African Metals Corporation (TSX VENTURE:AFR) (FRANKFURT:OWW) ("AFR") reports a
delay in progress of the construction of the Dense Media Separation (DMS) plant,
spirals bank and ancillary equipment (the DMS Plant) at the Luisha South
Project. 


Construction 

M&J Investments Sprl ("M&J") have progressed construction of the DMS Plant at
the Luisha South Project (Photo 1). The feed bin, primary crusher, control units
and generator are in place, and assembly of the spirals bank and conveyor belt
modules completed. The placement of the DMS module and scrubber module onto
their respective concrete pads and final positioning of conveyor belt units
between modules was delayed significantly due to prime mover rig availability
and heavy downpours with the onset of the wet season. It is expected that final
assembly of all conveyor belts and electrical fit out will continue into early
January. Site drainage works are ongoing. 


Delays 

The national elections produced delays in assembly of the plant with key
expatriate contractor personnel temporarily leaving the country after reports of
violent confrontations between supporters of presidential candidates. The
personnel returned after the political situation stabilised with the re-election
of Mr. Kabila as President. Seasonal rain storms continued to cause delays in
the concreting and plant assembly programs, with the placement of the DMS module
and scrubber module onto their respective concrete pads delayed for several
weeks due to the lack of availability of a prime mover suitable for towing in
the wet access conditions. 


Nigel Ferguson, CEO and President of African Metals Corp, commented:

"The Company is pleased to report good progress on construction of the DMS plant
despite delays due to the onset of wet season weather and stability concerns
during national presidential elections. The assembly-teams continue to strive to
bring the plant into operation as soon as possible, which is now looking to be
January 2012."


ON BEHALF OF THE BOARD OF DIRECTORS OF AFRICAN METALS CORPORATION 

Nigel Ferguson, President & CEO

To view the photo associated with this press release, please visit the following
link:


http://www.marketwire.com/library/20111230-1230afr1.jpg

This News Release contains forward-looking statements. Forward-looking
statements are statements which relate to future events. These statements are
only predictions and involve known and unknown risks, uncertainties and other
factors that may cause our or our industry's actual results, levels of activity,
performance or achievements to be materially different from any future results,
levels of activity, performance or achievements expressed or implied by these
forward-looking statements. While these forward-looking statements, and any
assumptions upon which they are based, are made in good faith and reflect our
current judgment regarding the direction of our industry, actual results will
almost always vary, sometimes materially, from any estimates, predictions,
projections, assumptions or other future performance suggested herein. Except as
required by applicable law, the Company does not intend to update any of the
forward-looking statements to conform these statements to actual results.


About African Metals Corporation. 

African Metals Corporation (TSX VENTURE:AFR) is a Canadian listed company
focused on the discovery and development of Copper and Cobalt deposits in the
highly mineralized Katanga Copper Belt of the world renowned Africa Copper Belt
in the Democratic Republic of Congo ("DRC").


AFR purchased all the assets of Chevalier Resources Inc. in March 2010 including
a 57% interest in the Luisha South Project contained within licence PEPM 4881,
Katanga Provence, Democratic Republic of the Congo ("DRC") through subsidiaries
incorporated in the DRC. In July AFR negotiated a further 18% interest in the
project with the option to increase the equity interest to 90% based on results.
The project is located 75 kilometres northwest of Lubumbashi, the capital of
Katanga Province and consists of approximately 16.2km2.


The Luisha South Project includes a small historical open pit mine and
associated stockpile and is underlain by Roan Group sediments which host major
Cu-Co deposits in the DRC. The Luisha South ore body was explored between 1923
and 1928 and an oxide deposit with an estimated pre-production tonnage of
approximately 350,000 tonnes at 8.6% Cu was delineated (the resource estimate
non-compliant in terms of NI 43-101). The results of a 2,002 metre RC percussion
drilling program completed by Titan Drilling Sprl in June 2010 enabled the
estimation of a NI 43-101 compliant maiden Inferred Resource of 5.8 Million
tonnes at 1.3% Cu for 75,400 tonnes of contained copper metal and 0.4% Co for
23,200 tonnes of contained cobalt metal (using 0.5% Cu cut-off). See the
technical report of Geosure Exploration & Mining Solutions Pty Ltd, an
independent firm contracted by AFR to prepare the technical report, dated
November 15, 2010 and filed on www.sedar.com on December 2, 2010. Rubaco Sprl
and DrillTek Sprl further combined to complete a total of 1,538.73 metres of
diamond core drilling at the project in January 2011. The results of the
drilling program enabled a re-estimation of the resource to produce a NI 43-101
compliant Inferred Resource of 14.7 Million tonnes at 1.1% Cu for 161,700 tonnes
of contained copper metal and 0.3% Co for 44,100 tonnes of contained cobalt
metal (using a 0.5% Cu cut-off). The revised resource represented an increase of
114% and 90% respectively of the previous contained copper and cobalt metal
estimates. See the technical report of Geosure Exploration & Mining Solutions
Pty Ltd., an independent firm contracted by AFR to prepare the technical report,
dated October 10, 2011 and filed on www.sedar.com on October 17, 2011. 


The Luisha South Project also covers some three kilometres of the Roan Group
strike length which is favorable for Cu-Co mineralization.


Ronald J. Lawrence, MAIG, Vice President - Exploration for the Company and a
qualified person under National Instrument 43-101, has reviewed and approved the
technical information disclosed in this release.


Grafico Azioni Nuventure Resources (TSXV:AFR)
Storico
Da Mag 2024 a Giu 2024 Clicca qui per i Grafici di Nuventure Resources
Grafico Azioni Nuventure Resources (TSXV:AFR)
Storico
Da Giu 2023 a Giu 2024 Clicca qui per i Grafici di Nuventure Resources