Bunker Hill Mining Corp. (“Bunker
Hill” or the
“Company”) (TSXV:BNKR
|OTCQX:BHLL) announces that the Bunker Hill Mine restart project,
which is approximately 64% complete with 98% of procurement
completed, has undergone a strategic review resulting in an updated
timeline and capital requirements.
Pursuant to this review, the Company now
forecasts a total restart expenditure (excluding working capital)
of $103 million, up from the previously forecasted $67 million and
the $56 million in the 2022 Pre-Feasibility Study (the
“PFS”), with the restart project anticipated to be
delayed by up to four months. To provide sufficient project finance
for the ongoing development of the Bunker Hill Mine, the Company
intends to draw down on the $21 million standby facility (the
“Standby Facility”) provided by Sprott Private
Resource Streaming and Royalty Corp. and finalize the ongoing
discussions with its strategic partners for potential offtake or
similar financing for an additional $30 million.
Sam Ash, President and CEO, commented: “This
revised plan takes full account of the many challenges facing the
project and the rest of the US mining industry. Work onsite
continues round the clock at the highest intensity possible to
complete mechanical installation and commissioning and deliver the
demanding restart plan. The adjustment we’re announcing reflects
the outcome of weeks of intense work by the small Bunker team,
Gypsy LLC, our procurement, construction, and management contractor
and their many supporters to counter the worst effects of
inflation, scope changes since the PFS, and an unplanned contractor
change. We are pleased to be able to draw upon the Standby Facility
and conclude offtake and associated financing discussions to ensure
that profitable and sustainable operations may commence by the
revised start date of Q2 2025. We wish to thank our partners at
Sprott Private Resource Streaming and Royalty Corp. and our many
skilled contractors working on this critical US project for their
steadfast and enduring support.”
STRATEGIC REVIEW – ACTIVITY AND
CONCLUSIONS
Over the past eight weeks, the Company has
reviewed the impact of the following key factors on the restart
plan, seeking ways to mitigate them and incorporate them within the
revised forecast:
- Input
Cost Inflation—As widely reported across the US Mining
Industry, the cost of skilled construction labor (specifically
electricians) has increased by 53% over the last 12 months, from an
average of $75/hour to $114/hour. The cost of structural steel has
also increased by 40%, copper (a proxy for electrical fittings) by
40%, and concrete by 20%. These are extraordinary numbers that
deeply impact every aspect of the project.With labor being the
primary input cost in the project's mechanical installation and
commissioning phases, this has been the most challenging to
mitigate. Efforts have been made to bring some of this work
in-house, but these have not significantly impacted total cost
projections, particularly given the impact of steel, concrete,
electrical and other inflation (as crystallized in the recent and
final procurement orders).
- Filter
Press Scope Change - As reported in the news release dated
May 21, 2024 the Company chose to change the Tailings Management
System envisaged in the 2022 PFS and starting budget, in order to
improve long-term efficiency and sustainability, following tailings
filtration testing. The more effective and expensive filter press
(as compared to the $5 million disk filter system described in the
2022 PFS) passed the 90% engineering milestone in October 2024.
This final design and associated inflation-effected procurement
through November resulted in the final cost forecast increase from
$10 million to $18 million.
-
Specialist Contractor Walk-Out - In August 2024,
the specialist contractor conducting the auger-cast deep piers for
the tailings filter press demobilized unexpectedly to pursue other
work in North America. Given the tight market for this specialty
construction work, securing and mobilizing a replacement contractor
for this deep pier construction onto the mine site was challenging
passing on delays to the construction timeline.To mitigate this
unexpected schedule delay, the Company conducted an engineering
study to consider the deferral of the construction of the Tailings
Filter Press into 2026, with tailings instead being pumped directly
from the Kellogg Yard to the paste plant in the Wardner operating
base and into voids underground at start-up. After conducting
trade-off analysis, it was determined that this phased solution was
not workable and that it would be more prudent to continue the
complete construction as planned, albeit on a delayed timeline. It
was judged to be far better to have the optimal system at restart
geared to serving the 1,800 tons per day plan, than a potentially
risky work-around that would put initial cash flow at risk.
Taking account of these key factors and any
mitigating actions, the review determined that the project restart
would be delayed until at least Q2 2025 and that the total project
expenditure (including working capital) is expected to increase by
approximately $50 million.
RESTART PLAN UPDATE
Processing Plant - 66%
complete. The mechanical installation of the final elements of the
processing plant is continuing, with the phased commissioning of
the circuit starting by the end of December 2024 following the
plant's connection to the grid power via the Bunker Hill
transformer. The external conveyor network is being installed
connecting the crusher, ore silo, plant and concentrate load-out
facility. Inside the main building piping, pumps, electrical
infrastructure and working mezzanine platforms are installed in
stages.
Figure 1: Conveyor
installation
Figure 2: Mezzanine floor and equipment
installation
Tailings Filter Press - 38%
Complete. The concrete foundations for the tailings filter press
are laid in stages upon the deep piers. This is concurrent with the
construction of the tailings storage tank and associated
infrastructure and off-site, the final construction of the various
components of the facility.
