of the world's largest mines reach
their end of life. Currently, slower than anticipated economic
growth in China and a voluntary import ban on rough diamonds into
India in Q4 2023 dampened the recovery of rough diamond prices
towards the end of 2023. Changes in global economic conditions,
consumer demand, geopolitical events, and industry-specific
dynamics resulted in a challenging market in 2023 with reduced
demand and downward pressure on both polished and rough diamond
pricing, especially in the smaller size classes. Restricted supply
by the largest producers towards the end of 2023, together with the
Group of Seven discussions surrounding sanctions on rough diamonds
from Russia, resulted in low levels of price recovery at the end of
2023.
Sales of lab-grown diamonds
increased steadily through 2023 with many smaller retail outlets
increasingly adopting these diamonds as a product. Lab-grown stones
have established themselves in the marketplace and is expected to
continue to take up increasing market share in the smaller to
medium sized goods over time. The longer-term market fundamentals
for natural diamonds remain positive, pointing to continued price
growth as demand is expected to outstrip future supply, which is
now declining globally.
2024 OUTLOOK
This section of the press release
provides management's production and cost estimates for 2024. These
are "forward-looking statements" and subject to the cautionary note
regarding the risks associated with forward-looking statements.
Diamond revenue guidance does not include revenue related to the
sale of exceptional stones (an individual rough diamond which sells
for more than $10 million), or the Sethunya. No changes have been
made to the Company's Guidance which was released in November
2023.
Karowe Diamond Mine
|
2024
|
In
millions of U.S. dollars unless otherwise noted
|
Full
Year
|
Diamond revenue
(millions)
|
$220 to $250
|
Diamond sales (thousands of
carats)
|
345 to 375
|
Diamonds recovered (thousands of
carats)
|
345 to 375
|
Ore tonnes mined
(millions)
|
2.8 to 3.2
|
Waste tonnes mined
(millions)
|
0.8 to 1.4
|
Ore tonnes processed
(millions)
|
2.6 to 2.9
|
Total operating cash
costs(1) including waste mined (per tonne
processed)
|
$28.50 to $33.50
|
Underground Project
|
Up to $100 million
|
Sustaining capital
|
Up to $10 million
|
Average exchange rate - Botswana
Pula per United States Dollar
|
12.5
|
(1) Operating cash costs are a
non-IFRS measure. See "Non-IFRS Financial Performance
Measures".
DIAMOND SALES
Karowe diamonds are sold through
three separate and distinct sales channels, namely through the HB
sales agreement, on the Clara digital sales platform and through
quarterly tenders.
SALES FOR +10.8 CARAT DIAMOND
PRODUCTION FROM KAROWE
Karowe's large, high value diamonds
have historically accounted for approximately 60% to 70% of
Lucara's annual revenues. In September 2023, Lucara
terminated the definitive sales agreement executed with HB in
November 2022 (for all +10.8 carat diamonds recovered from Karowe)
due to HB's material breach of its financial commitments. The rough
diamonds delivered to HB prior to the termination of the agreement
continued to be manufactured and sold as polished diamonds. The
Company retains a contractual right to receive "top-up" payments
from polished diamond sales for goods delivered prior to the
termination of the agreement. The Company continued to sell its
+10.8 carat production through this established sales channels
while it continued to work with the management of HB on options for
a new Diamond Sales Agreement which is subject to pre-approval from
the Government of the Republic of Botswana.
For the three months ended December
31, 2023, the Company recorded revenue of $17.4 million from the HB
arrangements (inclusive of top-up payments of $6.8 million), as
compared to revenue of $24.1 million (inclusive of top-up payments
of $3.6 million) for the three months ended December 31, 2022. The
fourth quarter saw a reduction in the goods delivered to HB as a
result of the termination of the agreement at the end of the third
quarter. Revenue was affected by a 92% recovery factor achieved in
2023, 8% below plan. Revenue in the fourth quarter was also
affected by the natural variability in the value of large stones
recovered in any given period. As a result of these factors,
revenue from HB decreased to 48% of total revenue recognized in the
fourth quarter of 2023 (Q4 2022 - 60%). The product mix in Q4 2023
was predominantly from the South Lobe ore body, with some
contribution from the Centre Lobe (Q4 2022 - 100% South Lobe
ore).
