DENVER, Jan. 24, 2018 /PRNewswire/ -- Vista Gold Corp.
("Vista" or the "Company") (NYSE American and TSX: VGZ) today
announced the positive results of an updated preliminary
feasibility study (the "PFS") for its Mt Todd gold project ("Mt
Todd" or the "Project") in Northern Territory, Australia. The
PFS is based on the results of a comprehensive review of all
aspects of the Project and the re-design of elements of the process
flow sheet, incorporating automated sorting and grinding circuit
design changes in a 50,000 tonne per day ("tpd") project. The
process improvement efforts have resulted in reduced operating
costs, increased gold recovery and higher gold production at Mt
Todd. Management of Vista believes that the design changes
have allowed Vista to achieve a significant improvement in the
Project's economics at the current gold price. The PFS was authored
by Tetra Tech Inc. with Mine Development Associates, Resource
Development Inc., Proteus EPCM Engineers (a Tetra Tech Company),
and POWER Engineers, Inc. Unless otherwise specified, all $
amounts in this press release are expressed in US$.
Highlights of the updated PFS include:
- Estimated proven and probable reserves of 5.85 million ounces
of gold (221.0 million tonnes at 0.82 g Au/t) at a cut-off grade of
0.40 g Au/t, a decrease of 0.9% from the Company's May 2013 PFS(1);
- Average annual production of 382,211 ounces of gold per year
over the life of the Project, including average annual production
of 479,450 ounces of gold per year during the first five years of
operations;
- Life of mine average cash costs of $645 per ounce, including average cash costs of
$571 per ounce during the first five
years of operations;
- A 13 year operating life;
- Initial capital requirements of $839
million; and
- After-tax NPV5% of $679.0
million and IRR of 20.5% at a $1,300 per ounce gold price with a $0.80:AUD1.00 exchange rate.
(1)
|
See Cautionary Note
to United States Investors below.
|
Vista's President and CEO, Frederick H.
Earnest, commented, "In 2016, we began an effort to review
all aspects of the Mt Todd development plan, focused on improving
the economics of the Mt Todd gold project. The results of
this updated PFS demonstrate that Mt Todd is a robust project at
today's gold price and foreign exchange rate. We believe it
is a world class project that enjoys long-standing government and
community support. As we announced earlier this week, we have
received the last major environmental permit for the Project.
We believe this environmental authorization, together with the PFS
results that we are announcing today provide a solid foundation for
continued advancement of Mt Todd and an improved valuation for the
Vista shareholder."
He added, "Through the comprehensive testing and design work
completed over the past 18 months, we have significantly improved
Mt Todd. The incorporation of automated sorting technology
enabled us to improve the grade and reduce the quantity of feed to
the newly designed grinding circuit. By using the excess capacity
in the high pressure grinding roll ("HPGR") crushing circuit, and
changing to a more efficient 2-stage grinding circuit, we are able
to economically grind to 60 microns and achieve an expected gold
recovery of 86.4% (net of solution losses). As a result, gold
recovery is expected to increase 4.1% net of sorting losses.
The reduced feed to the grinding circuit and efficiencies in the
design of the grinding circuit result in lower operating costs, in
part due to a 6% reduction in required power. The combination
of increased gold recovery, higher gold production, and reduced
power consumption, results in an economically robust, advanced
stage gold development project with a 20.5% after-tax IRR at a
$1,300 gold price."
Vista's senior management team is attending the AME Mineral
Exploration Roundup January 24-25,
2018 in Vancouver and will
be available to discuss these results at the conference.
A conference call and webcast to discuss highlights of the PFS will
be held Tuesday, January 30, 2018 at
2:00 pm MST. Call-in
details are located at the end of this release.
Jessica Spriet, Rex Bryan, and Erik
Spiller on behalf of Tetra Tech, Thomas Dyer, on behalf of Mine Development
Associates, Deepak Malhotra, on
behalf of Resource Development Inc., and Zvon Ponos, on behalf of Proteus EPCM Engineers,
all independent Qualified Persons as defined by Canadian National
Instrument 43-101 ("NI 43-101"), prepared or supervised the
preparation of the information that forms the basis for the
scientific and technical information disclosed herein and they have
reviewed this press release and consented to its release. Dr.
