(In United States dollars, except where noted otherwise)
TORONTO, Feb. 14, 2019 /PRNewswire/ -- First Quantum
Minerals Ltd. ("First Quantum" or the "Company") (TSX:
FM) today reported comparative earnings1 of
$182 million ($0.26 per share1), net earnings
attributable to shareholders of the Company1 of
$198 million ($0.29 per share) and cash flows from operating
activities of $338 million
($0.49 per share1) for the
three months ended December 31, 2018
("Q4").
For the full year 2018, the Company reports comparative
earnings1 of $487 million
($0.71 per share1), net
earnings attributable to shareholders of the Company1 of
$441 million ($0.64 per share1) and cash flows from
operating activities of $1,980
million ($2.88 per
share1).
FOURTH QUARTER AND FULL YEAR 2018 SUMMARY:
- Operations Delivered Solid Results with Lower Costs
-
- 158,304 tonnes of copper2 produced in Q4:
-
- Record Q4 production at Sentinel of 60,840 tonnes, reflecting
continued improvement quarter over quarter in production and
costs.
- Q4 Unit cost of copper
production3: All-in sustaining cost ("AISC")
= $1.68 per pound; Cash cost ("C1") =
$1.23 per pound; Total cost ("C3") =
$2.04 per pound.
- 605,853 tonnes of copper2 produced for the full
year.
- 2018 full year unit cost of copper production3: AISC
= $1.74 per pound; C1=$1.28 per pound; C3=$2.11 per pound.
- Strong Operating Cash Flows and Continued Liquidity;
Dividend Declared
-
- $338 million of cash flows from
operating activities ($0.49 per
share3) during the quarter, an increase of 67% from the
comparable prior year period.
- $1,980 million of cash flows from
operating activities ($2.88 per
share1) during all of 2018.
- Ended the quarter and year with $788
million in net unrestricted cash and cash equivalents,
$700 million of committed undrawn
facilities and in full compliance with all financial
covenants.
- Final dividend declared of CDN$0.005 in respect of the 2018 year-end; total
dividends for the full year 2018 were CDN$0.01.
- Cobre Panama Project nears completion as of
year-end.
-
- The focus at the Cobre Panama project remains on construction
completion, commissioning of the process plant and commissioning
and ramp-up of the power station. During the quarter, project
pre-strip was completed, engineering and procurement were
essentially completed, and the tailings management facility
earthworks advanced to 87% completion. Construction of the two
power sets was completed in the quarter with commissioning being
well advanced with the reliability and ramp-up program for set 1
completed in January 2019. Set 2 is
in full commissioning with synchronization to the grid having
occurred in January 2019. Extensive process plant
commissioning and testing were ongoing throughout the quarter in
preparation for production. First ore was introduced to the
mill on February 11, 2019. The
project remains scheduled for ramp-up over 2019 and 2020.
- During 2019, Cobre Panama mine is expected to produce 140,000 –
175,000 tonnes of contained copper and by year end be running at an
annualized rate of 72 million tonnes per year ("mtpa"). Limited
copper production is expected in the first half of 2019 while the
commissioning and start-up continues with approximately 80% of
production expected to occur in the second half of the year.
Commercial production will be declared in arrears and is expected
to occur in the final quarter of 2019.
- In 2020, contained copper production of between 270,000-300,000
tonnes is expected as a throughput rate of 85 mtpa is
reached. In 2021, production of approximately 300,000 tonnes
of contained copper is expected, increasing in 2022 to 350,000
tonnes. In 2022, the C1 unit cost of production is estimated at
$1.20 per lb and $1.50 per lb all-in sustaining. Both estimates
are net of an assumed by-product credit principally gold as well as
some molybdenum and silver, of approximately $0.25 per lb. Gold production in 2020 and
2021 is estimated at approximately 100,000 ounces per year.
CEO'S COMMENTS
"2018 was a very important year for the Company with the
development of Cobre Panama nearing completion. We achieved
record production for the year, ahead of target, and in line with
the expected low unit production costs. Much of this was due
to a 17% increase in production at Sentinel," noted Philip Pascall, Chairman and CEO. "Our financial
results for the quarter and the full year reflect this strong
operating performance through the year."