CLARA SALES PLATFORM
During Q4 2023, the sales volume
transacted was $2.3 million (Q4 2022: $6.6 million), as lower
volumes and lower valued goods were placed for sale (due to the
shift in product mix from the Karowe Mine). Some sales are
recognized on a net revenue basis. A softer market was
observed with the voluntary import ban on rough diamonds into India
during the fourth quarter. Prices increased 5% overall in December
with a resumption of purchasing across most size categories;
however, prices remain lower than Q4 2022. Price stability
continues to be observed in the stones between 5 to 10.8 carats in
size.
QUARTERLY TENDER
A total of 108,137 carats were sold
in the December 2023 tender, generating revenues of $16.9 million
or $156 per carat (Q4 2022 tender: $12.2 million from the sale of
76,264 carats or $133 per carat). Rough diamond prices saw a strong
rebound in the fourth quarter of 2023 following the significant
decrease observed earlier in 2023 as market fundamentals
strengthened. A 19% increase from the third quarter tender was
observed owing to price increases and product mix offered in the
fourth quarter tender.
SUBSEQUENT EVENT
On February 18, 2024, the Company
announced the signing of a NDSA with HB in respect of all
qualifying diamonds produced in excess of 10.8 carats in size from
the Karowe Mine. The NDSA is subject to the approval of the
Company's project lenders. Upon such approval the agreement terms
will be effective retroactively from December 1, 2023. Since that
time, Lucara has continued to supply qualifying rough diamonds to
HB in order to fund its operations and the Karowe UGP.
KAROWE UNDERGROUND EXPANSION
UPDATE
The Karowe UGP is designed to access
the highest value portion of the Karowe orebody, with initial
underground carat production predominantly from the highest value
eastern magmatic/pyroclastic kimberlite (south) ("EM/PK(S)")
unit. The underground expansion is expected to extend mine
life to at least 2040.
On July 16, 2023, an update to the
Karowe UGP schedule and budget was announced (Press
Release). This update was initiated in
response to slower than planned ramp up to expected sinking rates
in 2022, and, to account for time incurred to complete grouting
programs while mining through the water-bearing geological zones.
These chemical grouting programs took longer than anticipated due
to a combination of high-water volumes in the sandstone lithologies
between 870 and 752 metres above sea level in depth (144 metres to
262 metres below the shaft collar) and technical challenges
associated with the transition to main sinking.
The updated schedule incorporates a
28% increase in the duration of construction, extending the
anticipated commencement of production from the underground from H2
2026 to H1 2028. The revised forecast of costs at completion is
$683.0 million (including contingency), a 25% increase to the May
2022 estimated capital cost of $547 million. The forecasted
increase of $136.0 million in estimated capital to reach project
completion is predominantly related to increased schedule duration
and related labour costs (approximately 56% of the total increase),
grouting costs (approximately 20% of the total increase), with the
balance of the increase attributable to owner's costs, procurement,
and indirect project costs. As at December 31, 2023, capital
expenditures of $310.5 million had been incurred and capital
commitments of $77.2 million had been made.
During the year ended December 31,
2023, a total of $101.3 million was spent on the Karowe UGP
development, capitalized borrowing costs, surface infrastructure,
grouting programs, and ongoing shaft sinking activities. The
following activities were completed during Q4 2023:
· Main
sinking in the production and ventilation shafts:
o The
ventilation shaft reached 348 metres below collar, with a planned
final depth of 731 metres. The shaft is currently 61 metres or
approximately 26 days ahead of the July 2023 schedule update
(combined vertical and lateral metres).
o The
production shaft reached 348 metres below collar, with a planned
final depth of 765 metres. The production shaft is 11 metres or
approximately 24 days behind the July 2023 schedule update
(combined vertical and lateral) mainly due to an unscheduled
grouting event in Q3 2024. The production shaft is not on the
project schedule critical path.
o At
the end of 2023, both shaft bottoms were at 348 metres below collar
(666 masl) having completed the first shaft stations at the
670-level and engaged in the start of 670-level lateral
development.
o During Q4 2023, the ventilation shaft sank 76 metres,
completed the 718 slinging cubby and established the 670-level
station, catwalk and was engaged in level development. Total
lateral developed in Q4 2023 was 97 metres. During the quarter, a
Kubota, Sandvik DD321 two boom jumbo drill and a Caterpillar
RG1300G 7-tonne LHD were slung down in the ventilation shaft to the
670-level for lateral development mining.
o Production shaft activities included sinking a total of 114
metres and establishing the 670-level station, catwalk and
initiating lateral development. A total of 30 metres of lateral
development was completed.
o Commissioning of the temporary bulk air coolers at each shaft
was completed and construction of the permanent bulk air coolers at
the production shaft continued.
o Detailed engineering and fabrication of the permanent men and
materials winder commenced during the quarter, representing the
last major component for the permanent winders.
o Both
shafts have completed sinking through the water-bearing Ntane and
Mosolotane sandstones. Sinking and lateral development during the
fourth quarter took place in the Thalbala mudstone in dry
conditions.