Deepak Malhotra has verified the
metallurgical testing program and data in respect of the process
improvements. For additional information on data
verification, quality assurance and control, key assumptions and
other matters relating to the Project, see Vista's Annual Report
Form 10-K as filed on February 22,
2017.
Highlights
Highlights of the PFS are presented in the table
below.
50,000 tpd @
$1,300/oz Au
|
Years
1-5
|
Life of Mine
("LOM")
(13 years)
|
|
Annual
Average
|
Total
|
Annual
Average
|
Total
|
Average Milled Grade
(g Au/tonne)
|
0.98
|
0.82
|
Payable Gold (000's
ozs)
|
479
|
2,397
|
382
|
4,956
|
Gold
Recovery
|
86.4%
|
85.8%
|
Cash Costs
($/oz)
|
$571
|
$645
|
Strip Ratio
(waste:ore)
|
2.83
|
2.52
|
Initial Capital ($
millions)
|
$839
|
After-tax Payback
(Production Years)
|
3.2
|
Pre-tax
NPV5% ($ millions)
|
$1,178
|
After-tax
NPV5% ($ millions)
|
$679
|
IRR (Pre-tax /
After-tax)
|
27.3% /
20.5%
|
Note: Economics
presented using $1,300/oz gold and a flat $0.80 USD : $1.00 AUD
exchange rate and assumes deferral of certain Territory tax
obligations as well as realization of equipment salvage values at
the end of the mine life.
|
Project Economics
The following table provides additional details of the Project's
after-tax economics at variable gold prices and Australian dollar
assumptions.
Foreign
Exchange
(US$/AUD)
|
Gold
Price
|
$1,100
|
$1,200
|
$1,300
|
$1,400
|
$1,500
|
IRR
|
NPV5
|
IRR
|
NPV5
|
IRR
|
NPV5
|
IRR
|
NPV5
|
IRR
|
NPV5
|
0.70
|
15.9%
|
$439
|
20.5%
|
$632
|
24.9%
|
$825
|
29.1%
|
$1,016
|
33.2%
|
$1,208
|
0.75
|
13.8%
|
$366
|
18.3%
|
$559
|
22.6%
|
$752
|
26.8%
|
$944
|
30.8%
|
$1,136
|
0.80
|
11.9%
|
$292
|
16.3%
|
$486
|
20.5%
|
$679
|
24.6%
|
$872
|
28.6%
|
$1,063
|
0.85
|
10.1%
|
$222
|
14.3%
|
$412
|
18.5%
|
$606
|
22.5%
|
$799
|
26.4%
|
$991
|
0.90
|
8.3%
|
$150
|
12.5%
|
$339
|
16.6%
|
$532
|
20.6%
|
$726
|
24.4%
|
$918
|
Note: Changes in
Foreign Exchange rates are only applied to operating costs and not
applied to either initial or sustaining capital
costs.
|
Capital Costs
Key capital expenditures for initial and sustaining capital
requirements are identified in the following table.
Capital
Expenditures ($Thousands)
50,000 tpd
|
Initial
Capital
|
Sustaining
Capital
|
Mining
|
$144,278
|
$385,207
|
Process
Plant
|
$340,768
|
$22,992
|
Project
Services
|
$117,744
|
$82,857
|
Project
Infrastructure
|
$23,263
|
$0
|
Site Establishment
& Early Works
|
$19,723
|
$0
|
Management,
Engineering, EPCM Services
|
$85,941
|
$0
|
Preproduction
Costs
|
$11,127
|
$0
|
Contingency
|
$95,988
|
$3,189
|
Sub-Total5
|
$838,832
|
$494,245
|
Asset Sale and
Salvage
|
$0
|
($141,788)
|
Total
Capital
|
$838,832
|
$352,457
|
Total Capital per
payable ounce gold
|
$169
|
$71
|
Note: may not add
due to rounding.
|
Operating Costs
The following table presents a breakdown of operating
costs. The Project includes a 70MW power plant in the initial
capital. Power is anticipated to be generated by gas-fired
reciprocating engines (nominal 10MW capacity). The Project
consumes all power generated during the operating life.