"2019 will be another important year for the Company. With Cobre
Panama starting operation, and the continuing steady production
from our existing mines, we expect significantly higher
output. I appreciate and laud our staff and employees for what
was accomplished in 2018 and look forward to another exciting and
productive year," Mr. Pascall concluded.
OPERATING HIGHLIGHTS
|
|
|
Three months
ended December
31
|
Full year
ended
December 31
|
(U.S. dollars
where applicable)
|
2018
|
2017
|
2018
|
2017
|
|
|
|
|
|
COPPER
|
|
|
|
|
- Production2
(tonnes)
|
158,304
|
154,319
|
605,853
|
573,963
|
- Sales4 (tonnes)
|
156,212
|
151,905
|
596,513
|
580,130
|
|
|
|
|
|
- Cost of
production3:
|
|
|
|
|
o AISC (per
lb)
|
$1.68
|
$1.76
|
$1.74
|
$1.65
|
o C1 (per
lb)
|
$1.23
|
$1.30
|
$1.28
|
$1.23
|
o C3 (per
lb)
|
$2.04
|
$2.16
|
$2.11
|
$2.05
|
- Realized price
(per lb)
|
$2.83
|
$2.50
|
$2.84
|
$2.33
|
|
|
|
|
|
GOLD
|
|
|
|
|
- Production
(ounces)
|
48,039
|
51,904
|
185,414
|
199,736
|
- Sales
(ounces)
|
53,221
|
50,723
|
193,072
|
201,376
|
FINANCIAL HIGHLIGHTS
|
|
|
Three months
ended December
31
|
Full year
ended
December 31
|
(U.S. dollars
millions, except where noted otherwise)
|
2018
|
2017
|
2018
|
2017
|
Sales
revenues
Gross
profit
Net earnings (loss)
attributable to shareholders of the Company
Basic and diluted
earnings (loss) per share
Comparative
EBITDA1
Comparative earnings
(loss)1
Comparative earnings
(loss) per share1
Cash flow from
operating activities
|
1,054
280
198
$0.29
481
182
$0.26
338
|
885
117
(115)
($0.17)
318
(36)
($0.05)
203
|
3,966
978
441
$0.64
1,737
487
$0.71
1,980
|
3,310
335
(316)
($0.46)
1,154
(111)
($0.16)
914
|
1 Net earnings (loss) attributable to shareholders of
the Company has been adjusted to exclude items which are not
reflective of underlying performance to arrive at comparative
earnings (loss). Comparative earnings (loss), comparative earnings
(loss) per share, comparative EBITDA and cash flows per share are
not measures recognized under IFRS and do not have a standardized
meaning prescribed by IFRS. The Company has disclosed these
measures to assist with the understanding of results and to provide
further financial information about the results to investors. Refer
to the "Regulatory Disclosures" section in the MD&A for the
year ended December 31, 2018 for further information.
|
2
Production is presented on a copper
contained basis, and is presented prior to processing through the
Kansanshi smelter.
|
3
AISC, C1 and C3 costs per pound are not
recognized under IFRS. Refer to the "Regulatory Disclosures"
section in the MD&A for the year ended December 31, 2018 for
further information. C1, C3 and AISC costs exclude third-party
concentrate purchased at Kansanshi. C1, C3 and AISC costs for Q3
2018 have been revised from amounts previously disclosed to exclude
the $0.03 per pound impact of third-party concentrate
purchased.
|
4
Copper sales exclude the sale of copper
anode produced from third-party concentrate purchased at Kansanshi.
Sales of copper anode attributable to third-party concentrate
purchases were 5,884 tonnes and 7,349 tonnes for the three months
and year ended December 31, 2018, respectively. Q3 2018 copper
sales have been adjusted to exclude copper anode sales of 1,465
tonnes attributable to third-party concentrate
purchased.
|
Other
- On January 23, 2019, the Company
announced a land slippage at Cobre Las Cruces, and production at
the hydrometallurgical plant was suspended immediately. Prior to
the incident, mine personnel identified a risk and immediately
implemented safety protocols. Following the incident, the pit was
evacuated and no injuries occurred. On February 1, 2019 the production resumed at the
processing plant with the processing of lower grade stockpiled ore
which is expected to continue for the next several months while the
necessary regulatory approvals are obtained to begin the mining of
Phase 6, an area unaffected by the incident.