· Contract for fabrication of the permanent men and materials
winder was signed during the quarter, representing the last major
component for the permanent winders.
· Mining
engineering advanced with a focus on supporting shaft sinking,
underground infrastructure engineering and finalizing level
plans.
· The
impact of implementing a behavioural-based safety training program,
Safe Start®, in Q4 2022 has been evident in 2023. During 2023, the
UGP achieved a twelve-month rolling Total Recordable Injury
Frequency Rate of 0.19. Project to date Total Recordable Injury
Frequency Rate at December 31, 2023 was 0.55.
The capital cost for the underground
expansion in 2024 is expected to be up to $100 million - see "2024
Outlook". Activities for the Karowe UGP in Q1 2024 are
expected to include the following:
· Resumption of sinking within the ventilation and production
shafts.
· Completion of mining and construction activities on the 670
level station, including connection of the two shafts and
establishment of electrical substation, sump and de-watering pumps
and ventilation doors.
· Planned grouting events at the base of the Tlapana
carbonaceous shale and top of Mea formation is expected during the
period in the production shaft.
· Procurement of underground equipment, including dewatering
pumps, underground crush and convey systems and the permanent stage
winder.
· Commissioning of the permanent bulk air cooler
system.
· Preparation of tender documents for the underground lateral
development work; and,
· Continuation of detailed design and engineering of the
underground mine infrastructure and layout.
FINANCIAL HIGHLIGHTS - Q4 2023
|
|
|
|
|
|
|
|
|
Three months ended December
31,
|
|
Year ended December 31,
|
In millions of U.S. dollars, except
carats or otherwise noted
|
|
2023
|
2022
|
|
2023
|
2022
|
|
|
|
|
|
|
|
Revenues
|
$
|
36.5
|
42.5
|
$
|
177.4
|
212.9
|
Operating expenses
|
|
(22.3)
|
(18.5)
|
|
(78.6)
|
(79.3)
|
Net income for the
period
|
|
(36.7)
|
7.1
|
|
(20.2)
|
40.4
|
Earnings per share (basic and
diluted)
|
|
(0.07)
|
0.02
|
|
(0.04)
|
0.09
|
Operating cash flow per
share(1)
|
|
0.00
|
0.03
|
|
0.11
|
0.19
|
Cash on hand
|
|
13.3
|
26.4
|
|
13.3
|
26.4
|
Cost overrun facility (restricted
cash)
|
|
18.6
|
-
|
|
18.6
|
-
|
Amounts drawn on working capital
facility(2)
|
|
35.0
|
15.0
|
|
35.0
|
15.0
|
Amounts drawn on project finance
facility
|
|
90.0
|
65.0
|
|
90.0
|
65.0
|
Karowe Revenue
|
|
36.3
|
40.1
|
|
172.4
|
203.8
|
Carats sold
|
|
111,523
|
81,264
|
|
379,287
|
327,028
|
QUARTERLY RESULTS OF OPERATIONS - KAROWE MINE,
BOTSWANA
|
UNIT
|
Q4-23
|
Q3-23
|
Q2-23
|
Q1-23
|
Q4-22
|
Sales
|
|
|
|
|
|
|
Revenues from the sale of Karowe
diamonds
|
US$M
|
36.3
|
56.2
|
38.6
|
41.3
|
40.1
|
Karowe carats sold
|
Carats
|
111,523
|
111,673
|
72,717
|
83,374
|
81,264
|
Production
|
|
|
|
|
|
|
Tonnes mined (ore)
|
Tonnes
|
607,101
|
869,188
|
682,636
|
541,400
|
484,705
|
Tonnes mined (waste)
|
Tonnes
|
456,880
|
954,226
|
907,051
|
761,295
|
199,385
|
Tonnes processed
|
Tonnes
|
703,472
|
724,640
|
720,345
|
700,678
|
690,946
|
Average grade
processed(1)
|
cpht (*)
|
14.0
|
13.6
|
12.6
|
12.8
|
12.5
|
Carats
recovered(1)
|
Carats
|
98,177
|
98,311
|
90,497
|
89,640
|
86,655
|
Costs
|
|
|
|
|
|
|
Operating cost per tonne of ore
processed(2)
|
US$
|
31.96
|
28.62
|
27.97
|
26.65
|
26.20
|
|
|
|
|
|
|
|
Capital Expenditures
|
|
|
|
|
|
|
Sustaining capital
expenditures
|
US$M
|
8.0
|
3.2
|
2.4
|
0.8
|
9.9
|
Underground expansion
project(3)
|
US$M
|
28.0
|
20.3
|
22.5
|
30.5
|
22.3
|
CONFERENCE CALL
The Company will host a conference
call and webcast to discuss the results on Wednesday, February 21,
2024 at 6:00am Pacific, 9:00am Eastern, 2:00pm UK, 3:00pm CET. To
join the conference call please use the following link
https://emportal.ink/48xMjQ6
or the phone numbers listed below.
