MINERAL AND FINANCIAL
INVESTMENTS LIMITED
Investment Update: Ascendant
/ Redcorp Report Significant
Metallurgical Improvements at The Lagoa Salgada VMS Project,
Portugal
HIGHLIGHTS:
· Results demonstrate ability
to produce saleable Zinc and Lead concentrates from the Primary
Massive Sulphide domain.
· Significant improvement in
Zinc recoveries (+13% increase) and concentrate grades (+22%
increase) compared to the Feasibility Study.
· Metallurgical results,
completed at coarser grind sizes supporting simplified flow sheet
and lower capital and operating costs relative to the Feasibility
Study ("FS").
· Demonstrated potential to
lower operating and capital costs relative to the current FS by
using a proven flotation reagent suite, simplified flowsheet, and
coarser primary grind.
· Further improvement
anticipated from additional ongoing metallurgical optimization test
work.
Camana Bay, Cayman Islands - 10 April 2024 -
Mineral and Financial Investments Limited
(LSE-AIM: MAFL) ("M&F" "MAFL" or the "Company") is
pleased to provide an update on its investments in Redcorp
Empreedimentos Mineros Lda. ("Redcorp") and Ascendant Resources Inc.
("Ascendant") which are
developing the Lagoa Salgada Polymetallic Project in Portugal (the
Project). The Project is
managed by Ascendant. M&F owns a conditional 20% carried
interest in Redcorp and Ascendant owns the balance (please see the
announcement dated 28 November 2022 for further details). Redcorp
has provided an update on the optimization
metallurgical test program on the primary massive sulphides ("PMS")
domain at Lagoa Salgada. The Massive Sulphides are the highest
margin domain and a large value driver of NPV for the Lagoa Salgada
Project. Bench scale metallurgical testing on composite samples
from the PMS ore body were completed by Maelgwyn Metallurgical
Laboratories (South Africa) with oversight from Minepro Solutions
(Spain) and DRA Global (South Africa).
Following completion of the July
2023 43-101 Feasibility Study ("FS"), Redcorp/Ascendant initiated
an optimization program for metallurgical performance to improve
metal recoveries, concentrate grades and characterization of the
deleterious elements to enhance the revenue potential for its Lagoa
Salgada Project. The initial phase of the optimization program has
been focused on the Primary Massive Sulphide mineralization from
its Venda Nova North Sector, as this zone is the major revenue
contributor for the project and is exploited early in the mine
life. In addition to the metallurgical work, Redcorp
continues to progress its environmental permitting activities and
expects to be granted the permit in Q3/24 which would position
Lagoa Salgada as the next mine ready project on the Iberian Pyrite
belt.
Jacques Vaillancourt, President
& CEO of M&F Investments Ltd. offered the following comment
- "This is a very exciting step
forward for the Lagoa Salgada project. The metallurgical test work
optimization program carried out on the zinc and lead sulphide
dominant mineralisation (PMS) has returned exceptional recoveries
and grades via a simplified and straightforward flotation process.
It compares favourably to current zinc and lead producers and is
positioned at the higher end of benchmarks for the Iberian Pyrite
Belt. Furthermore, these recoveries have been achieved at coarse
grind sizes with an industrially proven reagent suite supporting a
simple and conventional process flowsheet that will potentially
result in lower capital and operating costs to those typically
observed in Iberian Pyrite Belt operations of this
scale.
Optimization of metallurgical test works continues for the
remaining ore domains as we complete the optimization program for
the planned updated Feasibility Study of the Lagoa Salgada VMS
project."
KEY METALLURGICAL TEST WORK
HIGHLIGHTS:
·
Results from the optimization phase metallurgical
Locked Cycle flotation testing conducted by Maelgwyn Metallurgical
Lab has achieved:
o Zinc
Concentrates at 43% Zn (+8% points or 22% higher grade than FS
results) with a corresponding Zn recovery of 79% (+9% points or a
13% increase in Zn recovery to concentrate as compared to the FS);
and
o Lead
Concentrates at 24% Pb with a Lead recovery of 53%, from a sample
with comparatively lower contained Pb in feed, confirming the lead
recovery potential demonstrated in the FS testing phase.
· Results demonstrate the potential to produce saleable and
highly marketable Lead and Zinc concentrates from the PMS
domain.
· Demonstrated potential to lower operating and capital costs
relative to the current FS as a result of using a proven flotation
reagent suite, simplified flowsheet, and coarser primary
grind.
· Optimization bench scale test work is ongoing for the
Stockwork domain, where initial open circuit test work has also
demonstrated improved Zinc recovery and concentrate grades, with an
efficient separation of Copper and Lead for discrete concentrate
production.
· Further optimisation work on the Gossan and Transition domains
to commence shortly.