- On February 6, 2019, the Company
signed a new $2.7 billion Term Loan
and Revolving Credit Facility underwritten by three core
relationship banks. This new Facility replaces the existing
$1.5 billion Revolving Credit
Facility. The new $2.7 billion
Facility (with an accordion feature to increase it up to
$3.0 billion before the end of 2019)
comprises a $1.5 billion Term Loan
Facility and a $1.2 billion Revolving
Credit Facility (which can be upsized to $1.5 billion if the accordion feature is
activated), maturing on December 31,
2022. This financing includes revised financial covenants,
extends the debt maturity profile of the business, demonstrates the
Company's access to a diverse range of capital markets, and
improves the financial flexibility of the Company through the added
liquidity. The Facility will be used for the redemption of the
$1,121 million senior notes due
February 2021 in full, or in part,
and for general corporate purposes.
Production and Cost Outlook
(000's)
|
2019
|
2020
|
2021
|
Total Copper
(tonnes)
|
700 – 735
|
840 – 870
|
820
|
Cobre Panama –
Copper2 (tonnes)
|
140 - 175
|
270 - 300
|
300
|
Copper2
(tonnes) – excluding Cobre Panama
|
560
|
570
|
520
|
Gold (ounces) –
excluding Cobre Panama
|
185
|
180
|
170
|
Zinc
(tonnes)
|
12
|
2
|
-
|
Production guidance for Las Cruces reflects the land slippage in
January 2019, with lost production
currently estimated at 25,000 tonnes in 2019. Production at Las
Cruces for 2020 has also been reduced by a further 25,000 tonnes
from amounts previously disclosed as certain high grade ore is no
longer planned to be mined as part of the open pit operation. The
open pit mining operations are expected to be completed in the
second half of 2020.
In terms of quarterly phasing of annual production, it is
expected that production at Zambian operations will be at its
lowest in the first quarter. The first and second quarters will
also be impacted by lower production at Las Cruces following the
land slippage.
The wet season in Zambia
generally starts in November and continues through April, with the
heaviest rainfall normally experienced in the months of December,
January, February and March. As a result of the wet season, pit
access and the ability to mine ore is lower in the first quarter of
the year than other quarters and the cost of mining is higher.
Cash costs and AISC guidance in the tables below does not
include any costs in respect of Cobre Panama.
Copper
|
2019
|
2020
|
2021
|
C13 (per
lb)
|
$1.20 -
$1.40
|
$1.20 -
$1.40
|
$1.20 -
$1.40
|
AISC3 (per
lb)
|
$1.70 -
$1.85
|
$1.70 -
$1.85
|
$1.70 -
$1.85
|
Increase in AISC guidance reflects higher Zambian royalty and
gold sales levy rates effective January 1,
2019. This has increased AISC by $0.05 per lb in all three years. It is expected
that a Zambian sales tax will be introduced from April 1, 2019, and that this will result in
increased C1 and AISC unit costs. However, guidance given excludes
the impact of the sales tax as the rate to be introduced has not
yet been confirmed by the Government of the Republic of
Zambia.
CONFERENCE CALL & WEBCAST
Conference call and webcast details are as follows:
Date:
|
February 15,
2019
|
Time:
|
9:00 am (EST); 2:00
pm (GMT); 6:00 am (PST)
|
Webcast:
|
www.first-quantum.com
|
|
|
Dial
in:
|
North America: (toll
free) (877) 291-4570
|
|
North America and
international: 1 (647) 788-4919
|
|
United Kingdom: (toll
free) 0-800-051-7107
|
|
|
Replay:
|
Available from noon
(EST) on February 15, 2019 until 11:59 pm (EST) on March 3,
2019.
|
|
North America: (toll
free) (800) 585-8367
|
|
North America and
international: 1 (416) 621-4642
|
|
|
Passcode:
|
5469795
|
COMPLETE FINANCIAL STATEMENTS AND MANAGEMENT'S DISCUSSION AND
ANALYSIS
The complete consolidated financial statements and Management's
Discussion and Analysis for the year ended December 31, 2018 are available at
www.first-quantum.com and should be read in conjunction with this
news release.