Conference ID:
26126065 / Lucara Diamond
Dial-In Numbers:
Toll-Free Participant Dial-In North
America
(+1) 888 390 0605
UK Toll
free
0800 652 2435
Local
Toronto
(+1) 416 764 8609
Webcast:
To view the live webcast
presentation, please log on using this direct link:
https://app.webinar.net/lrAM9b291Zz
The presentation slideshow will also be available
in PDF format for download from the Lucara website
(Link to
presentation).
Conference Replay:
A replay of the telephone conference
will be available two hours after the completion of the call until
February 28, 2024. The pass code for the replay is: 126065
#
Replay number (Toll Free North
America) (+1) 888 390 0541
Replay number
(Local)
(+1) 416 764 8677
On
behalf of the Board,
William Lamb
President and Chief Executive
Officer
Follow Lucara Diamond on
Facebook,
Instagram,
and LinkedIn
For further information, please
contact:
ABOUT LUCARA
Lucara is a leading independent
producer of large exceptional quality Type IIa diamonds from its
100% owned Karowe Diamond Mine in Botswana. The Karowe Mine has
been in production since 2012 and is the focus of the Company's
operations and development activities. Clara Diamond Solutions
Limited Partnership ("Clara"), a wholly-owned subsidiary of Lucara,
has developed a secure, digital sales platform which ensures
diamond provenance from mine to finger. Lucara has an
experienced board and management team with extensive diamond
development and operations expertise. Lucara and its
subsidiaries operate transparently and in accordance with
international best practices in the areas of sustainability, health
and safety, environment, and community relations. Lucara has
adopted the IFC Performance Standards and the World Bank Group's
Environmental, Health and Safety Guidelines for Mining
(2007). Accordingly, the development of the Karowe
underground expansion project ("UGP") adheres to the Equator
Principles. Lucara is committed to upholding high standards while
striving to deliver long-term economic benefits to Botswana and the
communities in which the Company operates.
The information is information that
Lucara is obliged to make public pursuant to the EU Market Abuse
Regulation and the Swedish Securities Markets Act. This information
was submitted for publication, through the agency of the contact
person set out above, on February 20, 2024 at 2:00pm Pacific
Time.
NON-IFRS FINANCIAL PERFORMANCE
MEASURES
This news release refers to certain
financial measures, such as adjusted EBITDA, adjusted operating
earnings, operating cash flow per share, operating margin per carat
sold and operating cost per tonne of ore processed, which are not
measures recognized under IFRS and do not have a standardized
meaning prescribed by IFRS. These measures may differ from those
made by other corporations and accordingly may not be comparable to
such measures as reported by other corporations. These measures
have been derived from the Company's financial statements, and
applied on a consistent basis, because the Company believes they
are of assistance in the understanding of the results of operations
and financial position. Please refer to the Company's MD&A for
the year ended December 31, 2023 for an explanation of non-IFRS
measures used.
CAUTIONARY NOTE REGARDING FORWARD
LOOKING STATEMENTS
Certain of the statements made
herein contain certain "forward-looking information" and
"forward-looking statements" as defined in applicable securities
laws. Generally, any statements that express or involve discussions
with respect to predictions, expectations, beliefs, plans,
projections, objectives, assumptions or future events or
performance and often (but not always) using forward-looking
terminology such as "expects", "is expected", "anticipates",
"believes", "plans", "projects", "estimates", "budgets",
"scheduled", "forecasts", "assumes", "intends", "strategy",
"goals", "objectives", "potential", "possible" or variations
thereof or stating that certain actions, events, conditions or
results "may", "could", "would", "should", "might" or "will" be
taken, occur or be achieved, or the negative of any of these terms
and similar expressions) are not statements of historical fact and
may be forward-looking statements.