Metallurgical Test Update
The recent metallurgical testing on
a composite sample from the PMS ore body at Lagoa Salgada was
conducted by Maelgwyn Laboratories, with oversight from Minepro and
DRA Global. Composite head grades are presented in Table
1.
PMS COMPOSITE SAMPLE CHEMICAL
ASSAYS
(Table
1)
|
Cu (%)
|
Pb (%)
|
Zn (%)
|
Fe (%)
|
Ag (ppm)
|
As (ppm)
|
Bi (ppm)
|
Cd (ppm)
|
Hg (ppm)
|
Sb (ppm)
|
PMS Composite Sample
|
0.25
|
2.84
|
4.47
|
39.00
|
54.9
|
15,961.3
|
85.2
|
224.0
|
423.0
|
589.0
|
Through the implementation of an
optimized circuit configuration, along with a new reagent suite and
coarser primary grinding, the test work has yielded enhanced Zinc
concentrate grades and recoveries. Additionally, it has showcased
the potential to streamline the process flow sheet, decrease
grinding size, and diminish penalty elements. These modifications
are anticipated to lead to cost savings in operations owing to a
simplified process compared to the feasibility study.
Seven flotation tests were carried
out in open circuit, alongside two locked cycle tests, utilizing
the described composite sample. The most successful open circuit
test identified the circuit configuration and reagent regimes for
the locked cycle tests, with performance metrics outlined in Table
2 below:
HIGHLIGHTED METALLURGICAL
RESULTS
(Table
2)
|
July 43-101 Feasibility
Study
|
Latest Test
Results
|
PMS
Results
|
Zn
Concentrate
|
Pb
Concentrate
|
Zn
Concentrate
|
Pb
Concentrate*
|
Primary grind Size
(microns)
|
29
|
29
|
30
|
45
|
Regrind Size (microns)
|
15
|
7
|
15
|
10
|
Grade in Concentrate (%)
|
35%
|
30%
|
43%
|
24%
|
Primary Metal Recovery (%)
|
70%
|
60%
|
79%
|
53%
|
The Zinc circuit performance
indicates that a concentrate with saleable grade can be produced
with a recovery ranging around 79%. Based
upon the calculated grade/recovery curves a concentrate grade +45%
Zinc with slightly lower recoveries is expected to be achieved at
an industrial scale. Additionally,
selectivity and cleaning have notably improved compared to previous
works, leading to lower penalties content. The Zinc concentrate now
exhibits arsenic levels below 1.5% and antimony levels in the range
of 500 ppm (0.05%). Mercury grades are awaiting confirmation as the
reconstructed head grade reveal a lower mercury concentration than
the initial head grade sample analysis.
Lead concentrates at 24% Pb with a
lead recovery of 53% align with previous works completed for the
FS, as the head grade of the current composite sample exhibits
lower contained metal (1% less Pb content than the FS sample),
confirming the lead recovery potential demonstrated in the FS
testing phase. However, these results have been achieved at bench
scale only and there can be no guarantee at that stage that these
results will be achieved on a larger scale. Additional testing on
the remaining orebodies is currently underway, with completion of
the Stockworks testing expected in the next few weeks and the
results for the remaining lesser valued domains expected to be
incorporated into a planned updated Feasibility Study scheduled
towards Q3 of this year.
Review of Technical Information
The scientific and technical
information in this press release has been reviewed and approved
by Joao Barros, BSc (Engineering), MSc (Geology),
who has more than 18 years of relevant experience in the field of
activity concerned. Mr. Barros is a Member of the Portuguese
Engineers Association. Mr. Barros is employed by Redcorp
Empreedimentos Mineiros, Lda., a 50% owned subsidiary of M&FI,
and has consented to the inclusion of the material in the form and
context in which it appears.
The scientific and technical
information contained in this release in relation to metallurgical
test work has been approved and verified by Mr. David Castro López
(MIMMM), who serves as Process Engineer at Minepro Solutions and is
a "Qualified Person" in accordance with National Instrument 43-101
- Standards of Disclosure for Mineral Projects.
FOR MORE INFORMATION:
Jacques Vaillancourt, Mineral &
Financial Investments Ltd. +44
780 226 8247
Katy Mitchell and Sarah Mather, WH
Ireland
Limited
+44 207 220 1666
Jon Belliss, Novum Securities
Limited
+44 207 382 8300
The information contained within
this announcement is deemed by the Company to constitute inside
information as stipulated under the Market Abuse Regulations (EU)
No. 596/2014 (MAR) as in force in the United Kingdom pursuant to
the European Union (Withdrawal) Act 2018. Upon the publication of
this announcement via Regulatory Information Service (RIS), this
inside information is now considered to be in the public
domain.