Self-generated power creates significant savings in operating costs
compared to a grid-sourced power solution. During the four
years of reclamation and closure, the PFS assumes Vista will
continue generating power and will sell 20MW of power into the
Northern Territory electrical grid, for which there is a known
market and indicative purchase rates have been provided by the
government-owned utility.
Operating Cost –
50,000 tpd
|
First 5
Years
|
LOM
Cost
|
|
Per tonne
processed
|
Per ounce
|
Per tonne
processed
|
Per ounce
|
Mining
|
$7.06
|
$260.23
|
$6.08
|
$270.97
|
Processing
|
$6.66
|
$245.30
|
$6.72
|
$299.50
|
Site General and
Administrative
|
$1.18
|
$43.43
|
$1.22
|
$54.40
|
Jawoyn
Royalty
|
$0.35
|
$12.93
|
$0.29
|
$12.91
|
Water
Treatment
|
$0.07
|
$2.74
|
$0.09
|
$3.58
|
Tailings
Management
|
$0.08
|
$2.91
|
$0.08
|
$3.51
|
Refining
Costs
|
$0.09
|
$3.13
|
$0.07
|
$3.11
|
Power
Credit
|
0
|
$0.00
|
-0.062
|
-2.67
|
Total Cash
Costs
|
$15.49
|
$570.68
|
$14.48
|
$645.33
|
Note: Jawoyn
Royalty and refinery costs calculated at $1,300 per ounce
gold. May not add due to rounding.
|
Mining and Production
The mine plan contains 207.7 million tonnes of ore mined from
the Batman open pit plus 13.4 million tonnes of ore from the
existing heap leach pad that is processed through the mill at the
end of the mine life. The mine plan contemplates that
together, 221.0 million tonnes of ore containing 5.848 million
ounces of gold at an average grade of 0.82 g Au/t are to be
processed over the 13-year operating life of the Project.
Total gold recovered is expected to be 4.956 million ounces.
Average annual gold production over the life of the Project is
expected to be 382,211 ounces, averaging 479,450 ounces during the
first five years of operations, with 582,032 ounces produced in the
first year of operations. Commercial production is
anticipated to begin after two years of construction and
commissioning.
Estimated Annual Production
The table below highlights the production schedule.
Years
|
Ore Mined
(kt)
|
Waste Mined
(kt)
|
Strip
Ratio (W:O)
|
Milled Ore
(kt)
|
Milled Grade
(g/t)
|
Contained
Ounces
(kozs)
|
Mill
Production (kozs)
|
-1
|
10,437
|
16,850
|
1.61
|
-
|
-
|
-
|
-
|
1
|
13,174
|
27,284
|
2.07
|
17,750
|
1.19
|
682
|
582
|
2
|
23,679
|
32,692
|
1.38
|
17,750
|
0.83
|
473
|
404
|
3
|
20,112
|
74,220
|
3.69
|
17,799
|
0.95
|
543
|
463
|
4
|
34,149
|
54,933
|
1.61
|
17,750
|
1.00
|
570
|
487
|
5
|
10,843
|
98,928
|
9.12
|
17,750
|
0.95
|
542
|
462
|
6
|
6,427
|
71,318
|
11.10
|
17,750
|
0.56
|
317
|
270
|
7
|
10,429
|
53,987
|
5.18
|
17,799
|
0.55
|
317
|
270
|
8
|
14,965
|
43,800
|
2.93
|
17,750
|
0.61
|
349
|
298
|
9
|
22,633
|
33,942
|
1.50
|
17,750
|
0.78
|
448
|
382
|
10
|
37,943
|
14,990
|
0.4
|
17,750
|
1.24
|
709
|
605
|
11
|
2,895
|
47
|
0.02
|
17,799
|
0.84
|
481
|
411
|
12
|
-
|
-
|
-
|
17,750
|
0.49
|
278
|
224
|
13
|
-
|
-
|
-
|
7,895
|
0.54
|
137
|
98
|
Total
|
207,687
|
522,990
|
2.52
|
221,041
|
0.82
|
5,848
|
4,956
|
Note: May not add
due to rounding. Total milled ore includes material from the
heap leach pad that is planned to be processed at the end of the
mine life.
|
Project Mineral Reserves and Resources
The table below illustrates the updated reserve and resource
estimate for the Project. The effective date of the Batman
and Quigleys deposits resource estimates is January 24, 2018. The effective date of the
heap leach resource estimate is July
9, 2014.