Figure 3: Rendering of the final
tailings filter press design
Figure 4: Tailings storage tank
construction (December 2024)
Underground - 80% Complete.
Conducted from the Wardner Operating Facility, the underground
development continues to be on track and budget. Access to five
mining stopes has already been prepared in the underground area of
the mine. These are ready to be mined now. Refurbishment of the
access ramp to level 8 mining areas is 75% complete. Work is
currently focused on improving the ramp’s geotechnical strength as
it cuts through the Cate Fault; and thereby enable longer life
mining than that envisaged in the 2022 PFS. Stockpiling of ore
underground during the ramp refurbishment will commence by the end
of 2024.
Figure 5: Steel Sets supporting ramp
through Cate Fault
Mine Planning - This revised
forecast incorporates the Company’s optimization efforts conducted
over the prior months to ensure the most sustainable and profitable
restart operation possible while mitigating the impact of cost
increases. The plan update includes an adjusted mine plan to
maximize cash flows from year one.
Resource and Reserve Expansion
- This revised forecast incorporates more drilling and technical
work into the plan. Specifically, it incorporates the identified
silver targets in the upper part of the mine into the early mine
plan and technical studies for Bunker 2.0: the move to 2,500 tons
per day. The Company is processing the data gathered from the 2024
drilling campaign and intends to issue a Resource and Reserve
update as planned in Q1 2025, as well as provide periodic updates
on these results over the next few weeks.
FINANCING PLAN
The Company intends to commence drawing in
tranches upon the Standby Facility provided from December 12, 2024.
The first tranche will provide $5 million in working capital. The
ongoing negotiations with various financing partners to secure a
$30 million financing package are expected to be concluded by the
end of January 2025.
Concurrent with this, the Company will continue
to advance the process required to unlock the $150 million facility
from US EXIM by the end of 2025 which the Company would utilize to
refinance the existing debt and increase the mine’s expected
production capacity to 2,500 tons per day.
Even with the Company’s plans to secure the
necessary financing for the project restart pursuant to the updated
forecast, there is no certainty that the Company will be able to
raise the funds required to complete the necessary development work
needed to restart operations and advance the ongoing mine plan
adjustments. While the Company anticipates operations to commence
in the second quarter of 2025, there is no certainty that this will
be the case.
CORPORATE UPDATE WEBINAR
The Company will host a webinar on
Friday, December 13, 2024 at 9:00am PST/12:00pm EST featuring
a presentation from Bunker Hill’s President and CEO Sam Ash,
Executive Chairman Richard Williams and CFO Gerbrand Van Heerden. A
recording of the webinar will be available on the Company’s
website.
Attendees can register for the webinar using the
following link:
https://6ix.com/event/bunker-hill-announces-updated-forecast-for-mine-restart-and-revised-financing
ABOUT BUNKER HILL MINING
CORP.
Under Idaho-based leadership, Bunker Hill
intends to sustainably restart and develop the Bunker Hill Mine as
the first step in consolidating and then optimizing a number of
mining assets into a high-value portfolio of operations, centered
initially in North America. Information about the Company is
available on its website, www.bunkerhillmining.com, or within the
SEDAR+ and EDGAR databases.
On behalf of the Board of Directors of
Bunker Hill Mining Corp.
Sam AshPresident and Chief Executive Officer
For additional information, please
contact:
Brenda DaytonVice President, Investor
RelationsT: 604.417.7952E: brenda.dayton@bunkerhillmining.com
Cautionary Statements
Neither the TSX Venture Exchange (the “TSX-V”)
nor its Regulation Services Provider (as that term is defined in
the policies of the TSX-V) accepts responsibility for the adequacy
or accuracy of this news release.
Certain statements in this news release are
forward-looking and involve a number of risks and uncertainties.
Such forward-looking statements are within the meaning of that term
in Section 27A of the Securities Act and Section 21E of the U.S.
Securities Exchange Act of 1934, as amended, as well as within the
meaning of the phrase ‘forward-looking information’ in the Canadian
Securities Administrators’ National Instrument 51-102 – Continuous
Disclosure Obligations (collectively, “forward-looking
statements”). Forward-looking statements are not comprised
of historical facts. Forward-looking statements include estimates
and statements that describe the Company’s future plans, objectives
or goals, including words to the effect that the Company or
management expects a stated condition or result to occur.
Forward-looking statements may be identified by such terms as
“believes”, “anticipates”, “expects”, “estimates”, “may”, “could”,
“would”, “will”, “plan” or variations of such words and
phrases.