On Behalf of the Board of Directors of First Quantum Minerals
Ltd.
G. Clive
Newall
President
For further information visit our website at
www.first-quantum.com.
CAUTIONARY STATEMENT ON FORWARD-LOOKING INFORMATION
Certain statements and information herein, including all
statements that are not historical facts, contain forward-looking
statements and forward-looking information within the meaning of
applicable securities laws. The forward-looking statements include
estimates, forecasts and statements as to the Company's
expectations of production and sales volumes, and expected timing
of completion of project development at Cobre Panama and Enterprise
and are subject to the impact of ore grades on future production,
the potential of production disruptions (including at Cobre Las
Cruces as a result of the land slippage in January 2019), capital expenditure and mine
production costs, the outcome of mine permitting, other required
permitting, the outcome of legal proceedings which involve the
Company, information with respect to the future price of copper,
gold, nickel, zinc, pyrite, cobalt, iron and sulphuric acid,
estimated mineral reserves and mineral resources, First Quantum's
exploration and development program, estimated future expenses,
exploration and development capital requirements, the Company's
hedging policy, and goals and strategies. Often, but not always,
forward-looking statements or information can be identified by the
use of words such as "plans", "expects" or "does not expect", "is
expected", "budget", "scheduled", "estimates", "forecasts",
"intends", "anticipates" or "does not anticipate" or "believes" or
variations of such words and phrases or statements that certain
actions, events or results "may", "could", "would", "might" or
"will" be taken, occur or be achieved.
With respect to forward-looking statements and information
contained herein, the Company has made numerous assumptions
including among other things, assumptions about continuing
production at all operating facilities, the price of copper, gold,
nickel, zinc, pyrite, cobalt, iron and sulphuric acid, anticipated
costs and expenditures and the ability to achieve the Company's
goals. Forward-looking statements and information by their nature
are based on assumptions and involve known and unknown risks,
uncertainties and other factors which may cause the actual results,
performance or achievements, or industry results, to be materially
different from any future results, performance or achievements
expressed or implied by such forward-looking statements or
information. These factors include, but are not limited to, future
production volumes and costs, the temporary or permanent closure of
uneconomic operations, costs for inputs such as oil, power and
sulphur, political stability in Zambia, Peru,
Mauritania, Finland, Spain, Turkey, Panama, Argentina and Australia, adverse weather conditions in
Zambia, Finland, Spain, Turkey, Mauritania and Panama, labour disruptions, potential social
and environmental challenges, power supply, mechanical failures,
water supply, procurement and delivery of parts and supplies to the
operations, and the production of off-spec material.
See the Company's Annual Information Form for additional
information on risks, uncertainties and other factors relating to
the forward-looking statements and information. Although the
Company has attempted to identify factors that would cause actual
actions, events or results to differ materially from those
disclosed in the forward-looking statements or information, there
may be other factors that cause actual results, performances,
achievements or events not to be anticipated, estimated or
intended. Also, many of these factors are beyond First Quantum's
control. Accordingly, readers should not place undue reliance on
forward-looking statements or information. The Company undertakes
no obligation to reissue or update forward-looking statements or
information as a result of new information or events after the date
hereof except as may be required by law. All forward-looking
statements and information made herein are qualified by this
cautionary statement.
North American contact: Lisa
Doddridge, Director, Investor Relations, Tel: (416)
361-3752, Toll Free: 1 (888) 688-6577, E-Mail:
lisa.doddridge@fqml.com; United
Kingdom contact: Clive
Newall, President, Tel: +44 140 327 3484,
E-Mail: clive.newall@fqml.com