Mt. Todd Gold
Project Reserves – 50,000tpd, 0.40 g Au/t cut-off and $1,250 per
ounce gold
|
|
Batman
Deposit
|
Heap Leach
Pad
|
Quigleys
Deposit
|
Total
|
|
Tonnes
(000s)
|
Grade
(g/t)
|
Contained Ounces
(000s)
|
Tonnes
(000s)
|
Grade
(g/t)
|
Contained Ounces
(000s)
|
Tonnes
(000s)
|
Grade
(g/t)
|
Contained Ounces
(000s)
|
Tonnes
(000s)
|
Grade
(g/t)
|
Contained Ounces
(000s)
|
Proven
|
72,672
|
0.88
|
2,057
|
-
|
-
|
-
|
-
|
-
|
-
|
72,672
|
0.88
|
2,057
|
Probable
|
135,015
|
0.82
|
3,559
|
13,354
|
0.54
|
232
|
-
|
-
|
-
|
148,369
|
0.79
|
3,791
|
Proven &
Probable
|
207,687
|
0.84
|
5,616
|
13,354
|
0.54
|
232
|
-
|
-
|
-
|
221,041
|
0.82
|
5,848
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Mt. Todd Gold
Project Resources
|
|
Batman
Deposit
|
Heap Leach
Pad
|
Quigleys
Deposit
|
Total
|
|
Tonnes
(000s)
|
Grade
(g/t)
|
Contained Ounces
(000s)
|
Tonnes
(000s)
|
Grade
(g/t)
|
Contained Ounces
(000s)
|
Tonnes
(000s)
|
Grade
(g/t)
|
Contained Ounces
(000s)
|
Tonnes
(000s)
|
Grade
(g/t)
|
Contained Ounces
(000s)
|
Measured
|
77,725
|
0.88
|
2,191
|
-
|
-
|
-
|
457
|
1.27
|
19
|
78,182
|
0.88
|
2,210
|
Indicated
|
200,112
|
0.80
|
5,169
|
13,354
|
0.54
|
232
|
5,743
|
1.12
|
207
|
219,209
|
0.80
|
5,608
|
Measured &
Indicated
|
277,837
|
0.82
|
7,360
|
13,354
|
0.54
|
232
|
6,200
|
1.13
|
225
|
297,391
|
0.82
|
7,818
|
Inferred
|
61,323
|
0.72
|
1,421
|
-
|
-
|
-
|
1,600
|
0.84
|
43
|
62,923
|
0.72
|
1,464
|
Note: Measured
& indicated resources include proven and probable
reserves. Batman and Quigleys resources are quoted at a 0.40g
Au/t cut-off grade. Heap Leach resources are the average
grade of the heap, no cut-off applied. Economic analysis
conducted only on proven and probable reserves. Rex Bryan of
Tetra Tech is the Qualified Person responsible for the geologic
resource estimates. Thomas Dyer of Mine Development
Associates is the Qualified Person responsible for developing
reserves for the Batman deposit. Deepak Malhotra of Resource
Development Inc. is the Qualified Person responsible for the
metallurgical data and program, and for developing reserves for the
heap leach. See Cautionary Note to United States Investors
below.
|
Project Description
Gold mineralization in the Batman deposit at the Project occurs
in sheeted veins within silicified
greywackes/shales/siltstones. The Batman deposit strikes
north-northeast and dips steeply to the east. Higher grade
zones of the deposit plunge to the south. The core zone is
approximately 200-250 meters wide and 1.5 km long, with several
hanging wall structures providing additional width to the
deposit. Mineralization is open at depth as well as along
strike, although the intensity of mineralization weakens to the
north and south along strike.
In addition to the Mt Todd mining licenses, Vista controls over
1,100 sq. km of contiguous exploration licenses – all of which are
located at the southeast end of the Pine Creek District.