In particular, forward-looking
information and forward-looking statements may include, but are not
limited to, information or statements with respect to the Company's
ability to continue as a going concern, the project schedule and
capital costs for the Karowe UGP, the diamond sales, projection and
outlook disclosure under "2024 Outlook", the Company's ability to
fund the COF, the impact of supply and demand of rough or polished
diamonds, expectations regarding top-up values, estimated capital
costs, the timing, scope and cost of additional grouting events at
the Karowe UGP, the Company's ability to comply with the terms of
the Facilities which are required to construct the Karowe UGP,
including future funding requirements to the COF, that expected
cash flow from operations, combined with external financing will be
sufficient to complete construction of the Karowe UGP, that
the estimated timelines to achieve mine ramp up and full production
from the Karowe UGP can be achieved, that sufficient stockpiled ore
will be available to generate revenue prior to the achievement of
commercial production of the Karowe underground mine, the economic
potential of a mineralized area, the size and tonnage of a
mineralized area, anticipated sample grades or bulk sample diamond
content, expectations that the Karowe UGP will extend mine life,
forecasts of additional revenues, future production activity, that
depletion and amortization expense on assets will be affected by
both the volume of carats recovered in any given period and the
reserves that are expected to be recovered, the future price and
demand for, and supply of, diamonds, expectations regarding the
scheduling of activities for the Karowe UGP in 2024, future
forecasts of revenue and variable consideration in determining
revenue, the impact of the termination of the HB sales agreement on
the Company's projected revenue and sales channels, estimation of
mineral resources, exploration and development plans, cost and
timing of the development of deposits and estimated future
production, interest rates, including expectations regarding the
impact of market interest rates on future cash flows and the fair
value of derivative financial instructions, currency exchange
rates, rates of inflation, credit risk, price risk, requirements
for and availability of additional capital, capital expenditures,
operating costs, timing of completion of technical reports and
studies, production and cost estimates, tax rates, timing of drill
programs, government regulation of operations, environmental risks
and ability to comply with all environmental regulations,
reclamation expenses, title matters including disputes or claims,
limitations on insurance coverage, the profitability of Clara and
the Clara Platform, and the scaling of the digital platform for the
sale of rough diamonds owned by Clara, the expected use of the
Clara Facility, that the Company intends to continue to seek
additional supply, both from third-party producers and the
secondary market for Clara, and the potential impacts of COVID-19,
economic and geopolitical risks, including potential impacts from
the Russian military invasion of Ukraine and the escalating
conflict between Israel and Hamas.
Forward-looking information and
statements are based on the opinions and estimates of management as
of the date such statements are made, and they are subject to
several known and unknown risks, uncertainties and other factors
which may cause the actual results, performance or achievements of
the Company to be materially different from any future results,
performance or achievement expressed or implied by such
forward-looking statements. The Company believes that expectations
reflected in this forward-looking information are reasonable, but
no assurance can be given that these expectations will prove to be
correct. Certain risks which could impact the Company are
discussed under the heading "Risks and Uncertainties" in the
Company's most recently filed Annual MD&A and, in the Company's
most recent Annual Information Form available at
http://www.sedar.com (the "AIF").
The foregoing is not exhaustive of
the factors that may affect any of our forward-looking statements.
Forward-looking statements are statements about the future and are
inherently uncertain, and our actual achievements or other future
events or conditions may differ materially from those reflected in
the forward-looking statements due to a variety of risks,
uncertainties, and other factors, including, without limitation,
those referred to in this news release.
Although the Company has attempted
to identify important factors that could cause actual actions,
events, or results to differ materially from those described in
forward-looking statements, there may be other factors that cause
actions, events or results not to be as anticipated, estimated or
intended. The forward-looking statements contained in this news
release are based on the beliefs, expectations, and opinions of
management as of the date of this disclosure. There can be no
assurance that forward-looking statements will prove to be
accurate, as actual results and future events could differ
materially from those anticipated in such statements. Accordingly,
readers and investors should not place undue reliance on
forward-looking statements. Forward-looking information and
statements are made as of the date of this disclosure and
accordingly are subject to change after such date. Except as
required by law, the Company disclaims any obligation to revise any
forward-looking information and statements to reflect events or
circumstances after the date of such information and statements.
All forward-looking information and statements contained or
incorporated by reference in this news release are qualified by the
foregoing cautionary statements.