Critical
Metals plc / EPIC: CRTM / Market: Main Market
11 November 2024
Critical Metals
plc
("Critical Metals" or the
"Company")
Operational and Financing
Update
Critical Metals plc, developer and
operator of the Molulu Copper/Cobalt Project ("Molulu" or the
"Project") in the Democratic Republic of Congo ("DRC"), provides
the following update with regards to the investments and loans made
to the Company along with an operational update.
Operational Update and Delivery of Ore
After taking several samples from
the various ore stockpiles, OM Metals SARL, the current copper ore
off-taker, has sent its first ore haulage truck to load ore from
the Company's stockpile for purchase and processing at the OM
Metals plant. Approximately 40-tonnes of copper ore was loaded onto
the truck and has arrived at the OM Metals plant for crushing,
assaying, analysis, and processing.
Figure 1 - Truck arriving at OM Metals scale to weigh Molulu
copper ore
Figure 2 - Delivery and discharge of Molulu copper ore at OM
Metals plant
Additional trucks from OM Metals
will follow once sampling and assaying are completed this week.
Payment for this ore should happen within two weeks after invoicing
OM Metals.
In addition, geotechnical and
geological activities at Molulu are resuming as the geologist team
has returned from leave. There are several areas identified for
continued geotechnical activities in the Southern zone and an area
where the Conglomerate outcrops with traces of copper malachite in
the Northern zone. These geotechnical activities will provide
further data points for consideration when designing the new
diamond drill programme.
Preliminary discussions are ongoing
with various agencies to plan a feasibility study for the potential
installation of a 2 MW solar power unit at Molulu. This power unit
is designed to reduce costs at the camp and to supply enough power
to operate a potential future copper concentrator plant and
surrounding area, including the E.P. Molulu school. The
installation of any solar power unit would be subject to the
Company obtaining additional funding or grants.
Financing
On 18th September 2023,
the Company announced that it had signed a facility (the
"Facility") with an international financial institution ("Lender"),
enabling it to drawdown in tranches, up to a maximum of US$3
million of loan funds. To date, the Company has borrowed a total of
US$650,000 from the Facility. On 10 April 2024, the Company
previously announced that US$100,000 was repaid from the proceeds
of the convertible loan notes issued on that date. The
Company also announced that same day that US$79,500 of interest and
fees from the Facility were applied towards the subscription price
for convertible loan notes issued by the Company. Of the
remaining balance under the Facility, US$511,525 was due to be
repaid in June 2024 in interest and principal and the remaining sum
being due in three instalments before 20 September 2024.
The Company and Lender had agreed to
extend the time for repayment until 30
September 2024 in anticipation of the closing of a financing that
would have fully repaid the Facility. In consideration, the Company
extended the period for the exercise of the 2,000,000 warrants
granted to the Lender at the time the Facility was entered into
until 15 September 2025. The 30 September 2024 deadline for
the extension has not been met due to continuing due diligence
related to the financing.
On 10 November 2024, the Company
reached an agreement with the Lender to reschedule its payments
under its current Facility. The Lender has now agreed to defer
payments totalling US$645,651 (including accrued interest) until 20
December 2024. The Company has a right to gain a further extension
until 31 January 2025 through the payment of $75,000 towards the
outstanding principal before 20 December 2024. The Lender's
consent to a standstill is subject to customary conditions
including but limited to no insolvency type events occurring, the
Company's shares remaining trading and the Company complying with
various warranties and obligations (including authority and
capacity warranties, information undertakings in favour of the
Lender and compliance with a prohibition on certain third-party
security).
For avoidance of doubt, the Company
has not received any default notice from the Lender regarding the
Facility. In addition, the Lender is aware the Company is actively
engaged in advanced discussions about refinancing.
Finally, the Company has implemented
cost-saving measures to preserve cash, including voluntary salary
deferral reductions of 25% at the executive level and strategic
reductions in workforce to align with current conditions. The
recruitment of additional staff and the engagement of essential
consultants for comprehensive hydrological, geohydrological,
topographical, and JORC reports will be re-looked at when financing
is available.
Further updates will be provided as
and when appropriate.
**ENDS**
For further information on the
Company please visit www.criticalmetals.co.uk or
contact:
Critical Metals plc
CEO
Russell Fryer
|
critical@stbridespartners.co.uk
|
Fox-Davies Capital Limited
Corporate Broker
Daniel Fox-Davies
|
Tel: +44 (0)20 3884 8450
|
St
Brides Partners Ltd
Financial PR
Ana Ribeiro / Charlotte
Page
|
critical@stbridespartners.co.uk
|
About Critical Metals
London listed Critical Metals plc is
focused on identifying low CAPEX and OPEX brown-field projects with
near-term production and cash-flow, concentrating on minerals that
have strategic importance to future global economic growth.
In line with this, and with an off-take partner already in place,
the Company is currently focused on recommencing production at the
formerly producing Molulu Copper/Cobalt Project in the Katangan
Copperbelt in Democratic Republic of Congo
('DRC').