Various gold targets have been identified in early-stage, grass
roots exploration programs along the Cullen-Australis and
Batman-Driffield structural corridors, the latter of which is the
host to the Batman deposit. To-date, Vista's exploration
efforts have primarily focused on the Batman deposit. The
Company is now in a position to expand its exploration activities
in search of new deposits.
The Project is designed to be a conventional, owner-operated,
large open-pit mining operation that will utilize large-scale
mining equipment in a blast/load/haul operation. Ore is
planned to be processed in a large comminution circuit consisting
of a gyratory crusher, two cone crushers, two HPGR crushers, and
primary grinding by two ball mills and secondary grinding by six
horizontal IsaMills as discussed in greater detail below.
Vista plans to recover gold in a conventional carbon-in-pulp
("CIP") recovery circuit.
Metallurgy, Processing and Infrastructure
Vista has completed extensive metallurgic test work that was
announced in separate press releases dated May 22, 2013, July 21,
2017 and November 24,
2017.
Vista's metallurgic test work programs support: (1) ore hardness
estimates at the Batman deposit that are consistent and do not
change at depth; (2) the selection of HPGR, automated sorting and
2-stage grinding technologies as part of the comminution circuit;
(3) estimated gold recovery rates based on optimized grind size and
leach conditions; and (4) the processing of material from the
historic heap leach pad at the end of the proposed mine life.
Significant improvements to the Project have been achieved
through design changes in the comminution circuit. Vista
plans to screen the HPGR crusher product at 16 mm (5/8") and use
automated sorting technology (both x-ray transmission and laser) to
remove the material that is sub-economic. Testing indicates
that approximately 10% of the run-of-mine plant feed can be
eliminated with only a 1.3% gold loss using automated
sorting. The excess capacity in the HPGR circuit will be
employed to create a final product that is nominally 3.5 mm (1/8")
or, approximately 50% smaller than previously planned. This
material will be wet screened and then classified to provide feed
to the redesigned primary and secondary grinding circuits.
The Company has selected smaller, more energy efficient ball mills
for the primary grinding circuit and horizontal IsaMills for the
secondary grinding circuit. Together, these mills are
expected to efficiently produce a final product that is nominally
60 microns in size (a 33% reduction from previous studies).
Leaching tests conducted at this finer grind size indicated that an
overall gold recovery of 86.4% (net of solution losses) can be
expected, a significant improvement from the previous 81.7%
recovery. This results in a 4.1% increase in total gold
production (net of sorting losses).
The robust comminution circuit is designed to process material
with an average bond-work index 5% in excess of actual rock
hardness based on the test work completed. Gold will be
recovered through a traditional CIP circuit. Recovery rates
are based on the results of 41 tests recently completed at present
design conditions in addition to the tests completed in 2013.
Because the Project was an operating mine, infrastructure exists
that reduces initial capital expenditure and significantly reduces
capital risk related to infrastructure construction, which has been
a major source of capital overruns in the mining industry over the
last decade. Existing mining infrastructure items
include:
- an existing tailings storage facility that will receive two
raises and is expected to contain 62 million tonnes of material
processed;
- an existing fresh water storage reservoir that will receive a
two-meter dam raise and will harvest stormwater sufficient to
provide process water for year-round operations;
- a natural gas pipeline at site that can supply sufficient
natural gas to meet the Project's energy requirements and would
save considerably on project operating costs compared to
grid-supplied power;
- a paved road to site;
- current electrical connection to the Northern Territory
electric grid; and
- process plant location has been cleared and graded, resulting
in reduced earthworks costs due to the process plant location being
the same as the previous process plant.
Other benefits of Mt Todd's Northern Territory location
include:
- the Stuart highway – the main North / South highway in the
Northern Territory is less than 15 km from the project site;
- rail line parallel to the Stuart highway; and
- the regional center of Katherine (population approximately
12,000) less than 60 km from site and the Territory capital of
Darwin less than 300 km from site, which has port
access.
Vista continues to work with the communities of Katherine and
Pine Creek to develop a community-based project as opposed to the
more typical fly-in, fly-out project, which is generally more
expensive and limits the economic benefits of projects to local
communities.