Forward-looking statements in this news release
include, but are not limited to, statements regarding: the
Company’s objectives, goals or future plans, including the restart
and development of the Bunker Hill Mine and the updated timeline
and forecast and anticipated capital requirements in connection
therewith; the achievement of future short-term, medium-term and
long-term operational strategies and objectives and the expected
timing thereof, including with respect to planned production; the
Company raising the required funds for the planned project restart
through its project finance initiatives, including by way of debt,
equity, offtake or similar financings; and the expected budget and
estimated completion time for the underground development of the
Bunker Hill Mine. Forward-looking statements reflect material
expectations and assumptions, including, without limitation,
expectations and assumptions relating to: Bunker Hill’s ability to
receive sufficient project financing for the restart and
development of the Bunker Hill Mine on acceptable terms or at all;
the revised forecast, capital requirements and updated timeline for
the project restart resulting in planned production by Q2 2025; the
future price of metals; and the stability of the financial and
capital markets. Factors that could cause actual results to differ
materially from such forward-looking statements include, but are
not limited to, those risks and uncertainties identified in public
filings made by Bunker Hill with the U.S. Securities and Exchange
Commission (the “SEC”) and with applicable
Canadian securities regulatory authorities, and the following: the
Company’s ability to operate as a going concern and its history of
losses; the Company’s ability to raise sufficient project financing
for the restart and development of the Bunker Hill Mine on
acceptable terms or at all, including through equity or debt
financings, concentrate offtake financings or otherwise; the
Company requiring more capital expenditures than anticipated in the
updated forecast, resulting in delays in the updated timeline; the
fluctuating price of commodities; capital market conditions;
restrictions on labor and its effects on international travel and
supply chains; failure to identify mineral resources; failure to
convert estimated mineral resources to reserves; the preliminary
nature of metallurgical test results; the Company’s ability to
restart and develop the Bunker Hill Mine and the risks of not
basing a production decision on a feasibility study of mineral
reserves demonstrating economic and technical viability, resulting
in increased uncertainty due to multiple technical and economic
risks of failure which are associated with this production decision
including, among others, areas that are analyzed in more detail in
a feasibility study, such as applying economic analysis to
resources and reserves, more detailed metallurgy and a number of
specialized studies in areas such as mining and recovery methods,
market analysis, and environmental and community impacts and, as a
result, there may be an increased uncertainty of achieving any
particular level of recovery of minerals or the cost of such
recovery, including increased risks associated with developing a
commercially mineable deposit, with no guarantee that production
will begin as anticipated or at all or that anticipated production
costs will be achieved; failure to commence production would have a
material adverse impact on the Company’s ability to generate
revenue and cash flow to fund operations; failure to achieve the
anticipated production costs would have a material adverse impact
on the Company’s cash flow and future profitability; delays in
obtaining or failures to obtain required governmental,
environmental or other project approvals; political risks; changes
in equity markets; uncertainties relating to the availability and
costs of financing needed in the future; the inability of the
Company to budget and manage its liquidity in light of the failure
to obtain additional financing, including the ability of the
Company to complete the payments pursuant to the terms of the
agreement to acquire the Bunker Hill Mine complex; inflation;
changes in exchange rates; changes in labor costs and availability
of skilled labor and specialists; fluctuations in commodity prices;
delays in the development of projects; and capital, operating and
reclamation costs varying significantly from estimates and the
other risks involved in the mineral exploration and development
industry. Although the Company believes that the assumptions and
factors used in preparing the forward-looking statements in this
news release are reasonable, undue reliance should not be placed on
such statements or information, which only applies as of the date
of this news release, and no assurance can be given that such
events will occur in the disclosed time frames or at all, including
as to whether or when the Company will achieve its project finance
initiatives, or as to the actual size or terms of those financing
initiatives or as to whether and when the Company will achieve its
operational and construction targets. The Company disclaims any
intention or obligation to update or revise any forward-looking
information, whether as a result of new information, future events
or otherwise, other than as required by law. No stock exchange,
securities commission or other regulatory authority has approved or
disapproved the information contained herein.
Readers are cautioned that the foregoing risks
and uncertainties are not exhaustive. Additional information on
these and other risk factors that could affect the Company’s
operations or financial results are included in the Company’s
annual report and may be accessed through the SEDAR+ website
(www.sedarplus.ca) or through EDGAR on the SEC website
(www.sec.gov).
Photos accompanying this announcement are available at:
https://www.globenewswire.com/NewsRoom/AttachmentNg/7cf78a59-dcd6-473e-9eca-0e3d3e2cf415
https://www.globenewswire.com/NewsRoom/AttachmentNg/e4917b71-939b-4ee3-bdff-93b2f4c7e7ab
https://www.globenewswire.com/NewsRoom/AttachmentNg/5d897893-9f21-4e64-abdc-f3f00bdd6452
https://www.globenewswire.com/NewsRoom/AttachmentNg/7c786dc5-e95e-4f33-af66-bce2b86595ee
https://www.globenewswire.com/NewsRoom/AttachmentNg/10e15f9b-5df0-48f2-832f-e9fac73d8118
Grafico Azioni Bunker Hill Mining (TSXV:BNKR)
Storico
Da Dic 2024 a Gen 2025
Grafico Azioni Bunker Hill Mining (TSXV:BNKR)
Storico
Da Gen 2024 a Gen 2025