TSX-V: MKO; OTCQX:
MAKOF
VANCOUVER, BC, July 20,
2022 /CNW/ - Mako Mining Corp. (TSXV:
MKO) (OTCQX: MAKOF) ("Mako" or the "Company") is
pleased to provide second quarter 2022 ("Q2 2022")
production results from its San Albino gold mine ("San
Albino") in northern Nicaragua, which is the fourth full quarter of
production results since declaring commercial production on
July 1st, 2021. Financial
results for Q2 2022, including detailed reporting of our operating
costs, are expected to be released in August.
Q2 2022 Production
Highlights
- 47,220 tonnes mined containing 11,421 ounces of gold ("oz
Au") at a blended grade of 7.52 grams per tonne gold ("g/t
Au")
-
- 22,560 tonnes mined containing 9,324 oz Au from diluted vein
material at 12.85 g/t Au
- 24,660 tonnes mined containing 2,097 oz Au from historical dump
and other mineralized material above cutoff grade ("historical
dump + other") at 2.65 g/t Au
- 7.0:1 strip ratio for Phase 1
- 26.5:1 strip ratio overall which includes accelerated waste
development of the West and the Central Pit ("Arras
Zone")
- 49,332 tonnes milled containing 11,576 oz Au at a blended
grade of 7.30 g/t Au
-
- 47% and 53% from diluted vein and hanging-wall/footwall,
respectively
- 589 tonnes per day ("tpd") milled at 92%
availability
- 74.5% gold recoveries (majority of material processed was fresh
material)
- 139,401 tonnes in stockpile containing 13,385 oz Au at a
blended grade of 2.99 g/t Au
- 8,630 oz Au recovered and 9,027 oz Au sold at an average
realized price of US$1,866 per
ounce
Akiba Leisman, Chief Executive
Officer of Mako states that, "this quarter was the fourth full
quarter of commercial production at San Albino. The mine is
performing well, where the diluted vein material continues to
positively reconcile to the resource model, and mill throughput has
been running at above nameplate capacity of 500 tonnes per day,
including all availability factors. The mill averaged 589 tonnes
per day for the quarter at 92% availability, 8% above nameplate
capacity. Replenishment of spare parts and minor adjustments to the
plant since the beginning of the year improved mill availability
throughout the first half of 2022, and we expect to be running at
or above nameplate capacity for the foreseeable future.
Recoveries have been below the 86% metallurgical recoveries
predicted in our December 2019
metallurgical update (see press release dated December 13, 2019), due to organic carbon present
in the hanging-wall and footwall of the vein. The plant is going
through a series of optimizations to eliminate free cyanide
concentrations in the recycled water, which will continue
throughout Q3 2022. Additionally, we have implemented robust
sampling mechanisms, and mining and stockpiling processes aimed at
ensuring that particularly problematic material is kept away from
the mill. Fortunately, the high grade vein material is not as
problematic as the hanging-wall and footwall material, and to the
extent possible we will be processing the diluted vein separately
during the quarter with the plant optimized specifically for the
high grade material. With all of these changes, we are optimistic
that improvements in recoveries can be made later this year. A
total of 9,027 ounces were sold in the quarter (9,580 ounces sold
in Q1 2022), and operating cash flow from the mine remains robust,
with exploration expenditures increasing, preparations for rainy
season complete, an aggregate of US$10.3
million of principal being repaid under the Company's loan
facility with Wexford and Sailfish Royalty Corp. since the
beginning of Q3 2021, and 2 million common shares repurchased
through our normal course issuer bid."
Table 1 – Production Results
|
* Includes historical
dump, hanging-wall, footwall, historical muck and all other
non-vein mineralized material above cutoff grade
|
|
**For the purpose of
calculating revenue, payments to Sailfish are deducted from the
Average Realized Price
|
Table 2 – Mining by phases Q2 2022
Table 3 – Quarter End Stockpile Statistics
|
* Includes stockpiles
of mineralized material at the crusher.
|
|
** Includes historical
dump, hangingwall, footwall, historical muck and all other non-vein
mineralized material above cutoff grade.
|
Mining
The mine averaged 519 tpd of diluted vein material and
historical dump + other in Q2 2022 with a strip ratio of 26.5 in
total from the West Pit and Arras Zone that includes accelerated
waste stripping in preparation for the rainy season (see Table 2).
The current stockpile is 139,401 tonnes with 4,061 tonnes of higher
grade diluted vein mineralization with a grade of 11.81 g/t Au and
135,340 tonnes at 2.72 g/t Au of historical dump + other for a
total contained gold of 13,385 oz (mineral grade of 2.99 g/t
Au).
The higher-grade material for the quarter came from the West Pit
with an average grade of 8.02 g/t Au. As we are now deeper in the
deposit we are mining mostly fresh material. The detailed grade
control processes and procedures have been very effective in
controlling mining dilution with a range as low as 30 cm on either
side of the vein. Along with geological mapping and assays,
additional lab testing has been implemented to identify increased
organic content of the more difficult to process material,
typically found in the footwall and hanging-wall rather than the
high-grade vein itself. These improvements have increased the
ability to selectively mine, separate, and stockpile according to
grade and metallurgical characteristics while maintaining low
dilution.