Opportunities for Additional Project Improvement
The PFS uses a natural gas price derived from east coast gas
pricing. Historically the Northern Territory gas grid was
isolated from the national market and pricing was based on local
supply and demand. With the construction of the Northern Gas
Pipeline (presently in progress), producers of natural gas will be
able to sell gas to higher value markets on the east coast of
Australia. Presently there is little demand for NT gas on the
east coast. Vista has used a natural gas price derived from
the east coast market. The Company believes that there is
significant opportunity to achieve a lower gas price when it is
able to commit to the delivery of gas.
The power plant, as presently designed, is situated at the mine
site. This results in an AUD 0.60 per GJ pipeline charge for
transportation of gas in a spur line. The Company has
completed preliminary evaluations to consider moving the location
of the power plant to a location near the main NT gas pipeline to
eliminate this sustained operating cost. Additional capital
would be required, but reduced operating costs could be
achieved. The Company may elect this option after further
evaluation.
The Company has a known resource at the Quigleys deposit.
Additional drilling and metallurgical testing is required to
develop mine plans and ultimately convert part of the Quigleys
resource to either proven or probable reserves. The estimated
grade of the Quigleys deposit is higher than the estimated average
grade of the Batman deposit and could provide a source of
higher-grade feed in the mid years of the Project when higher
stripping in encountered and the average grade of feed to the plant
is expected to decrease.
Conference Call Details
A conference call and webcast to discuss highlights of
the PFS will be held Tuesday, January 30,
2018 at 2:00 pm
MST. A presentation accompanying the conference
call will be made available on the Company's website prior to the
conference call.
Toll-free in North America:
888-378-4413
International: 647-792-1280
Confirmation Code: 8526874
This call will also be web-cast and can be accessed at the
following web location:
http://event.on24.com/r.htm?e=1591324&s=1&k=D07C2A33BFD459430C3091BC1FBE6A04
This call will be archived and available at www.vistagold.com
after January 30, 2018. Audio
replay will be available for 21 days by calling toll-free in
North America: 888-203-1112,
passcode 8526874.
Detailed Report
A NI 43-101 Technical Report will be filed on SEDAR within 45
days and will be available on our website at that time. As
part of the sensitivity analysis of the Project, Vista intends to
complete and present the results of an alternate 33,000 tpd project
as part of the NI 43-101 report.
About Vista Gold Corp.
The Company is a well-funded gold project developer. Our
principal asset is our flagship Mt Todd gold project in Northern
Territory, Australia. Mt Todd is the largest known
undeveloped gold project in Australia.
For further information, please contact Connie Martinez at (720) 981-1185.
For more information about our projects, including technical
studies and resource estimates, please visit our website at
www.vistagold.com.
Forward Looking Statements
This press release contains forward-looking statements within
the meaning of the U.S. Securities Act of 1933, as amended, and
U.S. Securities Exchange Act of 1934, as amended, and
forward-looking information within the meaning of Canadian
securities laws. All statements, other than statements of
historical facts, included in this press release that address
activities, events or developments that Vista expects or
anticipates will or may occur in the future, including such things
as, the Company's continued work on the Mt Todd gold project,
process improvements will result in lower operating costs, reduced
power consumption, increased gold recovery and higher gold
production, estimates of reserves and resources, projected project
economics, including anticipated production, average cash costs,
before and after-tax NPV, IRR, capital requirements and
expenditures, gold recovery after-tax payback, operating costs,
average tonne per day milling, mining methods procedures, recovery,
project design, life of mine, the Project is robust and world
class, the continued advancement of Mt Todd, the improved valuation
for shareholders, the Project is an advanced stage development
project, estimated gold recovery, average annual production
overtime, commencement of commercial production, timing for
construction and commissioning, exploration of new deposits at Mt
Todd, size of final product through the HPGR crusher, potential
costs or savings related to gas price, ability to convert Quigley's
estimate to proven or probable reserves, grade of minerals at the
Quigley deposit, timing for and completion of PFS and other such
matters are forward-looking statements and forward-looking
information. The material factors and assumptions used to develop
the forward-looking statements and forward-looking information
contained in this press release include the following: the
accuracy of the results of the PFS, mineral resource and reserve
estimates, and exploration and assay results, the terms and
conditions of our agreements with contractors and our approved
business plan, the anticipated timing and completion of a
feasibility study on the Project; the anticipated receipt of
required permits; no change in laws that materially impact mining
development or operations of a mining business, the potential
occurrence and timing of a production decision; the anticipated
gold production at the Project; the life of any mine at the
Project; all economic projections relating to the Project,
including estimated cash cost, NPV, IRR, and initial capital
requirements; and Vista's goal of becoming a gold producer.
When used in this press release, the words "optimistic,"
"potential," "indicate," "expect," "intend," "plans," "hopes,"
"believe," "may," "will," "if," "anticipate," and similar
expressions are intended to identify forward-looking statements and
forward-looking information. These statements involve known
and unknown risks, uncertainties and other factors which may cause
the actual results, performance or achievements of Vista to be
materially different from any future results, performance or
achievements expressed or implied by such statements. Such
factors include, among others, uncertainty of resource estimates,
estimates of results based on such resource estimates; risks
relating to cost increases for capital and operating costs;
risks related to the timing and the ability to obtain the necessary
permits, risks of shortages and fluctuating costs of equipment or
supplies; risks relating to fluctuations in the price of gold; the
inherently hazardous nature of mining-related activities; potential
effects on Vista's operations of environmental regulations in the
countries in which it operates; risks due to legal proceedings;
risks relating to political and economic instability in certain
countries in which it operates; as well as those factors discussed
under the headings "Note Regarding Forward-Looking Statements" and
"Risk Factors" in Vista's Annual Report Form 10-K as filed on
February 22, 2017 and other documents
filed with the U.S. Securities and Exchange Commission and Canadian
securities regulatory authorities. Although Vista has
attempted to identify important factors that could cause actual
results to differ materially from those described in
forward-looking statements and forward-looking information, there
may be other factors that cause results not to be as anticipated,
estimated or intended. Except as required by law, Vista
assumes no obligation to publicly update any forward-looking
statements or forward-looking information; whether as a result of
new information, future events or otherwise.
Cautionary Note to United States Investors
The United States Securities and Exchange Commission ("SEC")
limits disclosure for U.S. reporting purposes to mineral deposits
that a company can economically and legally extract or produce.
This press release uses the terms "Proven reserves" and "Probable
reserves". Reserve estimates contained in this press release
are made pursuant to NI 43-101 standards in Canada and do not represent reserves under SEC
Industry Guide 7 standards. Under SEC Industry Guide 7
standards, a "final" or "bankable" feasibility study is required to
report reserves, the three-year historical average price is used in
any reserve or cash flow analysis to designate reserves and all
necessary permits and government approvals must be filed with the
appropriate governmental authority. Additionally, this press
release uses the terms "Measured resources", "Indicated resources",
and "Measured & Indicated resources". We advise U.S.
investors that while these terms are Canadian mining terms as
defined in accordance with NI 43-101, such terms are not recognized
under SEC Industry Guide 7 and normally are not permitted to be
used in reports and registration statements filed with the
SEC. Mineral resources described in this press release have a
great amount of uncertainty as to their economic and legal
feasibility. The SEC normally only permits issuers to report
mineralization that does not constitute SEC Industry Guide 7
compliant "reserves" as in-place tonnage and grade, without
reference to unit measures. The term "contained gold ounces" used
in this press release is not permitted under the rules of the
SEC. "Inferred resources" have a great amount of uncertainty
as to their existence, and great uncertainty as to their economic
and legal feasibility. It cannot be assumed that any or all
part of an Inferred resource will ever be upgraded to a higher
category. U.S. Investors are cautioned not to assume that any
part or all of mineral deposits in these categories will ever be
converted into SEC Industry Guide 7 reserves.
View original
content:http://www.prnewswire.com/news-releases/vista-gold-announces-updated-mt-todd-preliminary-feasibility-study-showing-strong-returns-at-us1300-gold-price-300587262.html
SOURCE Vista Gold Corp.