There were no additional night shifts to increase production
during Q2. The rainy season started in mid-May and, as anticipated,
production was delayed due to weather with a decline in June
tonnage of approximately 22%. Although year-to-date production
remains 1.6% over forecast, a limited extra shift of one excavator
and seven trucks will start in July in an effort to ensure waste
stripping stays on schedule.
Milling
All components of the 500 tpd gravity and carbon-in-leach
processing plant have been fully operational since the beginning of
May 2021. During Q2, 2022, the plant
has been averaging 589 tpd at 92% availability (see Table
1). In Q2 2022 the plant processed 47% diluted vein material
and 53% historical dump + other to achieve an average blended grade
of 7.30 g/t Au and recovering an average of 74.5% (see Table
1).
The first two quarters of 2022 saw the mill operate at a
throughput rate significantly higher than previous quarters. This
was primarily due to improved equipment performance. The gold
recovery was lower than previous quarters due to the much higher
quantity of fresh material in the mill feed.
The fresh material contains naturally occurring carbon which can
interfere with the gold recovery process. Eliminating free
cyanide in the grinding circuit and only adding cyanide to the
slurry in the CIL is essential in order to achieve optimal
recoveries. Reducing cyanide concentrations from recycled water to
optimal levels required a change in reagents. We were previously
using the standard INCO/SO2 process (sodium metabisulfite and
copper sulfate) but the results weren`t consistent and reliable. To
adjust, we are now detoxing with sodium hypochlorite (common
bleach), but the logistics needed to obtain necessary quantities
took some time to develop. Further mill optimization efforts to
lower cyanide concentrations in the mill grinding circuit are
planned in the months ahead to more effectively treat the increased
quantity of fresh material feeding the mill.
In the meantime, we have developed robust sampling mechanisms
and mining and stockpiling processes aimed at ensuring
particularly problematic material is kept away from the mill. The
high grade vein material does not exhibit as strong pre-robbing
tendencies as the material from the hanging-wall and footwall, and
to the extent possible we will be processing that material
separately during the quarter with the plant optimized specifically
for the high grade material.
In addition, a second carbon stripping vessel is scheduled for
installation in the third quarter of 2022 which will further
debottleneck the carbon stripping circuit.
All of the above mentioned improvements to the processing plant
have helped the plant achieve processing rates of an average of 589
tpd in Q2 2022, with over 9,000 ounces of gold sold for the third
consecutive quarter (see Table 1).
Qualified Person
John Rust, a metallurgical
engineer and qualified person (as defined under NI 43-101) has read
and approved the technical information contained in this press
release. Mr. Rust is a senior metallurgist and a consultant to the
Company.
On behalf of the Board,
Akiba Leisman
Chief
Executive Officer
About Mako
Mako Mining Corp. is a publicly listed gold mining, development
and exploration company. The Company operates the high-grade San
Albino gold mine in Nueva Segovia,
Nicaragua, which ranks as one of
the highest-grade open pit gold mines globally. Mako's primary
objective is to operate San Albino profitably and fund exploration
of prospective targets on its district-scale land package.
Forward-Looking Information: Statements
contained herein, other than historical fact, may be considered
"forward-looking information" within the meaning of applicable
securities laws. The forward-looking information contained herein
is based on the Company's plans and certain expectations and
assumptions, including that Q2, 2022 detailed operating costs and
financial results will be available in August 2022; that the replenishment of spare
parts and minor adjustments to the plant are expected to further
improve mill availability for the first quarter of 2022 and beyond;
that we expect to be running at or above nameplate capacity for the
foreseeable future, and that we are optimistic that improvements in
recoveries can be made thereafter; now that the gravity circuit is
operating continuously it is expected to improve recoveries and
reduce processing costs of the high-grade mineralization; the
additional carbon stripping vessel is expected to increase
stripping capacity in the elution circuit and be operational in Q3
2022; ;and that the Company can operate San Albino
profitably in order to fund exploration of prospective targets on
its district-scale land package. Such forward-looking information
is subject to a variety of risks and uncertainties which could
cause actual events or results to differ materially from those
reflected in the forward-looking information, including, without
limitation, the risk that the expected improvements noted will not
be completed in the timeframes expected and/or will lead to the
improvements expected; that the Company is not successful in
operating San Albino profitably and/or funding its exploration of
prospectus targets on its district-scale land package; political
risks and uncertainties involving the Company's exploration
properties; the inherent uncertainty of cost estimates and the
potential for unexpected costs and expense; commodity price
fluctuations and other risks and uncertainties as disclosed in the
Company's public disclosure filings on SEDAR at www.sedar.com. Such
information contained herein represents management's best judgment
as of the date hereof, based on information currently available and
is included for the purposes of providing investors with the
Company's expectations regarding the Company's Q2 2022 production
results at San Albino gold project, and may not be appropriate for
other purposes. Mako does not undertake to update any
forward-looking information, except in accordance with applicable
securities laws.
Neither the TSX Venture Exchange nor its Regulation Services
Provider (as that term is defined in the policies of the TSX
Venture Exchange) accepts responsibility for the adequacy or
accuracy of this release.
View original content to download
multimedia:https://www.prnewswire.com/news-releases/mako-mining-provides-q2-2022-production-results-301589875.html
SOURCE Mako Mining Corp.